Hill Cutting Planning For Terminal Building and Pier Clearance

PART-A DRILLING REQUIREMENT EXPLOSIVE REQUIREMENT

Quantity in Nos of Drilling Drilling Drilling Mtrs / Nos of Machine/ Charge / Total Expl - Total Expl in
Blast No Bench No Location L B D Area DRL Pattern Nos of Hole Total IKON
Cum Holes Meterage Days Day Day Hole Kg Box

1 B1 RL-75-43 32 2500.00 80,000 15 10.5 238 7857 3 2250 15 238 233.17 55517 2221 238

2 B2 RL-105-78 65 40 27 2600.00 70,200 15 10.5 248 6933 3 2250 15 248 194.95 48273 1931 248

3 B2 RL-105-78 0.00 22,278 15 7.5 0 0 0 0 0 0 0.00 20050 802 0

4 swp-1 RL-20 -8 180 25 12 4500.00 54,000 15 7.5 600 7800 3 2250 15 600 80.27 48164 1927 0

5 swp-2 RL-20 -8 180 25 12 4500.00 54,000 15 7.5 600 7800 3 2250 15 600 80.27 48164 1927 0

6 B1 RL 43 - 20 180 28 23 5040.00 1,15,920 15 10.5 480 11520 5 2250 15 480 164.37 78896 3156 480

7 B2 RL-78-43 130 40 35 5200.00 1,82,000 15 10.5 495 17829 8 2250 15 495 256.11 126834 5073 495

8 B1 RL 20 - 08 215 28 12 6020.00 72,240 15 7.5 803 10435 5 2250 15 803 80.27 64432 2577 0

9 B2 RL-43-8 215 40 35 8600.00 3,01,000 20 10.5 819 29486 10 3000 20 819 256.11 209764 8391 819

Total A 9,51,638 28004 2280

12 RL 42-8 60 20 34 1200.00 40800 7 10.5 114 4000 4 1000 7 114 248.46 28396 1136 114

13 RL 42-8 60 20 34 1200.00 40800 8 10.5 114 4000 4 1000 7 114 248.46 28396 1136 114

Ramp 38000 7 1031

Total B 119600