Professional Documents
Culture Documents
Noida Twin Tower Demolition
Noida Twin Tower Demolition
PLANNING
N ANISHA
GAUREE
MOHIT
CONTENTS
INTRODUCTION
TIMELINE
THE RISE
THE CRACK
THE FALL
CONCLUSION
REFERENCES
INTRODUCTION
In the mid-2000s, Noida-based builder Supertech Limited
1. launched a housing project called Emerald Court.
In August 2021, the Supreme Court affirmed the Allahabad High Court's decision
and ordered the structures to be demolished, stating that they had been built in
violation of the regulations.
Many applications from homebuyers in favor of and against the Allahabad High
Court's decision led to the apex court's conclusion.
Authorities from Noida informed the Supreme Court in February 2022 that the
demolition work had started and was expected to be finished by May 22.
The Supertech Twin buildings' demolition deadline was, however, extended by the
top court to August 28.
The Supreme Court has stated that August 28 may be upheld as the date of
demolition, with a"bandwidth of seven days" between August 29 and September 4
to accommodate for any minor lag times caused by weather or technical
difficulties.
TECHNIQUES USED:
The Noida's Twin Towers were crushed through a 'CONTROLLED COLLAPSE MECHANISM',
and that implies Twin Towers collapsed after explosives were decisively positioned and
exploded with insignificant harm to the surrounding environment.
The cycle behind the collapse incorporates the continuous debilitating of basic backings
of the structure, i.e., eliminating the supports that assist the structure against the
gravitation.
This was accomplished by various explosives set inside the towers. Main supports of the
structure are the columns. Hence, most of the explosives were placing on the columns.
in lower floors, more explosive was placed than the upper floors to start the controlled
breakdown of the structure.
DEMOLITION PLAN
COMPANY:
Edifice engineering, a Mumbai based firm, partnered with South Africa's Jet carried out the
demolition work of Twin Tower.
PRODUCTS USED:
3700 kg of explosives were used to demolish the Twin Towers.
Tower-16 had eleven primary floors and Tower-17 had ten primary floors.
Explosives were put on the columns of all these primary floors. Whereas, 60% of the
explosives were planted on the columns of the secondary floor of Tower 16 and 17.
Electric detonators were used to trigger the explosives.
Entire process of blasting took only ten second.
ISSUES AFTER THE DEMOL
ALTH ITION
HE
The following health problems have been observed in nearby residents health
due to air pollution that occurred after the demolition of the Twin Towers of
Noida:
Mild to moderate headache.
Irritation in eyes, nose and skin occurred in most people.
Respiratory became a major issue and many residents in the vicinity
developed sore throat, runny nose, nasal congestion and cough.
Some patients had shortness of breath and their SPO2 level went to 92%.
Some patients reported fever and body aches.
Few cases of abdominal pain and nausea were reported.
CONCLUSION
https://www.slideshare.net/HarshSah4/twin-
tower-twistdocx
REFERENCES
https://www.sarallearningclasses.com/twin-tower-
noidas-demolition-a-complete-case-study/
https://www.indiatoday.in/interactive/immersive/superte
ch-noida-twin-tower-demolition-case-history-reason/
https://www.livemint.com/news/india/explained-
why-are-noida-twin-towers-being-demolished-
11661442579350.html
https://www.youtube.com/watch?v=CjMChBtFfcI
GLIMPSES
DEMOLISION OF
NOIDA'S
TWIN TOWER