Professional Documents
Culture Documents
Untitled
Untitled
Table of Contents
1. INTRODUCTION ...................................................................................................................... 1
1.1 General ...................................................................................................................................... 1
1.2 Scope of the work and project area ........................................................................................... 1
1.2.1 Scope of the work .................................................................................................................. 1
1.2.2 Location and Accessibility of the area ................................................................................... 1
1.2.3 Geology of the area ................................................................................................................ 2
2. objective of the work .................................................................................................................. 3
3. Methodology of the Drilling ....................................................................................................... 3
4. Man power, Equipment and materials used ................................................................................ 4
4.1 Man Power ................................................................................................................................ 4
4.2 Equipment and Materials Used ................................................................................................. 4
5. drilling and construction history of the well ............................................................................... 5
5.1 Drilling ...................................................................................................................................... 5
5.2 DRILLING DIAMETER .......................................................................................................... 5
6. WELL DESIGN AND CONSTRUCTION ................................................................................ 5
6.1 ROCK SAMPLING .................................................................................................................. 5
6.2 LITHILOGICAL LOGGING ................................................................................................... 5
6.3 CASING ARRANGMENT AND WELL DESIGN ................................................................. 6
6.4 SURFACE CASING AND OBSERVATION PIPE................................................................. 9
6.5 GRAVEL PACKING................................................................................................................ 9
6.6 WELL DEVELOPMENT AND CLEANING .......................................................................... 9
6.7 WELL HEAD CONSTRUCTION ........................................................................................... 9
7. SUMMARY .............................................................................................................................. 10
8. PUMPING TEST DATA COLLECTION AND ANALYSIS ................................................. 11
8.1 OBJECTIVE OF THE PUMPING TEST ............................................................................... 11
8.2 Pumping Test Instruments and Equipment ........................................................................ 11
8.3 PUMPING TEST ............................................................................................................... 12
8.3.1 PUMPING TEST DATA COLLECTION AND ANALYSIS ....................................... 12
8.3.3 CONSTANT RATE DRAWDOWN TEST ................................................................... 12
CONCLUSION AND RECOMMEDNDATION ......................................................................... 20
9. Water quality............................................................................................................................. 22
9.1 Sampling method .................................................................................................................... 22
9.2 Measures of Groundwater Quality and Evaluation ................................................................. 22
9.2.1 Physical analysis .................................................................................................................. 22
9.2.2 Chemical Analysis ............................................................................................................... 23
9.2.3 PH ........................................................................................................................................ 23
9.2.4 Total hardness ...................................................................................................................... 23
9.2.5 Total Dissolved Solids (TDS) and Electrical Conductivity (EC) ........................................ 23
9.3 Presentation and Interpretation ............................................................................................... 24
9.3.1 Pie chart ............................................................................................................................... 24
1. INTRODUCTION
1.1 GENERAL
An agreement was made between International Rescue Committee (IRC) and Zekalay General
Trading PLC on Augest 23, 2018. The objective of the agreement was to drill, construct and
make a pumping test of Four (4) bore hole in Benishangul Gumuz regional state of Bambasi,
Tango and Tsore Refugee camp.
The drilling and related works of this well are completed as per the agreement & specification
and the completion report is presented here. In addition to the work activities included in the
BOQ, this report presents the location and accessibility, Methodology, Geology and
Hydrogeology of the area, Borehole hydrogeology, and the machinery and equipment used to
conduct the drilling of the wells.
The drilling of the borehole was completed at 115-meter depth based on the agreement in order
to fully penetrate the aquifer and the drilling technique applied was DTH System. And the whole
drilled depth is covered by production casing of 6 inch inside diameter PVC casing.
The project area is located in Assosa zone of the regional state Benishangul Gumuz. The
administrative town Assosa is located at about 675km far from Addis Ababa (the capital city of
Ethiopia). It is accessible through Addis Ababa, Ambo, Nekemt, Gimbi and Assosa main asphalt
road. The site is accessible 57km far from Assosa town on the way to Bambasi woreda and it is
accessible with asphalt road except the road to the site is only dry weather.
Detail location information of the site well is listed in the table below
S.N Zone Woreda Kebelle Site name (UTM) (UTM) northing Altitude
easting (m)
1 Assosa Bambasi Womba Bambasi refugee - - -
camp
The major suture zone in the Southern Arabian–Nubian Shield has an oceanic affinity,
containing sutures of meta‐sediments of deep‐sea marine sedimentary origins (trench sediments),
volcanic rocks of calc‐alkaline (island‐arc) origin and fragments of mafic to ultramafic rocks
(ophiolites) of oceanic crustal origin. The sutures of former oceanic areas that have accreted to
form the Arabian–Nubian Shield consist of linear schist belts, containing phyllitic to greenschist
facies meta‐sediments and meta‐volcanics. The sutures in the accreted shield areas are the loci
for major shear zones that commonly host gold deposits. The regional structural set‐up of the
western Ethiopian shield is shown by three phases of deformation‐associated foliations, folding
and lineations. The Asosa region is represented by the Kuluck shear zone. The area is also
characterised by syn‐ and post‐kinematic Neoproterozoic granitoid intrusions, Tertiary basalts
and a lateritic cover (extensive over basaltic lavas). Important gold mineralization zones are
hosted within quartz veins, schist units (amphibolite schist, quartz graphitic schist and quartzo‐
feldspathic sericite schist) and granitic gneiss. The ANS mineralization is dominated by orogenic
gold, tantalum, niobium, tungsten, rare earth elements, uranium and tin.
The local geology of the area is covered by top soil at its top part and highly weathered and
fractured quartz dike deposit which is the most aquifer part of the well, developed from primary
porosity and permeability through direct recharge, and basalt formation is under laid started at
about 7.5m depth.
Mobilization of drilling rig, manpower, equipment and materials for drilling and
construction
Site hand over from the representative
Site clearing and mud pit excavation
Borehole drilling, lithological & electrical logging
Installation of 12" steel surface casing
Installation of PVC production casing of 6" ID
Installation of 3/4" GI observation pipe
Supply & pack river gravel
T ABLE 2: - M AN P OWER
Drilling rig (drilling Rig with Mud Pump, Foam Pump, and Air Compressor (Atlas Copco,
with maximum capacity of 21 bars), Isuzu Truck & Toyota light vehicles (Double Gabion).
The Rig is completely hydraulic with the maximum pull up of 18 tones.
14" tungsten carbide inserted bit
14 1/4" hammer bit
Generator for welding and cutting
12" steel surface casing and 6" PVC production casing
10" & 12" different type of Drilling bits
Other many accessory tools/equipment’s necessary for drilling
DTH/MUD System was applied in order to drill 115meter depth. The upper surface of the well to
5-meter depth with 14-inch diameter bit. From 6-meter depth to 115meter depth, the well was
drilled and completed using DTH/MUD with 10-inch diameter bit.
The total drilled depth of the well is 115 meter and the whole depth is cased. The installed casing
is 6-inch internal diameter PVC casing. A total of 115.8m has cased including the stick-up length
as shown in the table below.
Casing Arrangement
From To Length (m) Remark
7. SUMMARY
Well Name Assosa IRC BH#2
GPS Location -
Drilling method DTH/MUD
Drilling diameter 12 inch for surface casing and 6 inch for production casing
Drilled depth 115m
Cased Depth Blind 81.60m with stick up (0.8m)
Screen 34.20m
105m
Well head type Trapezoidal
Well status Productive
Welding Machine
Tri pole with 5 tone chain block to install the submersible pump.
Isuzu truck for mobilization and Demobilization
Kitchen materials
The constant pumping test is carried out after the water level of the well has returned to almost
the normal static water level right after the last step drawdown test. The discharge rate for the
constant pumping test is fixed based on the result of the successive step drawdown tests. During
the constant rate test, the fixed discharge rate is maintained throughout the pumping period.
Close follow up on the discharge measuring device was also made to maintain and control the
fixed discharge rate. Duration for constant test is 24 hours for this well. At the end of the
duration the well almost maintained equilibrium position.
The water level measurements are taken at frequent time intervals during the early stage and
relatively large interval during the later stage.
T ABLE 6: - T IME INTERVALS SET FOR THE CONSTANT RATE DRAWDOWN TEST
Usually the sustainable discharging rate (Safe yield) of a well is determined from the constant
pumping test. It is obvious that the optimum yield of a well is controlled by the available
drawdown and the specific capacity.
Womba Well
Constant test for this well is conducted for 24 hours at the constant discharge rate of 6.5 l/sec
(.561.60m3/day) and the static water level was 2.50m and the pumping water level (dynamic
water level) after 24 hours discharge at the specified yield is 36.47m and at this point it doesn’t
reach the equilibrium level, it was not lowering down. Hence, we have approximately
extrapolated to get the equilibrium position. Thus by extrapolating and estimating the total
drawdown is 33.97m + 5.0m (extrapolated) = 38.97m. This well is only 24 hrs pumping duration
is conducted to estimate the total DD. But it is known that the 24 hrs pumping duration is the
minimum require to estimating the DD for long duration pumping test. Thus; the specific
capacity of the well = constant discharge rate (m3/day)/total drawdown = 561.60m3/d/38.97m=
14.41m2.
Being the aquifer is unconfined we can take 60% up to 80% of the section from the static water
level up to the pump position as available drawdown. In this case SWL (2.50m) up to the pump
position (105m) is 102.50m thick, and from this section 57m thick is water bearing (aquifer). The
105m pump position is not selected B/c at this depth the casing is Screen; then, the 96m pump
position is selected B/c at this depth the casing arrangement from 94.05m – 99.75m is Blind and
there is enough section below this depth up to the final depth of 115m to accommodate siltation
for long time.
Being the aquifer almost unconfined we take 70% this value as available draw down. Thus; the
available drawdown for this well is 57m*0.70 = 39. 90m.Thus; maximum yield of the well =
available drawdown * specific capacity of the well = 39.90m*14.41m2/d =574.96m3/d (6.65.01
l/sec). So the safe yield = 574.96 m3/d * 0.70(safe factor) = 402.47m3/d = 4.66 l/sec.
Hence the well is safe to be pumped up to 4.66 l/sec; the amount of the water to be pumped up to
this yield is depending on the intended purpose and the required amount. The recommended
pump position is around 96m because at this depth the casing is blind and there is enough section
below this depth up to the final depth of 115 m to accommodate siltation for long time.
RECOVERY TEST
Recovery test for the well is conducted with the main objectives to understand the recovery
capacity of the well. The test is conducted assuming that after the pump has been shut down, the
well pumped at the same discharge as the constant test.
During the analysis of the pumping test data, the drilling log data is basically used to identify
the type and nature of aquifer. According to the close observation of the log data, static water
level and water strike of the well reveal that the major aquifer of the well has unconfined
nature. From the constant test the value of safe yield and maximum yield are calculated and
the summarized values are tabulated above.
The constant discharge rate of this well is also determined based on the result of the step tests
and the actual finding of the wells.
The specific capacity and safe yield of the well is also calculated from the constant rate test.
Based on the results of the analysis, the pump position and pumping duration of the well is
determined.
The recommended pump position and pumping duration of the well is summarized in the table
below.
For sustainable and efficient use, there must be sufficient time gap between the recharge
and discharge period. As a result, the pumping duration of the well should not exceed
from the recommended period. Since the well has fast recovery means high recharge can
be pumped for longer time per day.
For the efficient and sustainable use of the well, continuous monitoring and evaluation of
the groundwater in and around the well should be carried out. Hence it is important to
establish a long term systematic measurements of water levels from observation or
production well that well provide essential data needed to evaluate fluctuations in the
groundwater resource.
For long time siltation is expected, so rehabilitation work is recommended every 5 years
or less
9. WATER QUALITY
Quality of water depends upon quality and quantity of inorganic and organic compounds present
in water. During its traverse water picks up impurities in varying amounts; Gases from
atmosphere, inorganic and organic salts from top soil and geological strata. And also, water gets
contaminated by inorganic and organic salts sometimes beyond desirable limits.
Of the various parameters in potable water few are objectionable even when present in
very small quantity
Others if only present in unusual quantities as to relegate the water from the potable to
the unusable class
9.2.3 PH
The balance of positive hydrogen ions (H+) and negative hydroxide ions (OH-) in the water
determines how acidic or basic the water is. The pH scale ranges from 0 (high concentration of
positive hydrogen ions, strongly acidic) to 14 (high concentration of negative hydroxide ions,
strongly basic). In pure water, the concentration of positive hydrogen ions is in equilibrium with
the concentration of negative hydroxide ions, and the pH measures exactly 7. Drinking water
with a pH value of between 6.5 and 8.5 is generally considered as satisfactory. In this specific
water well the pH value is 7.51 which is found in acceptable range for domestic use.
The degree of hardness of the water is classified in terms of its calcium carbonate concentration
(after Sawyer and McCarty, 1967). The laboratory analysis indicates that the total hardness value
is 224.67mg/l (CaCO3). These values indicate that the sample from the borehole is soft water.
The WHO maximum allowable concentration is 500 mg/l (CaCO 3).
The presences of all these chemical constituents give water the ability to conduct electricity.
Thus, the electrical conductivity (EC) of water is an indirect measure of its dissolved
constituents. In practice, EC is often expressed in terms of mili Siemens (ms) and micro
Siemens. The TDS and the EC are in a close connection. The more salts are dissolved in the
water; the higher is the value of the electric conductivity.
This specific water sample has a Total Dissolved Solid (TDS) value of 361.55 (mg/l) and
Electrical conductivity (EC) value of 507 (μS/cm).
5%
Na
24%
43% Ca
Mg
2% 4% Cl
22%
So4
Hco3
F IGURE 3. P IE CHART