METODE PELAKSANAAN PEKERJAAN

PEKERJAAN : Pengadaan dan Pemasangan Lift


PROYEK : Pembangunan HOTEL HOLIDAY INN EXPRESS

PEMELIHARAAN /
NO. PEKERJAAN PERSIAPAN PELAKSANAAN GAMBAR / SKETSA
PEMBERSIHAN

1 ELEVATOR Design Elevator Fabricate Finishing & Cleaning -


Prepare Spec of Elevator ON SITE Free Maintenance, selama 12 bulan
Approval Specification Installations Bracket Wall
Site Preparation Installations Bracket Main Rail
Centering Hoistway Installations Bracket Counter weight
Installations Main Rail
Installations Counter Weight Rail
Installations Door Sill
Installations Jamb
Installations Machine & Control Panel
Assembling Car
Installations Landing Device
Installations Doors
Installations Push Button & Indicator
Installations Door Operator
Installations Counterweight
Installations Wiring Cable
Installations Bracket Wall
Testing & Commissioning