Provisional Site Acceptance Checklist: Contractor's Representative Unity Digital Infrastructure
Provisional Site Acceptance Checklist: Contractor's Representative Unity Digital Infrastructure
v20210518
Project - Phase: Date of Inspection:
Unity Site ID: Customer ID: Site Type: Tower Model:
Site Address: Green Field
Contractor: Roof Top
CW-A 1.2 Minor Excess soil from excavation has either been removed or landscaped
property
CW-A 1.3 Minor Site is free from trip hazards
Resurfacing / restoration of damaged properties where applicable for
CW-A 1.4 Minor both GF and RF site
CW-A 1.8 Minor Access road restored to a state equal to or better than the initial
condition. Vehicles are able to pass easily
CW-A 2.0 Records & Documents
CW-A 2.1 Minor Redline Drawing sign-off by Contractor and Unity during site visit
Concrete cube test passed for 7,14,28 days verified by Unity during
CW-A 2.2 Major site visit
CW-A 3.0 Earthworks
CW-A 3.1 Minor Grading and levelling as indicated according to approved DDD
CW-A 3.2 Minor Crushed rock gravel surfacing 100mm thk with geotextile membrane;
random location to be checked
CW-A 3.3 Major Site is free from soil settlement
CW-A 3.4 Major Final site elevation according to approved DDD
CW-A 3.5 Minor Access road construction 3m wide according to approved DDD
CW-A 3.6 Minor Access road length according to approved DDD
CW-A 4.0 Site Final Clean
CW-A 4.1 Minor General Cleaning (inside compound)
CW-A 4.2 Minor General Cleaning (outside compound within Lease area)
CW-A 5.0 Fence
CW-A 5.1 Minor 3 strand galvanized barbed; check quality, connections and tension of
wires
CW-A 5.2 Minor Gate installed properly according to approved DDD
CW-A 5.3 Minor Barrel bolt and lock plates properly installed according to approved
DDD
CW-A 5.4 Minor Gate hinges installed correctly and welded to column rebars
CW-A 5.5 Minor Footbolts installed correctly on both gate opening
CW-A 5.6 Minor Footbolt catcher installed correctly according to approved DDD
CW-A 5.7 Minor Mesh wire of approved type and installed according to approved DDD
CW-A 5.8 Minor Fence is aligned, plumb, secure and correct tension
CW-A 5.9 Minor Secuirty bolts installed with bolt head on the outside and tightened
CW-A 5.10 Minor Fence materials sizes according to approved DDD
CW-A 5.11 Minor Fence materials are hot dip galvanized
Minor Concrete
tapping of top CHB done correctly according to approved
CW-A 5.12 DDD
CW-A 5.13 Minor CHB construction joints plastered and tidy
CW-A 5.14 Minor Weep holes installed according to approved DDD; 2 pcs per span
CW-A 5.15 Minor concrete columns done correctly
CW-A 5.16 Minor CHB wall plastered smooth on both sides
Minor Padlock
of approved type; provide key handover form signed by Unity
CW-A 5.17 during site visit
CW-A 5.18 Minor Perimeter fence ligthing installed correctly; check functionality
1 of 7
PROVISIONAL SITE ACCEPTANCE CHECKLIST
v20210518
Project - Phase: Date of Inspection:
Unity Site ID: Customer ID: Site Type: Tower Model:
Site Address: Green Field
Contractor: Roof Top
CW-A 7.9 Major TEST: random torque check per tower sections; refer to separate
inspection sheet approved by Unity on site
TEST: Verticality, tolerance 1:500; refer to separate inspection sheet
CW-A 7.10 Major
approved by Unity on site
CW-A 7.11 Major No missing bolts/Nuts/flat washers/spring washers/lock nuts
CW-A 7.12 Major Bolts correct size and grade 8.8; no visible corrosion
CW-A 7.13 Major Protrusion above nut shall be minimum 2 full threads
CW-A 7.14 Major Bolts installed have correct sizes as per erection drawing
CW-A 7.15 Major No misaligned bolt holes and slotted holes
CW-A 8.5 Major Wires/cables of approved type and correct size as per approved SLD
CW-A 8.9 Major Circuit breakers of approved type and capacity as per approved SLD
CW-A 8.10 Major Circuit breakers are labelled according to the approved SLD
2 of 7
PROVISIONAL SITE ACCEPTANCE CHECKLIST
v20210518
Project - Phase: Date of Inspection:
Unity Site ID: Customer ID: Site Type: Tower Model:
Site Address: Green Field
Contractor: Roof Top
CW-A 8.12 Minor Conduits of approved type and properly installed with metal clamps
CW-A 8.14 Major Service entrance wires and conduits properly fix, sealed and secured;
provide adequate drip loop at entrance cap
CW-A 8.15 Minor Provide protective grill for KHh meter with padlock; if installed at
service entrance pedestal
CW-A 8.16 Major Panel boards grounded to the main busbar
3 of 7
PROVISIONAL SITE ACCEPTANCE CHECKLIST
v20210518
Project - Phase: Date of Inspection:
Unity Site ID: Customer ID: Site Type: Tower Model:
Site Address: Green Field
Contractor: Roof Top
CW-A 10.1 Minor Site Identification and warning board fitted to approached side of site
CW-A 10.2 Minor signage connected using stainless cable or proper clip approved by
Unity
CW-A 10.3 Minor Site identification clearly indicate the Unity Site ID
CW-A 10.4 Minor Signage supplied by the contractor indicates the Burmese and English
wordings on each signage
CW-A 10.5 Minor Supplied signage not fading or discoloration
CW-B BRACKET AND ACCESORIES INSTALLATIONS
CW-B 1.0 Bracket Installations
CW-B 1.1 Major RF and MW brackets installed at correct height
HS-A 2.4 Minor Management waste in site (such as: temporary bin / separated area
for temporary waste)
HS-A 2.5 Minor Housekeeping for camp of contractor's employee
HS-A 2.6 Minor Hygiene for meal of contractor's employee
4 of 7
PROVISIONAL SITE ACCEPTANCE CHECKLIST
v20210518
Project - Phase: Date of Inspection:
Unity Site ID: Customer ID: Site Type: Tower Model:
Site Address: Green Field
Contractor: Roof Top
HS-A 4.1 Major Competent personnel's; there should be a foreman who supervised
the work and the implementation of the HSE on the site
HS-A 4.2 Major No workers under age
HS-A 4.3 Major There is no people smoking in site area and no cigarrete butts
If rain condition, there is no working employee for tower erection,
HS-A 4.4 Major electricity activity, etc. (If the condition is no rain, please interview
with the employee if possible)
There is no beer and drugs consumption by the workers and found no
HS-A 4.5 Minor
liquor cans on site
HS-A 4.6 Minor Padlock and keys when applicable
HS-A 5.0 Waste Management
HS-A 5.1 Major Flammable Material Sign and No Smoking Sign properly attached (If
there is permanent generator)
Material Safety Data Sheet (MSDS) for generator fuel and oil(s) are
HS-A 5.2 Minor available and attached to permanent generator body
HS-A 5.3 Major There is no leakage or spill of generator fuel/oil found on site
HS-A 5.4 Minor Locked Generator (If there is permanent generator)
HS-A 5.5 Minor There is any secondary containment for fuel tank with 110% capacity
(if there is permanent generator)
HS-A 5.6 Minor Is there any used oil temporarily stored around site area?
HS-A 5.9 Major Spill kit available during maintenance supply by vendor such as
sawdust
5 of 7
PUNCHLIST
v20210518
Item Deficiency Description BEFORE - Deficiency Photo AFTER - Rectification Photo Pass / Fail Remarks
(same angle)