Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

BKHP Constru

Elemental Costs Pr

PROJECT NO
PROJECT NAME

Cost Centre Activity Intial Price ($)


1 TOTAL PRELIMINARIES TO SUMMARY
2 TOTAL GROUNDWORKS TO SUMMARY
3 TOTAL CONCRETOR TO SUMMARY
4 TOTAL BRICKWORK TO SUMMARY
5 TOTAL CARPENTRY TO SUMMARY
6 TOTAL JOINERY TO SUMMARY
7 TOTAL WINDOWS TO SUMMARY
8 TOTAL GARAGE DOORS TO SUMMARY
9 DOMESTIC HARDWARE TO ALL DOORS
10 TOTAL ROOFING TO SUMMARY
12 TOTAL PLASTERING TO SUMMARY
13 TOTAL TILING TO SUMMARY
14 TOTAL FLOOR FINISHES TO SUMMARY
15 TOTAL GLAZING TO SUMMARY
16 TOTAL PAINITING TO SUMMARY
17 TOTAL PLUMBING TO SUMMARY
18 TOTAL ELECTRICAL TO SUMMARY
19 TOTAL PC ITEMS TO SUMMARY
20 TOTAL MISCELLANEOUS TO SUMMARY
21 TOTAL METAL WORK TO SUMMARY
BKHP Constructions
Elemental Costs Preparation

1 Contract Sum Go to Main


XXXX Menu
Kai McJannett 20566584

Variation ($) Actual Cost ($) Profit (%) Profit ($) Bonus ($)
108% $0 10.9% $0.00 $0.00
90% $0 7.3% $0.00 $0.00
110% $0 11.3% $0.00 $0.00
109% $0 5.8% $0.00 $0.00
85% $0 10.8% $0.00 $0.00
104% $0 10.7% $0.00 $0.00
93% $0 5.6% $0.00 $0.00
86% $0 11.1% $0.00 $0.00
104% $0 8.1% $0.00 $0.00
91% $0 5.9% $0.00 $0.00
105% $0 11.3% $0.00 $0.00
106% $0 11.8% $0.00 $0.00
96% $0 6.4% $0.00 $0.00
96% $0 8.7% $0.00 $0.00
95% $0 11.7% $0.00 $0.00
91% $0 6.1% $0.00 $0.00
90% $0 6.5% $0.00 $0.00
111% $0 5.6% $0.00 $0.00
102% $0 9.0% $0.00 $0.00
93% $0 9.7% $0.00 $0.00
Go to Main
Menu

Net Profit
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
BKHP Constructions
VARIATION
PROJECT NO 1
PROJECT NAME XXXX
Cost centre Description Intial Price
100 TOTAL PRELIMINARIES TO SUMMARY
200 TOTAL GROUNDWORKS TO SUMMARY
300 TOTAL CONCRETOR TO SUMMARY
400 TOTAL BRICKWORK TO SUMMARY
500 TOTAL CARPENTRY TO SUMMARY
600 TOTAL JOINERY TO SUMMARY
700 TOTAL WINDOWS TO SUMMARY
800 TOTAL GARAGE DOORS TO SUMMARY
900 DOMESTIC HARDWARE TO ALL DOORS
1000 TOTAL ROOFING TO SUMMARY
1100 TOTAL PLASTERING TO SUMMARY
1200 TOTAL TILING TO SUMMARY
1300 TOTAL FLOOR FINISHES TO SUMMARY
1400 TOTAL GLAZING TO SUMMARY
1500 TOTAL PAINITING TO SUMMARY
1600 TOTAL PLUMBING TO SUMMARY
1700 TOTAL ELECTRICAL TO SUMMARY
1800 TOTAL PC ITEMS TO SUMMARY
1900 TOTAL MISCELLANEOUS TO SUMMARY
2000 TOTAL METAL WORK TO SUMMARY
2100 TOTAL 0
ions

Kai McJannett 20566584


Variation Actual Cost
89% $0
94% $0
114% $0
104% $0
104% $0
107% $0
91% $0
111% $0
89% $0
86% $0
101% $0
89% $0
97% $0
89% $0
104% $0
87% $0
98% $0
91% $0
107% $0
102% $0
91% 0

You might also like