Contract ID: 22OI0124

Contract Name: Rehabilitation of Road and Drainage System

Location of the Contract: Brgy. Talon 3, Las Piñas City

CASH FLOW BY QUARTER

Particular Total 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Accomplishment in % 100% 30% 30% 20% 20%
Cash Flow in PHP 748,184.82 748,184.82 498,789.88 498,789.88
Cumulative Accomplishment in % 100% 30% 60% 80% 100%
Cumulative Cash Flow in PHP 748,184.82 1,496,369.64 1,995,159.52 2,493,949.40

PAYMENT SCHEDULE

Payment Milestone Payment (%) Amount (PHP)


Mobilization and Start of Construction 10% 249,394.94
Completion of Foundation 20% 498,789.88
Completion of Structural Framework 20% 498,789.88
Completion of Building Envelope 20% 498,789.88
Completion of Interior Finishes 20% 498,789.88
Substantial Completion and Punch-list Items 10% 249,394.94
Total 100% 2,493,949.40

Submitted by:

MARK AERON OCOP

Name and Signature of Bidder’s Authorized Representative Date: April 20, 2023

JUAN DELA CRUZ

position

JUSTIN LLOYD ELMIDO

Name of Bidder