Project Schedule: 24-Apr-23 16-May-23
Project Schedule: 24-Apr-23 16-May-23
Project schedule
PERIODS
10-May-23
11-May-23
12-May-23
13-May-23
14-May-23
15-May-23
16-May-23
24-Apr-23
25-Apr-23
26-Apr-23
27-Apr-23
28-Apr-23
29-Apr-23
30-Apr-23
1-May-23
2-May-23
3-May-23
4-May-23
5-May-23
6-May-23
7-May-23
8-May-23
9-May-23
Task
ID Items Duration DIDx Start Date Finish Date
1 Excavate slab hole 8 hours 1 24-Apr-23 24-Apr-23
2 Install wooden forms around the excavated slab hole 2 hours 2 25-Apr-23 25-Apr-23
3 Pour base course or gravel, and compact 4 hours 3 25-Apr-23 25-Apr-23
4 Place reinforcing mesh 8 hours 4 26-Apr-23 26-Apr-23
5 Pour and cure concrete 10 hours 5 27-Apr-23 28-Apr-23
6 Assembly metal frame 16 hours 6 1-May-23 2-May-23
7 Assembly electric system 8 hours 7 3-May-23 3-May-23
8 Assembly colorbond Sheets for the roof 6 hours 8 4-May-23 4-May-23
9 Assembly roof gutter 4 hours 9 5-May-23 5-May-23
10 10