- Critical Path - Non Critical Path DIDx - Predecessors' ID

Project schedule

PROJECT START DATE 24-Apr-23 TODAY DATE 16-May-23


### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

PERIODS

10-May-23

11-May-23

12-May-23

13-May-23

14-May-23

15-May-23

16-May-23
24-Apr-23

25-Apr-23

26-Apr-23

27-Apr-23

28-Apr-23

29-Apr-23

30-Apr-23

1-May-23

2-May-23

3-May-23

4-May-23

5-May-23

6-May-23

7-May-23

8-May-23

9-May-23
Task
ID Items Duration DIDx Start Date Finish Date
1 Excavate slab hole 8 hours 1 24-Apr-23 24-Apr-23
2 Install wooden forms around the excavated slab hole 2 hours 2 25-Apr-23 25-Apr-23
3 Pour base course or gravel, and compact 4 hours 3 25-Apr-23 25-Apr-23
4 Place reinforcing mesh 8 hours 4 26-Apr-23 26-Apr-23
5 Pour and cure concrete 10 hours 5 27-Apr-23 28-Apr-23
6 Assembly metal frame 16 hours 6 1-May-23 2-May-23
7 Assembly electric system 8 hours 7 3-May-23 3-May-23
8 Assembly colorbond Sheets for the roof 6 hours 8 4-May-23 4-May-23
9 Assembly roof gutter 4 hours 9 5-May-23 5-May-23
10 10