CALCULATIONS OF
BRIDGE AT KM 4+950
Hydraulic Calculation For Minor Bridge
Hydraulic calculation of Marpalli-Mutukpalli-Regulwahi-Muduwahi To Join Road at Ch. 4+950 M
1) Proposal :- 2 x 8.0m
Topographical Details :
1 Catchment Area (Provided)3 x 10.0 m 11.11 Km2
2 Bed Width at proposed section 12.00 m
3 Bank Width at proposed section 20.00 m
4 Location of Defined section 0.0 m U/S
5 Bed Width at Defined section 10.00 m
6 Bank Width at Defined section 17.00 m
4 L.B.L at Proposed Section 86.385 m
8 L.B.L at Defined Section 86.385 m
5 Slope 0.0020
6 Hydraulic Gradient 1 IN 493.695
It receives an annual rainfall of about 1,000 mm (39 in), almost entirely from monsoon
rains between June and September.
A1 = 17.12 P 1= 40.04
Compartment II
Ground Obsreved Depth of Mean Wetted Wetted
Chainage Length Diff. in G.L.
level H.F.L. Water Depth of Area Perimeter
A2 = 0.00 P 2= 0.000
Compartment III
Ground Obsreved Depth of Mean Wetted Wetted
Chainage Length Diff. in G.L.
level H.F.L. Water Depth of Area Perimeter
A3 = 5.35 P3 = 20.109
89.000
88.500
88.000
87.500
GL
87.000 HFL
86.500
86.000
85.500
85.000
-50 -40 -30 -20 -10 -5 0 5 10 20 30 40 50
Hydraulic Calculation For Minor Bridge
Hydraulic calculation of Marpalli-Mutukpalli-Regulwahi-Muduwahi To Join Road at Ch. 4+950 M
Bed = Clean, straight bank, full stage, no rifts or deep pools but some weeds and stone ( Fair )
Bank = Winding,some pools and shoals.clean, some weeds and stones ( Fair )
Rugosity Coefficient 0.035 0.035 0.035
Compartment II I III
Wetted Area m2 0.000 17.125 5.350 22.5
Wetted
m 0.000 40.035 20.109 60.144
Perimeter
Hydraulic
m 0.000 0.428 0.266
Mean Depth
Bed Slope 0.0020 0.0020 0.0020
According to SP-13 Maximum discharge from [A] & [B] is to be considered as designed discharge. Provided it should
not exceed the next highest by more than 50%., if it does, restrict it to that limit
50% increased Discharge is (66.939+(66.939/2)) = 100.408 m3/sec
P1 AR
AL
89.000
88.000
87.000
86.000
85.000
-50 -40 -30 -20 -10 -5 0 5 10 20 30 40 50
A1 = 50.43 P1 = 40.04
Compartment II
Ground Depth of Mean Wetted Wetted
Chainage H.F.L. Length Diff. in G.L.
level Water Depth of Area Perimeter
A2 = 5.60 P2 = 30.033
Compartment III
Ground Depth of Mean Wetted Wetted
Chainage H.F.L. Length Diff. in G.L.
level Water Depth of Area Perimeter
A3 = 18.46 P3 = 20.109
Compartment II I III
The discharge calculated by mannings formula is fairly tallied with the Final 0.00%
design discharge i.e.which is within the permissble limit of 2%.
Width
Member Chainage GL HFL Ht of water
Top At HFL At GL
x of HFL & GL -13.000 Average ht= 0.589
AL -8.000 86.796 87.974 1.178 0.900 0.900 0.900
P1 0.000 86.385 87.974 1.589 0.900 0.900 0.900
AR 8.000 86.496 87.974 1.478 0.900 0.900 0.900
x of HFL & GL 12.000 Average ht= 0.739
RTL 89.633
Clearance
LBL 86.385
Foundation
Level
Note :
1. While working out the value of Db , the discharge has been increased by 30% as per clause 703.1.1 of IRC-78-2014.
Annexure-I
2
Afflux = V2 + 0.015 { ( A / A1 ) -1}
17.88
Where,
V = Mean Velocity = 1.04 m/sec
A = Unobstructed = 74.49 Sq m.
Sectional Area of River
A1 = Sectional Area of = 64.77 Sq m.
River At Obstruction
Afflux = 0.025 mtr. <0.60 m Hence OK.
Hydraulic Calculation For Minor Bridge
Hydraulic calculation of Marpalli-Mutukpalli-Regulwahi-Muduwahi To Join Road at Ch. 4+950 M
50 0 89.040
Hydraulic Calculation For Minor Bridge
Hydraulic calculation of Marpalli-Mutukpalli-Regulwahi-Muduwahi To Join Road at Ch. 4+950 M
L- section
-300 0 85.8
-270 0 85.86
-240 0 85.92
-210 0 85.97
-180 0 86.04
-150 0 86.12
-120 0 86.17
-90 0 86.21
-60 0 86.28
-30 0 86.32
0 0 86.385
30 0 86.42
60 0 86.49
90 0 86.57
120 0 86.62
150 0 86.7
180 0 86.77
210 0 86.82
240 0 86.93
270 0 86.98
300 0 87
0.002026
1 IN 493.6952
y = 0.0020x + 86.3988
87.2
87
86.8
86.6
86.4
86.2
86
85.8
85.6
-400 -300 -200 -100 0 100 200 300 400
Hydraulic Calculation For Minor Bridge
Hydraulic calculation of Marpalli-Mutukpalli-Regulwahi-Muduwahi To Join Road