Material Requirement Planning

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

1.

Prepare a material requirements plan for component J

LEVEL 1

BV( E
LEVEL 2 B (2) J (3)

LEVEL 3 J (4) F (3)

Master Week Beginning 1 2 3 4 5 6


Schedule Quantity             80

E LT = 2 Beg. Inv. 1 2 3 4 5 6
Gross requiements             80
Schedules receipts              
Projected on hand              
Net requirements             80
Planned order receipts             80
Planned order releases         80    

B (2) LT = 2 Beg. Inv. 1 2 3 4 5 6


Gross requiements         160    
Schedules receipts              
Projected on hand 60 60 60 60 60 20 20
Net requirements         100   80
Planned order receipts         120   80
Planned order releases     120        

J (4) AND J (3) LT = 1 Beg. Inv. 1 2 3 4 5 6


Gross requiements     480   240    
Schedules receipts       30 30 30  
Projected on hand 20 20 20 50 80 50 50
Net requirements     460   160    
Planned order receipts     480   180    
Planned order releases   480   180      
2. Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned order releases
through week 3 have all been executed. How many more B’s and J’s will be on hand in week 6.

LEVEL 1

E
LEVEL 2 B (2) J (3)

LEVEL 3 F (3)
J (4)

Master Week Beginning 1 2 3 4 5 6


Schedule Quantity             70

E LT = 2 Beg. Inv. 1 2 3 4 5 6
Gross requiements             70
Schedules receipts              
Projected on hand              
Net requirements             70
Planned order receipts             70
Planned order releases         70    

B (2) LT = 2 Beg. Inv. 1 2 3 4 5 6


Gross requiements         160    
Schedules receipts              
Projected on hand 60 60 60 60 60 20 20
Net requirements         80    
Planned order receipts         120    
Planned order releases     120        

J (4) AND J (3) LT = 1 Beg. Inv. 1 2 3 4 5 6


Gross requiements     480   210    
Schedules receipts       30 30 30  
Projected on hand 20 20 20 50 80 80 80
Net requirements     460   130    
Planned order receipts     480   180    
Planned order releases   480   180      
 An additional 20 units for B and 30 units for J will be on-hand in week 6.