Republic of the Philippines

Department of Education
REGION VIII (EASTERN VISAYAS)
SCHOOLS DIVISION OFFICE OF CATBALOGAN CITY
GUINSORONGAN ELEMENTARY SCHOOL
Catbalogan City

PROJECT TITLE: INSTALLATION OF STAGE ROOFING AND HANDRAILING STAINLESS STEEL


RPOJECT LOCATION: GUINSORONGAN ELEMENTARY SCHOOL
SOURCE OF FUND:
AMOUNT OF THE PROJECT:

ID DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST


NO.
Rib Type single 16 feet pcs 18 1,024.00 P18,432.00
Tubular bar 2x2 pcs 18 795.00 14,310.00
Angle bar 3/16 1 ½ inches pcs 20 697.00 13,940.00
Angle bar 3/16 1 inch pcs 12 404.00 4,848.00
Angle bar 3/16 2 inches pcs 14 875.00 12,250.00
Tube Stainless 1 ½ inches pcs 5 1,800.00 9,000.00
Welding Rod boxes 2 212.00 636.00
Tek Screw 2 inches pcs 1000 2.00 2,000.00
Galvanized Iron 4x8 inches pcs 4 840.00 3,360.00
w/paint
Nails 3 inches kilo 1 66.00 66.00
Nails 1 ½ inches kilo 1 71.00 71.00
RSB 16 mm pcs 10 415.00 4,150.00
RSB 10 mm pcs 8 157.00 1,256.00
Cement (Mabuhay Premium) bags 15 245.00 3,675.00
Tie Wire kilo 1 78.00 78.00
Sand cubic 2 1,300.00 2,600.00
Graba cubic 1 1,700.00 1,700.00
Epoxy Primer gal 1 1,150.00 1,150.00
Laquer Thinner pcs 2 64.00 128.00
Paint Brush 2 inches pcs 4 27.00 108.00
Cutting Dish Metal 4 inches pcs 6 35.00 210.00
Cutting Dish Metal 14 inches pcs 3 255.00 765.00
Sander Blade (metal) 4 inches pcs 2 42.00 84.00
Blind Rivets 5/32x1/2 inches pcs 250 1.60 400.00
Drill Bit (metal) 5/32x1/2 inches pcs 3 150.00 450.00
I TOTAL MATERIAL COST P95,667.00
LABOR NO. OF NO. OF DAILY RATE TOTAL
PERSONNEL DAYS AMOUNT
LABOR 4 16 600.00 38,400.00
WELDER 2 16 700.00 22,400.00
II TOTAL LABOR COST P60,800.00
EQUIPMENT NO. OF NO. OF DAILY RATE TOTAL
EQUIPMENT DAYS AMOUNT

III TOTAL EQUIPMENT COST


IV TOTAL PROJECT COST (I+II+III) P156,467.00
Prepared by: Noted by:

FRANCISCO M. RAQUIZA ROY S. GABITANAN


GPTA President Principal