Timeline Schedule Project HR System: Minggu - 4 Periode: Agustus - November 2022
Timeline Schedule Project HR System: Minggu - 4 Periode: Agustus - November 2022
Timeline Schedule Project HR System: Minggu - 4 Periode: Agustus - November 2022
MINGGU - 4
PERIODE : AGUSTUS - NOVEMBER 2022
MINGGU - 4
NO. URAIAN PEKERJAAN BOBOT (%) FISIK % PHASE KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A BEGINNING ADMINISTRATION
I BOX OF MEETING 0.450 0% PLAN 0.113 0.113 0.113 0.113
ACT
II DATA ANALYSIS & COORDINATION 0.550 0% PLAN 0.138 0.138 0.138 0.138
ACT
DEVELOPMENT PHASE
B ASSET MODULE
1 EQUIPMENT DATA TABLE PREPARATION 3.139 0% PLAN 0.785 0.785 0.785 0.785
ACT `
2 DATA TABLE CMMS PREPARATION 4.301 0% PLAN 1.075 1.075 1.075 1.08
ACT
3 DATA UPLOAD & DEVELOPMENT 3.250 0% PLAN 0.813 0.813 0.813 0.813
ACT
4 RUN TEST & ADJUSMENT 2.370 0% PLAN 0.593 0.593 0.593 0.593
ACT Series1
Series2
C SPAREPART MODULE Series3
1 EQUIPMENT DATA TABLE PREPARATION 2.510 0% PLAN 0.628 0.628 0.628 0.63 Series4
ACT
2 DATA TABLE CMMS PREPARATION 6.150 0% PLAN 1.538 1.538 1.538 1.538
ACT
3 DATA UPLOAD & DEVELOPMENT 3.250 0% PLAN 0.813 0.813 0.813 0.813
ACT
4 RUN TEST & ADJUSMENT 2.370 0% PLAN 0.593 0.593 0.593 0.593
ACT
GO LIVE IMPLEMENTATION
A DEPLOYMENT GO LIVE
1 UPLOAD TO SERVER 2.010 0% PLAN 1.005 1.005
ACT
2 RUN TEST & ADJUSMENT 1.432 0% PLAN 0.477 0.477 0.477
ACT
3 TRAINING CMMS OPERATIONAL 0.367 0% PLAN 0.367
ACT
CREATIVE DEV
ZAINI MAHMUD