Professional Documents
Culture Documents
A Design Framework For Building Services: by David Churcher, Martin Ronceray and John Sands
A Design Framework For Building Services: by David Churcher, Martin Ronceray and John Sands
DELIVERABLES
Models Drawings Informa�on
1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7
Mechanical
S
Y
S Electrical
T
E
M
S
Public Health
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 1 06/06/2018 16:17:15
Acknowledgements
In addition to those involved in the preparation of the previous editions of A Design Framework for
Building Services, BSRIA would like to thank the following organisations and individuals for their invaluable
contribution in the development of this 5th edition:
In addition, BSRIA would like to thank Ben Roberts, Martin Trentham and Bradley Fletcher for creating
exemplar 3D models for this guide.
This guide’s technical authors were David Churcher, Martin Ronceray and John Sands, and it was designed
and produced by Joanna Smith. Every opportunity has been taken to incorporate the views of the working
group, but final editorial control of this document rested with BSRIA.
Where this guide refers to another publication or standard, the relevant version is the one listed at the end
of this guide. However, if that version has been revised or updated, the new version may be used as a
source of guidance provided it continues to address the relevant topic.
Licensed versions
BSRIA is the owner or the licensee of all intellectual property rights in this publication, and in the content published in it. Consent is granted
to users of this publication to reproduce and modify the proformas in appendices A and B for use on their projects in accordance with
the limited licence on the inside back cover of this publication. All risk associated with the use of material from this publication is assumed
entirely by the user. Full terms and conditions can be found at www.bsria.co.uk/terms.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 2 08/06/2018 11:22:54
BG 6/2018
A Design Framework for
Building Services 5 edition th
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 3 06/06/2018 16:23:58
Contents
Glossary vi
1 Introduction 1
2 About BG 6 3
2.1 The purpose of BG 6 3
2.2 The structure of BG 6 3
2.3 The design process and definition of design outputs 4
2.4 Design coordination 7
2.5 Design clashes 10
2.6 BG 6 and BIM 12
2.7 Level of detail/level of information (LOD/LOI) 15
2.8 Contractor Design Portion (CDP) 15
3 How to use BG 6 17
3.1 The process of using BG 6 17
3.2 Allocating design responsibilities – Appendix A 17
3.3 Allocating information production – Appendix B 20
3.4 Completing the proformas 20
3.5 Non-building services specialist design 21
3.6 Effect of procurement route 21
3.7 Precision in design 22
3.8 Design reviews 23
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 4 06/06/2018 16:23:58
Appendices
References 120
Bibliography 121
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 5 06/06/2018 16:23:59
Glossary
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 6 06/06/2018 16:23:59
Introduction
1 Introduction
This latest version - the 5th edition – is the outcome of the largest and
most comprehensive review process BG 6 has ever undergone,
and has benefited from many people giving a significant amount
of their time to share their views and experience. Needless to
say, this new edition would not have been possible without this
tremendous effort and it has helped to ensure that the 5th edition is
an effective tool for all parties to understand what is required from
their design duties. By giving clear and, above all, mutually agreed
guidance, the design process should be carried out efficiently and
to the required standard.
The key changes in this edition of BG 6 from the 4th edition can be
summarised as follows:
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 1 06/06/2018 16:23:59
Introduction
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 2 06/06/2018 16:23:59
About BG 6
2 About BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 3 06/06/2018 16:23:59
About BG 6
At the start of the process, some initial concepts are explored and
drawings or models produced accordingly. The level of detail at
this stage would be limited to block diagrams for approximate
plant positions and some line diagrams to show the concepts of
the various systems.
The detail design would reflect the chosen solution and would
include accurate plant and services distribution sizing, and plant
room layouts. The drawings/models would be in double-line format
at this stage. At the end of this stage there would be sufficient
information produced to allow the project to be successfully
tendered and priced.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 4 06/06/2018 16:23:59
About BG 6
In this case, the main design activities take place during stages 2, 3
and 4, although stage 4 overlaps with stage 5, as shown in Figure 4.
As with the previous edition, this edition of BG 6 is designed to align
with the RIBA Plan of Work 2013. Individual proformas are provided
for each RIBA stage (except Stage 0), with the appropriate
activities and outputs included for selection and allocation to the
required party.
For each of these stages, the design outputs are defined and these
are shown in the following flow chart (Figure 2), demonstrating how
the depth of design information gradually increases.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 5 06/06/2018 16:23:59
About BG 6
INSTALLATION INSTALLATION
5 MODEL
AS-BUILT RECORD
MODEL
(
)
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 6 06/06/2018 16:23:59
About BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 7 06/06/2018 16:23:59
About BG 6
This process is shown in Figure 3, and examples of how this might work
in practice within the Stage 4 proforma, have been included in the
examples contained in Appendix C. In Figure 3, the horizontal axis
represents the increasing level of object definition and the vertical
axis represents the increasing level of coordination. It can also be
read diagonally if the ‘coordinated generic’ phase is not required.
This aims to highlight the shift in the focus of the project from
design to installation. By defining the three core design activities
that are undertaken during Stages 4 and 5, the persons or parties
that specify the design duties can select all three in the currently
favoured linear process, or can omit the need for some of these
activities to be implemented.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 8 06/06/2018 16:23:59
About BG 6
Coordinated-generic Coordinated-specific
design design
Feasible-generic
design
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 9 06/06/2018 16:24:00
About BG 6
Moderate Easily resolvable – does not have a major impact on ongoing design. Can be resolved at a future design stage
The stage examples given in Figure 5 are not exhaustive, and are
meant only as a guide to the type of instance. These should not be
seen as the only cases which are applicable.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 10 06/06/2018 16:24:00
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 11
©BSRIA
and terminals.
Moderate Easily resolvable - If a column clashes with a Cable trays clashing with Not applicable at this stage Not applicable at Not applicable at Not applicable at
does not have major plant zone but services can ductwork within ceiling this stage this stage this stage
impact on ongoing be coordinated within, or void, provided sufficient
design. Can be column re-arranged; space is demonstrated.
resolved at a future Riser zones clashing with
design stage. slabs and walls
Allowable Acceptable clash. Not applicable at this stage Not applicable at this stage Small pipework / conduit Not applicable at Not applicable at Not applicable at
Resolution not as the level of detail is not as the level of detail is not runouts to equipment / this stage this stage this stage
required in the sufficiently advanced sufficiently advanced final circuits where space is
design model. proven to be sufficient;
About BG 6
BG 6/2018
06/06/2018 16:24:00
| 11
About BG 6
Introduction to BIM
Building Information Modelling, or BIM as it is widely known, is
becoming an ever-increasing part of the construction world. At
its heart, BIM is about information management, but this is nothing
new to construction. Large scale formal information management
procedures have historically started when the main contractor is
appointed and brings their electronic document management
system to site to help them manage the flow of information with
their supply chain. The current drive to adopt BIM more widely
aims to start that information management process earlier in the
project timeline, and to carry it on into the operation of the new
asset. This becomes an even more powerful tool when the client
owns the common data environment and uses it from the start of
the project.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 12 06/06/2018 16:24:00
About BG 6
These help to ensure that all parties are producing data and
documents in the same way, and to an agreed standard.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 13 06/06/2018 16:24:00
About BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 14 06/06/2018 16:24:00
About BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 15 06/06/2018 16:24:00
About BG 6
• Audiovisual (AV)
• Fire alarms
• Lightning protection
• Prefabrication/offsite construction
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 16 06/06/2018 16:24:00
How to use BG 6
3 How to use BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 17 06/06/2018 16:24:00
How to use BG 6
Model definitions
Appendix A contains definitions and shows examples of the
development of a geometric building information model during
the building services design and construction process.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 18 06/06/2018 16:24:00
How to use BG 6
Drawing definitions
Appendix A also contains drawing definitions and shows examples
of what level of detail these drawings might typically contain.
A generic office building project is used as the subject for these
example drawings.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 19 06/06/2018 16:24:00
How to use BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 20 06/06/2018 16:24:00
How to use BG 6
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 21 06/06/2018 16:24:00
How to use BG 6
Stage 2: ±25%
Stage 3: ±15%
Stage 4: ±5%
The draft digital Plan of Work project process also includes levels of
confidence for the design, as follows:
The digital Plan of Work confidence levels broadly agree with the
rule of thumb precision figures.
However, these single precision figures for each design stage can
be misleading as there are many instances where significantly
tighter design precision is needed than the figures would suggest.
For example, if wall panels are being manufactured offsite then
complete precision related to the position, specification and
quantity of cast-in fittings is required. This may mean the positions
of electrical sockets, light switches and data points need to be
agreed by the end of Stage 3 or early in Stage 4 to allow the
manufacturing plant to deliver wall panels to site early in the
construction programme.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 22 06/06/2018 16:24:00
How to use BG 6
Similarly, the figures for main power, heating and cooling loads
from energy modelling software may need to be more precise at
an early stage of design than ±25% would suggest, so that utility
requirements, central plant layouts and plant rooms can be sized.
Also, design criteria relating to long lead-time components such as
lifts will need to be more precise than the above figures imply.
The third type of review is the sign-off by the client at the end of
each appropriate design stage. This review is included as the final
activity in the deliverables sub-group.
Ad hoc design reviews that are needed for specific design issues
are also allowed for in the Soft Landings and Pitstopping processes
(see BSRIA Guides BG 54[8] and BG 27[9] respectively), but these are
not specifically included in the Appendix A proformas.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 23 06/06/2018 16:24:00
24 |
Proformas
The following proformas are for use to allocate design activities from RIBA stages 1 to 7.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
By the end of this proforma, the design team has arrived at a design where each discipline has its allocated
volumes within the building. From a building services perspective, there is sufficient evidence to show that
the services volume is sufficient to contain the building services.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 24 06/06/2018 16:25:47
©BSRIA
Building services design is coordinated to remove all clashes. Where a building services contractor has
been appointed, it is likely that coordination will take place using plant and components that have been,
or are going to be, procured by the contractor, and specialist design is incorporated at the same time.
Where there is no trade contractor, coordination will be in terms of specified or generic items.
Building services design is finalised, including details from specialists, and where changes occur the
coordination of the design is checked. BSRIA’s view is that if these activities are allocated to the building
services consultant then these almost certainly occur after the building services contractor has been
appointed, even if earlier proforma activities do not.
been appointed. Depending on procurement route, the building services contractor may be appointed
much earlier than this. This stage covers the on-site installation of services and their commissioning, to take
the project to the state where handover can occur.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 25 06/06/2018 16:25:48
26 |
1. Fill in the details of the project and the organisations/roles involved, in the spaces below. The status of
the proforma (for example, ‘for discussion’, ‘for information’, ‘draft’, or ‘contract issue’), the date and
the person completing the proforma must all be indicated.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
2. Review each proforma and strike through activities that are not required for the project.
3. If an activity needs to be amended, strike through the original and rewrite it in sub-section 10 at the
end of the proforma. Recipients are entitled to expect that the standard proforma (sub-sections 1 to
9) has been used except where clearly indicated.
4. For the remaining activities, allocate leadership, support and review by placing L, S and R in the
columns corresponding to the appropriate parties. If activity leadership cannot be allocated to a
single party, strike it through and rewrite it in sub-section 10 as two or more activities that can each be
led by a single organisation or role. Alternatively use ticks () to indicate activity leadership only, most
likely to apply to simpler projects.
5. Add any appropriate notes to the Comments column, for example to clarify the scope of an activity.
6. In addition to the activities in proformas 1 to 7, there might be a need to identify and allocate other
activities which might be strategic (prior to formal commencement of Stage 1) or difficult to always
associate with the same project stage. If so, such activities should be included in sub-section 10 of
proforma 1 and made clear to all recipients.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 26 06/06/2018 16:25:48
©BSRIA
A ………………………………………………………………………………….…………………………………………
B …………………………………………………………………………………………………………………………….
C ………………………………………………………………………………….…………………………………………
D ………………………………………………………………………………….…………………………………………
E ………………………………………………………………………………….………………………………………….
Date ……………………………………………………………………………..………………………………………...
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 27 06/06/2018 16:25:48
STAGE 1
28 |
“Several significant and parallel activities need to be carried out during Stage 1 Preparation and Brief to ensure that Stage 2 Concept Design is as productive
as possible. These split broadly into two categories:
•• developing the Initial Project Brief and any related Feasibility Studies
•• assembling the project team and defining each party’s roles and responsibilities and the Information Exchanges.
The preparation of the Initial Project Brief is the most important task undertaken during Stage 1. The time required to prepare it will depend on the
complexity of the project.
•• the project’s spatial requirements − the desired Project Outcomes, which may be derived following Feedback from earlier and similar projects
•• the site or context, by undertaking site appraisals and collating Site Information, including building surveys
•• the budget.
A project Risk Assessment is required
to determine the risks to each party. The development of the procurement strategy, Project Programme and, in some
instances, a (town) planning strategy are all part of this early risk analysis.
The importance of properly establishing the project team should not be underestimated, given the increasing use of technology that enables remote
communication and project development using BIM. For Stage 2 to commence in earnest, it is essential that the team is properly assembled.”
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 28 06/06/2018 16:25:48
©BSRIA
1.2.2 Prepare the building services Employers Information Requirements in accordance with PAS State appointment this relates to
1192-2.
1.2.3 Prepare pre-contract BIM Execution Plan for building services design. As per PAS 1192-2
1.2.4 Appraise physical data, planning and environmental issues for each site or option.
1.2.5 Initial review of existing health and safety file to identify significant risks that need to be
considered (for refurbishment projects or additional construction on an existing site).
1.2.6 Explain Soft Landings process to the client, end-users and core design team.
1.2.7 Establish Soft Landings requirements for the project.
1.2.8 Establish Soft Landings team/proposals for the project.
STAGE 1
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 29 06/06/2018 16:25:48
STAGE 1
30 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
1.3.2 Investigate and advise on potential energy strategy options to comply with any energy-
related planning conditions.
1.3.3 Prepare visualisation model(s) of the proposed building(s) on the site(s) to show relationships
with other natural and built features, orientation to the sun and principal occupation zones/
interior spaces.
Selection of plant and specialist designers
1.4.1 Review potential delivery methods for the project, including offsite manufacture. Early consideration of whole-room offsite
assemblies is particularly important
1.4.2 Reflect agreed delivery methods for the project in contractual arrangements. See also 2.4.1 and 2.4.3
Mechanical design
Electrical design
Commissioning
1.8.1 Advise need for commissioning strategy.
Deliverables – including drawings, specifications, reports
1.9.1 Provide initial project brief. Usually compiled by the lead consultant
and signed off by the client
1.9.2 Provide initial design programme for the project.
1.9.3 Provide assessment of significant risks identified from existing Health and Safety File.
1.9.4 Provide COBie tables for BIM Level 2 Information Exchange 1 (Facility, Floor and Space sheets
started).
Amended and additional activity descriptions
1.10.1 <insert text here>
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 30 06/06/2018 16:25:48
©BSRIA
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 1
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 31 06/06/2018 16:25:48
STAGE 2
32 |
The project team also develops, in parallel with the Concept Design, a number of Project Strategies. Their importance at
this stage will depend on how they are to influence the Concept Design. For example, the Sustainability Strategy is likely to
be a fundamental component of the Concept Design, whereas a security strategy may have minimal or no impact and can
therefore be developed during a later stage.
It is essential to revisit the brief during this stage and it should be updated and issued as the Final Project Brief as part of the
Information Exchange at the end of Stage 2.
In parallel with design activity, a number of other related tasks need to be progressed in response to the emerging design,
including a review of the Cost Information, the development of a Construction Strategy, a Maintenance and Operational
Strategy and a Health and Safety Strategy and updating of the Project Execution Plan.”
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 32 06/06/2018 16:25:48
©BSRIA
provided information.
2.1.4 Advise on regulatory compliance of concept design.
2.1.5 Prepare initial strategy for fire safety (such as compartmentation, location of fire lifts, fire
detection and suppression philosophy, consultation with relevant authorities).
2.1.6 Establish impact of fire strategy on building services design.
Client liaison (briefing, handover, surveys)
2.2.1 Evaluate physical, environmental, functional and regulatory constraints from clients’ brief, for
potential schemes.
2.2.2 Visit site(s) and/or example project(s) to assess physical restrictions that might influence the
2.3.1 Undertake the role of lead project designer. Define scope of role
2.3.2 Fulfil role of Principal Designer under CDM Regulations 2015. Continues until Principal Contractor is
appointed
| 33
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 33 06/06/2018 16:25:48
STAGE 2
34 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
2.3.3 Discuss potential mechanical, electrical and public health schemes for the preferred solution
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 34 06/06/2018 16:25:48
©BSRIA
2.4.4 Advise on potential for off-site manufacture of building services plant and distribution Early consideration of room-scale or riser
equipment, including implications for construction strategy, project milestones and logistics. assemblies is particularly important
2.4.5 Agree initial off-site delivery strategy including programme milestones.
2.4.6 Establish areas/zones for central plant in line with mechanical, electrical and public health
design philosophies.
2.4.7 Consider and define need for provisional sums.
Mechanical design
2.5.1 Determine mechanical systems philosophy.
2.5.2 Determine passive design philosophy.
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 35 06/06/2018 16:25:48
STAGE 2
36 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 36 06/06/2018 16:25:48
©BSRIA
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 37 06/06/2018 16:25:48
STAGE 2
38 |
A model showing basic building services proposals, connections to incoming services and utilities, Line diagrams, layouts and sections indicating
locations of plant areas using rectangular blocks, and routes of main pipes, ducts and electrical basic proposals, connections to incoming services
distribution in such detail as to show the incorporation of the engineering services in the project as a and utilities, location of areas of central plant,
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
whole and with respect to any treatment zoning across the floor-plate. location and extent of main vertical and horizontal
Analogous to detail in BSRIA Concept sketch drawings and Concept Design schematics. distribution routes in such detail as to illustrate the
Tolerances for concept design models should be agreed between the recipient and the author before incorporation of the engineering services within the
concept design starts, with reference to other members of the project team as appropriate. Tolerances project as a whole and with respect to any zoning.
may be expressed in terms of absolute values, or percentage variance, in relation to volume, area,
length, weight or some other property.
Typical plant area data to include along with geometry at this stage would include:
•• Approximate size (length, width, height) of each plant area including estimates of space required
for installation and maintenance
Drawing definition: Concept schematics
•• Approximate weights for main central plant areas and primary distribution routes, especially if Line diagrams indicating main items of plant and
there are significant structural engineering implications their interrelationships, including with incoming
•• Outline/maximum performance based on building type and approximate area rules of thumb services and utilities, in such detail as to illustrate the
incorporation of the engineering services within the
Typical uses for the model at this stage:
project as a whole.
Analysis The model may be analysed for performance by applying generic criteria
to the generic model elements.
Costing The model may be used to develop cost estimates based on approximate
quantities and rules of thumb (cost per element or m2 floor area or m3
building volume).
Programme The model may be used to show the timescale of installation of major
elements and systems but not of detailed components.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 38 06/06/2018 16:25:49
©BSRIA
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 39 06/06/2018 16:25:56
STAGE 2
40 |
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 40 06/06/2018 16:26:17
©BSRIA
1 2 3 4 5 6 6
7 8 9 10
A A
Cooling Plant
Electrical Switchgear
31000 L x 5700 W x 3500 H
19000 L x 5700 W x 2500 H
Chillers, pumps, headers, pipework &
2No rooms for essential & non-essential
B ancillaries, space for access and airflow.
supplies B
Louvred wall required
Approximate Weight = 6500kg
Approximate Weight = 12000kg
G G
BG 6/2018
1 2 3 4 5 6 7 8 9 10
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 41 06/06/2018 16:26:18
STAGE 2
42 |
A
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
B
2000 W x 700 L
MEP service distribution zone
1750 L x 7000 W
Mechanical riser
2000 W x 700 L
D
1250 L x 2000 W 1500 L x 8000 W
Mechanical riser 150 mm deep service void
Electrical services
E
350 mm deep service void 2000 W x 700 L
MEP service distribution zone
F
Electrical substation
6000 L x 4500 W x 3000 H
approximate duty = 2000 kW
approximate weight = 8000 kg
G
Double door access to
electrical plant room from
vehicle route
1 2 3 4 5 6 7 8 9 10
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 42 06/06/2018 16:26:20
©BSRIA
Key
Pump Isolation valve Flow direction
/ buffer vessel
Chiller 4
Pressurisation
unit 3
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 43 06/06/2018 16:26:20
STAGE 2
44 |
Spare
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
meeting rooms
Plant DB-B
Plant DB-A
Chillers B
Chillers A
AV/Func. rm
Roof
7th floor
7th floor
Light and power Light and power “B”
combined boards combined boards
south and east north and west 7
Lifts 6
mrl FF
mrl 5
lifts
4
Fire
Basement Security alarm Sprinkers External
Computing
L.V switchboard
Basement
Normally Normally
closed open
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 44 06/06/2018 16:26:20
©BSRIA
HOLD
DOORS
OPEN
SD SD HD HD
FAI MCP
SB SB
FAI FAI
ACCESS PLANT
CONTROL
HOLD
DOORS
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
OPEN
SD SD HD HD
FAI MCP
SB SB
FAI PLANT
FAI
DISABLE
REFUGE
LEGEND
LEVEL 1
SD
HOLD SMOKE DETECTOR
DOORS
HD
OPEN HEAT DETECTOR
SPD LOCATED AT PERIMETER OF CANCER CENTRE
LEVEL 0
BG 6/2018
STAGE 2
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 45 06/06/2018 16:26:20
STAGE 3
46 |
“During this stage, the Concept Design is further developed and, crucially, the design work of the core designers is progressed until the spatial
coordination exercises have been completed between the main design disciplines. This process may require
a number of iterations of the design and
different tools may be used, including design workshops.
By the end of Stage 3, the architectural, building services and structural engineering designs will all have been developed, and will have been checked by
the lead designer, with the stage design coordinated between disciplines and the Cost Information aligned to the Project Budget.
Project Strategies that were prepared during Stage 2 should be developed further and in sufficient detail to allow the client to sign them off once the lead
designer has checked each strategy and verified that the Cost Information incorporates adequate allowances.
Change Control Procedures should be implemented to ensure that any changes to the Concept Design are properly considered and signed off, regardless
of how they are instigated.
While specialist subcontractors will undertake their design work at Stage 4, they may provide information and guidance at Stage 3 in order to facilitate a
more robust developed design. “
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 46 06/06/2018 16:26:21
©BSRIA
replacement.
3.3.3 Review design risk assessments and update to reflect developing design. Specify extent (e.g. H&S, technical,
commercial)
| 47
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 47 06/06/2018 16:26:21
STAGE 3
48 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
3.3.4 Review design against Building Regulations compliance in relation to energy performance
and (if relevant) EPC criteria.
3.3.5 Review dimensional and other numerical tolerances to be applied to building services design
and deliverables at different project stages.
3.3.6 Carry out calculations in relation to any energy-related planning conditions and advise team
of implications to overall design.
3.3.7 Incorporate frozen primary building geometry in building services design.
3.3.8 Approve and share primary building geometry (General Arrangement drawings or building
information model).
3.3.9 Obtain room data.
3.3.10 Populate room data with building services information.
3.3.11 Review specialist design inputs and incorporate into building services proposals. Specify extent (e.g. fire, acoustic)
3.3.12 Develop and update BIM Execution Plan during project. As per PAS 1192-2
3.3.13 Develop and update building services Task Information Delivery Plan for Design and Build
development.
3.3.14 Develop and update Master Information Delivery Plan during project. As per PAS 1192-2
3.3.15 Federate information models from separate task teams and oversee the clash avoidance As per PAS 1192-2. See also 2.3.14
process.
3.3.16 Carry out Stage 3 coordination.
3.3.17 Remove critical clashes from the building services developed design. See section 2.5 of BG 6
3.3.18 Review BIM protocol and determine data fields to be completed for each BIM object.
3.3.19 Team-wide design review to signal end of developed design stage. See section 3.8 of BG 6
Selection of plant and specialist designers
3.4.1 Prepare Developed Design for specialist design items not included in 3.5.2, 3.6.2, 3.7.2. Specify items (e.g. long lead time, critical
path or technically critical items) and
agree extent of developed design
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 48 06/06/2018 16:26:21
©BSRIA
3.5.4 Establish indicative plant sizes for mechanical systems and confirm plant room/riser
locations/sizes.
3.5.5 Undertake dynamic thermal simulation studies in the development of energy strategies Scope to be defined
for the fabric and engineering services as required to support the design and obtain
quantitative feedback – typically 3D modelling.
3.5.6 Undertake computational fluid dynamics studies as part of a detailed evaluation for the State requirements e.g. air movement
particular stated aspects of the building services design. in specific areas, smoke clearance,
effectiveness of air movement for natural
ventilation
3.5.7 Calculate zoned heat gains and losses based on fabric information, using approximate
3.6.2 Develop preliminary information on specialist electrical systems to be procured as Systems may include data, telephony,
Contractor Design Portions, such as performance specification, loads, schedules. security
3.6.3 Determine principal plant (equipment) locations/sizes.
3.6.4 Prepare principal metering strategy.
| 49
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 49 06/06/2018 16:26:21
STAGE 3
50 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
3.6.5 Establish indicative plant sizes for electrical systems and confirm equipment/switch room
and riser locations/sizes.
3.6.6 Undertake daylight computer modelling required to support the design and obtain State particular requirements for the
quantitative feedback. project
3.6.7 Calculate the maximum demand for small power and lighting using approximate methods.
3.6.8 Calculate the maximum demand for high voltage supply using approximate methods.
3.6.9 Determine main distribution routes and circuits around floors to and from risers and main Consider ability to install, commission and
switchgear, and approximate sizes of containment and switchgear. maintain
3.6.10 Design review. See section 3.8 of BG 6
Public health design
3.7.1 Propose primary design criteria and extent of public health systems.
3.7.2 Develop preliminary information on specialist public health systems to be procured as Systems may include syphonic drainage
Contractor Design Portions, such as performance specification, loads, schedules.
3.7.3 Establish approximate overall flow rates to allow below-ground drainage design to be
completed by others.
3.7.4 Establish main below-ground drainage routes and manhole locations.
3.7.5 Define the design interface between above-ground and below-ground drainage systems.
3.7.6 Ensure storm water discharge strategy meets the requirements of the planning authorities to
meet their SuDS aspirations and that discharge flow rate is in accordance with planning and
statutory authority requirements.
3.7.7 Prepare principal metering strategy.
3.7.8 Establish indicative plant sizes for public health systems and confirm plant room and riser
locations/sizes.
3.7.9 Calculate maximum demand for water supply and waste removal using approximate
methods.
3.7.10 Calculate approximate system capacities for hot and cold water central plant (tanks,
cylinders, and pumps).
3.7.11 Determine main pipe and drain routes around floors to and from risers. Consider ability to install, commission and
maintain
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 50 06/06/2018 16:26:21
©BSRIA
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 51 06/06/2018 16:26:21
STAGE 3
52 |
Allocated to ….
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 52 06/06/2018 16:26:21
©BSRIA
•• The type of system serving the space e.g. mechanical ventilation, cooling, etc.
•• The system performance standards e.g. for lighting, heating, cooling, etc.
•• The type and quantity of all other service elements within the space which are not defined in performance terms.
•• Incorporate performance and spatial requirements for Contractor Design Portion (CDP) elements.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Approximate locations of horizontal and vertical services runs are shown and should convey maximum space requirements for
expected plant and distribution systems, taking account of falls, coordination, tolerances, installation, maintenance and removal. The
model could also indicate designs for repeatable areas (e.g. standard room types) to identify key principles.
Tolerances for developed design models should be agreed between the recipient and the author before developed design starts,
with reference to other members of the project team as appropriate. Tolerances may be expressed in terms of absolute values, or
percentage variance, in relation to volume, area, length, weight or some other property.
•• Object name
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 53 06/06/2018 16:26:21
STAGE 3
54 |
Principal ductwork (within risers and from risers to local plant) could be shown as 3D objects to demonstrate that the routes
indicated are feasible. Ductwork from local plant to terminal units and pipework may be represented by centre-lines, but should also
detail routes to & from secondary areas. Additional sections / elevations may also be needed to demonstrate the robustness of the
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Costing The model may be used to develop cost estimates based on approximate
quantities and approximate sizes of plan
Programme The model may be used to show the timing of installation of the main
building services systems.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 54 06/06/2018 16:26:21
©BSRIA
•• plan layouts should be to a scale of at least 1:100 with key areas at 1:50.
•• Show the extent and type of services terminals visible within the occupied space. Alternatively, these can be quantified and
scheduled either as a tag on the drawing or as a separate schedule or room data sheet.
•• Show main plant and main distribution system sizes, particularly those affecting spatial allocation, while acknowledging that
these may need some adjustment and refinement in the preparation of the technical design drawings and equipment schedules.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
•• Pipework and electrical containment should be represented by single line layouts. Ductwork should be represented by
either double line or single line layouts as required to demonstrate that the routes indicated are feasible (this should also be
supplemented with key sections / elevations). Symbols and line conventions should be in accordance either with a recognised
standard, such as ISO or BS, or a supplied legend.
These drawings will show how space within risers and service zones is allocated to:
Where appropriate these drawings should indicate typical room/area details to show key principles of the systems within them or
serving them.
BG 6/2018
| 55
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 55 06/06/2018 16:26:21
STAGE 3
56 |
Line diagrams describing the interconnection of components in a system showing the engineering principles. The main features of a
Developed Design schematic drawing should be as follows:
•• The drawings should include all the engineering components that make the system work, such as main plant, distribution, inline
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
equipment supporting engineering performance, terminal plant providing HVAC performance. Quantities of performance-
specified components would only be indicative at this stage, with accurate quantities on schedules or similar.
•• Symbols and line conventions should be in accordance either with a recognised standard, such as ISO or BS, or a supplied legend.
•• The drawings should be labelled with appropriate pipe, duct, busbar and cable sizes, pressures and flow rates. These details may
be subject to adjustment during technical design and construction stages.
•• The drawings should indicate components which have a sensing, control or measurement function.
•• The major components indicated on the schematic drawing should be identified for cross-referencing purposes.
Where appropriate these drawings should indicate typical room/area details to show key principles of the systems within/serving
them.
The stage 3 Developed schematic fire alarm would be similar to the stage 2 concept schematic fire alarm. Only minor
additions would be made to reflect any changes to floors or areas covered.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 56 06/06/2018 16:26:21
©BSRIA
SAMPLE INFORMATION
Type: Chiller
Reference: CH-08-03
Cooling duty: 400 kW
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 57 06/06/2018 16:26:25
STAGE 3
58 |
75 mm Sanitary
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
50 mm LTHWF
50 mm LTHWR
65 mm CHWF
65 mm CHWR
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 58 06/06/2018 16:26:26
©BSRIA
1 2 3 4 5 6 7 8 9 10
A
Full height louvred room required
B
Access space Access space
100 mm CHWF
100 mm CHWR 600 mm x 100 mm main LV
1750 L x 7000 W 500 X 500
1750 L x 8500 W
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Access space
Roof AHU
Chiller
600 mm x 100 mm main LV
C
Access space
4 (N)room
1750 L x 8500 W
AHU 8
Training
1500x600
Combined services riser
AHU
1400x700
80 mm LTHWF
400ø flue
exhausts to
above
1000x600
D
Boiler
Access space
100 mm LTHWR
AHU 4 (N)
1400x600 LTHW Heating pumps and ancillaries
1400x700
1400X400 to
rooms below Boiler
1500 L x 8000 W
16351
Electrical services
Boiler 80 mm LTHWR
Access space
Function room
Access space
AHU 3 (W)
AHU 5
E
80 mm LTHWR
80 mm LTHWF
AHU 2 (S) 1500x700
Access space
1500x700
Access space
AHU 7
65 mm LTHWF 40 mm LTHWR
65 mm LTHWF 40 mm LTHWF
65 mm CHWR
65 mm CHWF
F
500x500
Access space
Access space
Service-on-services clashes may exist at this stage,
provided that sufficient spatial allocation is proven
AHU 6 (large
DN AHU10 (WC) meeting room
G
BG 6/2018
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 59 06/06/2018 16:26:27
STAGE 3
60 |
Staff accomodation
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
GF-076
24 m2
Winter temp: 21
Summer temp: 24
Ventilation strategy: supply & 54 mm Dia. WVP number of WHBs: 2
extract
Heating strategy: Underfloor
heating
Single power sockets: 0 54 mm Dia. WVP to HL and OS
Twin power sockets: 3
Data points: 1
100 mm Dia. SVP Number of WCs: 2
50 mm LTHWF
50 mm LTHWR
65 mm CHWF
65 mm CHWR
Admin office
GF-077 150 mmx50 mm ICT services
24 m2 300 mmx50mm LV tray
Winter temp: 21 100 mmx100mm LV trunking
Summer temp: 24
Ventilation strategy: Naturally 200 W x 200 H Supply air
ventilated
Heating strategy: Underfloor
heating 75 mm Dia. WP FA to HL and OS
Single power sockets: 3
Twin power sockets: 4
Data points: 1
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 60 06/06/2018 16:26:27
©BSRIA
Raised floor - 7
26452
Level 7
26250
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 61 06/06/2018 16:26:27
STAGE 3
62 |
150ø 25kg/s
P
150ø 25kg/s
150ø 50kg/s
Tx15
T TP
TP TP Unit 3 ΔP
P P
TP TP TP TP
T
ΔP ΔP FP
P SP8 P
TP TP TP TP
Tx13 Chiller 5
Pp11A Pp11B 150ø 25kg/s FP
TP TP ΔP SP9
P
Tx12
150ø 50kg/s
DOC DOC DOC DOC DOC DOC DOC DOC DOC DOC TP
CFR
TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP TP
AHU 1 AHU 2 AHU 3 AHU 4 AHU 5 AHU 6 AHU 7 AHU 8 AHU 9 AHU 10
zone east zone south zone west zone north func. room lg mtg rm 1 sm mtg rms training rm lg mtg rm 2 WC supply
Note: Key
Pump speed is set by variable
speed drive for correct flowrate Pump Isolation valve TP Test point FP Flushing point Union connector
Non-return valve Orifice plate DOC Drain cock Flexible connector Pressure independant valve
Control device Strainer Double check valve x Pressure/temp guage Constant flow regulator
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 62 06/06/2018 16:26:28
©BSRIA
Roof
m Meter MCCB ACB MCCB MCCB ACB MCCB MCCB
OC Overcurrent
Plant DB-A
LOCATED ROOF
AUTO
A. C. C. U. UPS Uninterruptible INTER
Emergency 63A 800A 63A 63A 125A 800A
Chiller 3
Chiller 4
-LOCK
Control panel / plant;
integral isolation
power supply Power Off TP&N TP&N TP&N TP&N TP&N TP&N GRID A8 B9.5
Power Factor BS88 ACB BS88 BS88 MCCB ACB
G Generator/G59
Correction I SC (NORTH EAST CORNER)
10 17 m 18 m 12 m 13 11 3kA
Light and power
combined boards
South + East Spare 7
MICC
MICC
7th floor
meeting rooms
m m Triplex MRL lifts 6
(commando sockets)
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
m m C C C
5
FF FF Goods Lift
mrl mrl
MICC
m m
4
Lift Lift
m m PANEL“B”
SECTION OMITTED 3
FOR CLARITY
m m
2
m m
1
Ground
Reprographics franchise
franchise “A”
Basement Fir
Fire Sump Computing (E) Computing (B)
plant Security Ala
Alarm BMS Sprinklers Pumps Mech. Plant Mech. Plant
m m m m m m m m m m m 21 m 22
22 m 23 m m m 26 m m m
Basement
125A 63A 400A 125A 125A 63A 63A 63A 63A 250A 500A 250A 800A 32A 32A 32A 63A 32A 800A 315A 325A 125A
TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N TP&N
MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB ACB MCCB MCCB MCCB BS88 BS88 ACB MCCB MCCB MCCB
ACB
(Electric Distribution
Network Operator)
Emergency Power Off
within Tx Room trips
2500kVA
11kV/400V Cast resin
inc
I SC
EARTH SCHEMATIC LOCATED BASEMENT, GRID B5 C7
DNO and transformer Transformer REF EF IEF OC 12kA
HV circuit breakers
STAGE 3
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 63 06/06/2018 16:26:28
STAGE 4
64 |
“The architectural, building services and structural engineering designs are now further refined to provide technical definition of the project and the design
work of specialist subcontractors is developed and concluded. The level of detail produced by each designer will depend on whether the construction on site
will be built in accordance with the information produced by the design team or based on information developed by a specialist subcontractor. The Design
Responsibility Matrix sets out how these key design interfaces will be managed.
Using the design coordinated during the previous stage, the designers should now
be able to develop their Technical Designs independently, with a degree of
autonomy. The lead designer will provide input to certain aspects, including a review of each designer’s work.
Once the work of the design team has been progressed to the appropriate level of detail, as defined in the Design Responsibility Matrix and the Design
Programme, specialist subcontractors and/or suppliers undertaking design work will be able to progress their design work. The lead designer and other
designers, where required as part of their Schedule of Services, may have duties to review this design information and to ensure that specialist subcontractor
design work is integrated with the coordinated design.
By the end of this stage, all aspects of the design will be completed, apart from minor queries arising from the site during the construction stage. In many
projects, Stage 4 and 5 work occurs concurrently, particularly the specialist subcontractor design aspects.”
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 64 06/06/2018 16:26:28
©BSRIA
4.1.4 Obtain final quotations for incoming services based on final agreed building loads. Define extent of incoming services
4.1.5 Seek utility company comments on the spatial requirements and builders’ work associated
with the provision of incoming services.
Client liaison (briefing, handover, surveys)
4.2.1 Prepare the building services Employers Information Requirements in accordance with PAS As per PAS 1192-2
1192-2.
4.2.2 Prepare pre-contract BIM Execution Plan for building services installation (as required by As per PAS 1192-2
procurement route).
4.2.3 Advise on an appropriate method of procuring maintenance expertise.
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 65 06/06/2018 16:26:29
STAGE 4
66 |
Some activities in RIBA Stage 4 may continue after the start of the project’s construction stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 66 06/06/2018 16:26:29
©BSRIA
Where items or manufacturers differ from provisional selections ensure they are fully
compatible with all the other system parameters, components and design requirements.
4.4.7 Advise whether the proposed alternative items or manufacturers comply with the selection
criteria.
| 67
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 67 06/06/2018 16:26:29
STAGE 4
68 |
Some activities in RIBA Stage 4 may continue after the start of the project’s construction stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
4.4.8 Advise whether the proposed alternative items or manufacturers are acceptable.
4.4.9 Re-evaluate all parts of the services design which may be affected by acceptance of
alternative items or manufacturers.
4.4.10 Re-evaluate all parts of the architectural or structural design which may be affected by
acceptance of alternative items or manufacturers.
4.4.11 Amend the building services design to incorporate agreed alternative items or
manufacturers.
4.4.12 Prior to confirming agreed final fixed costs with the client, agree final equipment selections
and manufacturers.
4.4.13 Monitor the specialist design input for compliance with the design intent.
4.4.14 Evaluate the impact of the specialist design on those parts of the overall design that are
provisional.
4.4.15 Monitor the ongoing progress of the procurement, manufacture, installation and
commissioning of all plant items.
4.4.16 Review all plant and equipment incorporated into the works with respect to safe
maintenance and access in compliance with current legislation.
Mechanical design
4.5.1 Determine parameters of flues to incorporate the requirements of the plant manufacturer,
building control, environmental health officer and current legislation such as the Clean Air
Act.
4.5.2 Finalise detailed design calculations for all mechanical services being included in the See Appendix B for specific services
technical design in accordance with recognised national standards.
4.5.3 Determine detailed flue, duct and pipe sizes and routes.
4.5.4 Following equipment procurement, modify distribution systems and equipment capacities
as may be required as a result of coordination (4.3.25).
4.5.5 Design all necessary facilities for flushing, and commissioning.
4.5.6 Size, select and determine final locations of commissioning sets based on coordination of
procured equipment (4.3.25).
©BSRIA
4.5.7 Carry out final sizing of sections of ductwork between terminal units and diffusers to ensure
the specified acoustic criteria and duct velocities.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 68 06/06/2018 16:26:29
©BSRIA
4.5.11 Check system water capacities and quantities of chemical additives based on the final Suggest checker is independent person
equipment selection. from selector
4.5.12 Carry out final detailing of drain and vent points.
4.5.13 Carry out final selection of all terminal devices.
4.5.14 Carry out final selection of pressurisation units and expansion vessels.
4.5.15 Detailed design and sizing of refrigerant pipework between items of equipment provided
under the contract works based on the final equipment selection and coordinated working
drawings.
4.5.16 Select and confirm location of fire dampers and any other fire-stopping for mechanical
4.6.2 Determine detailed cable and containment sizes, switchgear sizes and locations, control
panel locations, user equipment sizes and locations, and sensor locations for small power,
lighting, high voltage systems, and metering.
| 69
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 69 06/06/2018 16:26:29
STAGE 4
70 |
Some activities in RIBA Stage 4 may continue after the start of the project’s construction stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
4.6.3 Determine approximate sensor locations, control panel locations for fire safety and security
systems.
4.6.4 Design automatic controls systems as required to meet the operational, functional and spatial
requirements of the specification.
4.6.5 Determine control strategy for lighting.
4.6.6 Design fixing, connection, earthing and bonding details as required for final installation of
lightning protection systems.
4.6.7 Modify distribution systems and equipment capacities as may be required as a result of Stage
4 coordination with intended or procured equipment.
4.6.8 Verify spatial requirements for cable pulling and installation.
4.6.9 Verify cable sizes for primary electrical supply based on coordination of procured equipment
(4.3.25) and cable lengths.
4.6.10 Verify cable sizes for specialist systems based on coordination of procured equipment Such as fire alarm, datacomms, CCTV, and
(4.3.25) and cable lengths. access control
4.6.11 Select and confirm location of fire-stopping for electrical systems.
4.6.12 Check control panel cable entry and exits are possible in the final location and that safe
operating and maintenance clearances are provided.
4.6.13 Check compatibility of building services plant and equipment with the controls systems.
4.6.14 Carry out design and incorporation of all interfaces (including relays or other devices or
modifications to hardware or software).
4.6.15 Incorporate final information for electrical systems into the design via schedules or BIM
objects, including control addresses for lighting and fire alarm systems, BMS points.
4.6.16 Design review. See section 3.8 of BG 6
Public health design
4.7.1 Finalise detailed design calculations for all public health services being included in the See Appendix B for specific services
technical design in accordance with recognised national standards.
4.7.2 Determine detailed pipe sizes and routes for gravity and pumped drainage systems.
4.7.3 Determine final positions of cast-in drainage gullies ensuring coordination with structural
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 70 06/06/2018 16:26:29
©BSRIA
4.7.7 Verify storm water discharge flow rate satisfies planning and statutory authority
requirements including SuDS.
4.7.8 Determine detailed routing of pipework and drainage to/from risers.
4.7.9 Carry out detailed design of pipework gradients for builders’ work and coordination. Includes domestic and waste drainage
(gravity/pumped), surface drainage and
condensate runs
4.7.10 Modify distribution systems and equipment capacities as may be required based on
coordination of procured equipment (4.3.25).
4.7.11 Make allowance for anchors, guides and provision for movement of services and systems due
4.8.3 Identify and incorporate into system designs the essential components and features For example, including test points
necessary to enable the proper commissioning of building services (including preparation).
4.8.4 Review the commissioning plan.
4.8.5 Update the commissioning plan.
4.8.6 Review proposals and method statements from prospective commissioning specialist(s).
| 71
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 71 06/06/2018 16:26:29
STAGE 4
72 |
Some activities in RIBA Stage 4 may continue after the start of the project’s construction stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
4.9.15 Provide information for Construction Phase Plan as per CDM Regulations.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 72 06/06/2018 16:26:30
©BSRIA
(agreed/procured) equipment.
4.9.33 Provide coordinated reflected ceiling plans based on agreed architectural information for all
components.
4.9.34 Provide coordinated room elevations based on agreed architectural information for all
components.
| 73
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 73 06/06/2018 16:26:30
STAGE 4
74 |
Some activities in RIBA Stage 4 may continue after the start of the project’s construction stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 74 06/06/2018 16:26:30
©BSRIA
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 75 06/06/2018 16:26:30
STAGE 4
76 |
The technical design model can be developed to one or more levels of definition during Stage 4, to suit the chosen procurement route. If a
client wishes a designer to deliver a coordinated-generic object model but not the preceding feasible-generic object model then this has to
be clearly indicated in pro-forma 4 and/or Appendix B.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Tolerances for technical design models should be agreed between the recipient and the author before technical design starts, with reference
to other members of the project team as appropriate.
Not all the model variants defined below need to be delivered. This will be decided depending on the procurement route and the client’s
requirements.
General definition for feasible-generic General definition for coordinated- General definition for coordinated-specific
Technical Design model generic Technical Design model Technical Design model
A model showing detailed building A model showing detailed building A model showing detailed building services
services designs, with locations and sizes services designs, with locations and designs, with precise locations and sizes
of all items of plant, pipes, ducts and sizes of all items of plant, pipes, ducts of all items of plant, pipes, ducts and
cable containment using generic objects and cable containment using generic cable containment using specific objects
in positions that are feasible for building objects in positions that have been representing actual intended or procured
services contractor and trade contractor spatially coordinated between separate plant and equipment in positions that
pricing and for installation without major engineering services and also with have been spatially coordinated between
re-routing. This is analogous to the level architecture and structure. The model will separate engineering services and also with
of detail in Technical Design drawings not show hangers or supports apart from architecture and structure. The model will
using generic objects. builders’ work items. This is analogous to not show hangers or supports apart from
the level of detail in Coordinated working builders’ work items but spatial allowances
drawings, but using generic objects. should be included. This is analogous to
the level of detail in Coordinated working
drawings, but using procured or intended
objects.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 76 06/06/2018 16:26:30
©BSRIA
Typical object parameters to add to or substitute for those from Stages 2 and 3 (for generic or specific objects as appropriate)
would include:
•• Builders’ work information (holes and pockets to be shown as separate from the services equipment or components that pass through
or sit in them)
•• System reference
Costing The model may be used to develop cost estimates based on detailed quantities and estimated
costs of actual or generic elements (including labour, materials, prelims, overheads and profit)
Programme The model may be used to show the timescale of installation of detailed systems and
components.
BG 6/2018
| 77
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 77 06/06/2018 16:26:30
STAGE 4
78 |
Drawings showing the intended locations of plant items and service routes in such detail as to indicate the design. The main features of
detailed design drawings should be as follows:
•• Plan layouts should be to a scale of at least 1:100. Plant areas should be to a scale of at least 1:50, and should be accompanied by cross-
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
•• The drawing will not indicate the precise position of services, but it should nevertheless be feasible to install the services within the
general routes indicated. It should be possible to produce coordinated working drawings or installation drawings without major re-
routing of the services. The design must also consider procurement and installation methodologies.
•• The drawings should include all the functional, sensing, control and measuring components that are to be installed. This includes main
plant, distribution, inline equipment, terminal plant and components, control components.
•• Symbols and line conventions should be in accordance either with a recognised standard, such as ISO or BS, or a supplied legend.
•• The drawings should be labelled with appropriate pipe, duct, busbar, cable sizes and fault levels, pressures and flow rates. These details
may be subject to adjustment during construction stage.
•• The major components indicated on the schematic drawing should be identified for cross-referencing purposes.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 78 06/06/2018 16:26:30
©BSRIA
The critical criterion with builders’ work information is that it includes all openings (or other provisions) which significantly affect structure, fabric
or external works. The minimum dimensions of these openings need to be agreed among the project team.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
•• Plan layouts should be to a scale of at least 1:50 and be accompanied by cross-sections to a scale of at least 1:20 for all congested areas.
•• The drawing should make allowance for installation, commissioning, maintenance and replacement working space and methodologies.
•• The spaces between pipe and duct runs shown on the drawing should make allowance for the service at its widest point. Insulation,
standard fitting dimensions and joint widths should therefore have been allowed for on the drawing.
•• The drawing should indicate positions of main fixing points and supports where they have significance to the structural design or spatial
constraints.
BG 6/2018
| 79
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 79 06/06/2018 16:26:30
STAGE 4
80 |
SAMPLE INFORMATION:
Reference: SG3/145
Type: 3 -SLOT LINEAR
Air Flowrate: 70 L/s
System Type: Supply Air
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 80 06/06/2018 16:26:34
©BSRIA
Recessed downlight
HL_Smoke Detector
1G Switched Socket
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 81 06/06/2018 16:26:35
STAGE 4
82 |
SAMPLE INFORMATION
Type: A type FCU
Reference: FCU3/77
(right hand side connection box)
Duty: 8 kW
Fresh Air: 80 L/s
LTHW Flowrate: 0.095 L/s
CHW Flowrate: 0.198 L/s
Notes:
Ceiling mounted elements are
aligned to ceiling grid at this stage
Wall mounted elements are
coordinated with wall elevations at
this stage
.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 82 06/06/2018 16:27:01
©BSRIA
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
SAMPLE INFORMATION
Type: A type FCU
Reference: FCU3/88
(left hand side connection box)
Duty: 8 kW
Notes:
FCU model changed in office
room to reduce number of pipe
BG 6/2018
connections to install
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 83 06/06/2018 16:27:31
STAGE 4
84 |
D D
50 mm CHWR
50 mm CHWF
SG3/149 40 mm LTHWR
40 mm LTHWF
VCD
54 mm Dia. WVP Number of WHBs: 2
SG3/148 FCU3/77
50 mm CHWF
40 mm LTHWR
40 mm LTHWF
SG3/147
100 mm Dia. SVP Number of WCs: 2
50 mm CHWR
VCD
CTA FD
VCD
15 mm Condensate drain
E E
Connections SG3/059 SG3/058 SG3/057 EG3/003 SG3/056 SG3/055 SG3/054 EG3/004 SG3/053 SG3/052 SG3/051
capped off for
future use
400x200
SG3/146
40 mm CHWR
40 mm CHWF
32 mm LTHWR
32 mm LTHWF 25 mm CHWR
FCU3/78 FCU3/79 25 mm CHWF FCU3/80
20 mm LTHWR
VCD 20 mm LTHWF
200ø
SG3/145 FCU3/76
200ø
25 mm LTHWF 25 mm LTHWF
200ø
200ø
25 mm LTHWR 25 mm LTHWR
32 mm CHWF
VCD
25 mm CHWF
VCD
VCD
VCD CHWR
32 mm 25 mm CHWR
200ø 300x200
SG3/144 VCD
75 mm Sanitary
VCD
VCD
200ø
200ø
F F
-
SG3/143 ---
FCU3/73 15 mm Condensate drain
UP
SG3/142 FCU3/74 FCU3/75
DN
2 3 4
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 84 06/06/2018 16:27:37
©BSRIA
2 3 4
AD. ADE
. AD. ADE
.
2 2 2 2
B
11G
D
2D
AD AD EXIT AD AD B
DB/LTG/05
L32
B DB/LTG/05
AD ADE AD ADE
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
AD AD AD AD
E E
.
B 2
2
B. B B B B
2
2
DB/LTG/05
L14
AD ADE AD ADE .AD ADE AD ADE AD
2
2
EXIT
DB/LTG/05
EXIT L23
2
DB/LTG/05
L13
B EXIT B B
2D
F 11G 2 F
2
DB/LTG/05
L24
.
AD ADE AD ADE ADE AD
. 2
B B
2
DB/LTG/05 UP
L31
2
AD AD AD AD. 2 B B AD AD
DN
BG 6/2018
2 3 4
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 85 06/06/2018 16:27:38
STAGE 4
86 |
D D
DB/LTG/05
L34
DB/LTG/05
Staff Accommodation
22-5-1684 WC Male WC Female
22-2-1671 22-2-1676
Service Riser
22-2-1664
E E
Admin Office
22-5-1685 DB/LTG/05
L15
F F
Store
22-5-1686
UP
DN
2 3 4
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 86 06/06/2018 16:27:38
©BSRIA
Level 6
22500
PH Pipework zone
Pipework main zone
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Secondary pipework
not in final positions
at this stage, so Recessed Ceiling Light
minor clashes are
Level 5
18750
BG 6/2018
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 87 06/06/2018 16:27:38
STAGE 4
88 |
AD ADE AD ADE
B
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
D D
AD AD EXIT AD AD B
VCD
FCU3/77
AD ADE AD ADE
VCD
CTA FD
B
VCD
AD AD AD AD
E E
B
B B B B B
AD ADE AD FCU3/78
ADE AD FCU3/79
ADE AD ADE FCU3/80 AD
VCD
FCU3/76
EXIT
EXIT
VCD
VCD
VCD
VCD
2
AD AD VCD AD AD AD AD AD AD AD
PR-OR-ZZ-04-DR-M-07
VCD
VCD
B EXIT B B
3
F PR-OR-ZZ-04-DR-M-07
F
B B
FCU3/74 FCU3/75
AD AD AD AD B B AD AD
G G Note:
Cables in ceiling not
1 2 3 4 shown for readibility.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 88 06/06/2018 16:27:41
©BSRIA
Section A 2 3
2
Section B PR-OR-ZZ-04-DR-M-07
E
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 89 06/06/2018 16:27:42
STAGE 4
90 |
3 4 5 6 7
C
1300 1100 1300
1600x300
N/W 1300 1300
1300
x600
x1100 1300x300 x800 x1100 Supply
Tenants x1000 x1100
E zone
Electrical riser
goods area
Pipes
1300x300
1100 Future
x500 W zone E zone
Down
1300x300
Lift 1 Café
Pipes
W zone 1100 vent
Goods lift x800
Extract Extract
Up
1200
x600
1300x West zone Roof power 1300
E zone
1100 connections x1100
D Lift 2
1500
x600
1300x200
Supply
WC zone
Pipes
WC Zone Lift 3
1800 1600x300
1300 1300
1300
x600
1300
x700
x900
x1100 x1100 1300x300
E
Supply Extract Extract Supply Pipes Future S/E
W zone WC zone S zone S zone S zone S zone tenants
electrical riser
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 90 06/06/2018 16:27:42
©BSRIA
EOL EOL
SD SD HD HD
MCP
SOUNDER
FAI DRCP DI CONTROLLER
TP EOL EOL
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
SD SD HD HD
MCP
FAI PLANT
ASD SOUNDER
FAI FARP DRCP DI CONTROLLER
LEGEND
LEVEL 1
SD
SMOKE DETECTOR
TP EOL EOL
HD
HEAT DETECTOR
TENDER ISSUE
STAGE 4
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 91 06/06/2018 16:27:42
STAGE 5
92 |
“During this stage, the building is constructed on site in accordance with the Construction Programme. Construction includes the
erection of components that have been fabricated off site.
The procurement strategy and/or the designer’s specific Schedule of Services will have set out the designer’s duties to respond to Design
Queries from site generated
in relation to the design, to carry out site inspections and to produce quality reports.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 92 06/06/2018 16:27:42
©BSRIA
5.1.4 Apply for G59 interfaces (for connection of onsite electricity generation to the grid).
Client liaison (briefing, handover, surveys)
5.2.1 Oversee the instruction of the client’s staff (FM team and end-users as appropriate) in the
use, operation and maintenance of the installations.
5.2.2 Prior to handover, instruct the client’s staff (FM team and end-users as appropriate) in the
use, operation and maintenance of the installations in advance of handover.
5.2.3 Examine and comment on the contents of the operating and maintenance information in
order to ensure compliance with the specified requirements.
5.2.4 Modify and update operating details to reflect commissioning results.
5.3.1 Prepare accredited as-constructed energy consumption information for Building Regulations
and (if relevant) the actual Energy Performance Certificate.
5.3.2 Update building services information models in response to changes made during
construction, installation and commissioning.
| 93
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 93 06/06/2018 16:27:43
STAGE 5
94 |
Some activities that start in the project’s technical design stage may continue in parallel with this stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Electrical design
Commissioning
5.8.1 Comment on the adequacy of systems for commissioning as detailed on specialists’ drawings
and manufacturers’ shop drawings prior to actual manufacture at works.
5.8.2 Attend commissioning meetings as necessary.
5.8.3 Arrange and chair commissioning meetings as necessary.
5.8.4 Monitor the progress of commissioning and testing of all software programming, systems
and plant, including assessment of whether installations meet the original (or amended)
design intent.
5.8.5 Conduct mock-up performance tests.
5.8.6 Conduct pre-commissioning works (verification of installation works and static tests).
5.8.7 Commission all systems to agreed method, logic and programme, and in accordance with
the commissioning specification. Record the results.
5.8.8 Attend witness testing and commissioning of off-site manufactured assemblies at Usually during manufacture
manufacturers’ premises.
5.8.9 Demonstrate that the overall and complete systems perform correctly in the required
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 94 06/06/2018 16:27:43
©BSRIA
5.9.2 Provide final installation details, including dimensions, of automatic control panels to suit the
detailed requirements of the agreed supplier of the controls equipment.
5.9.3 Provide detailed BMS point schedules, wiring schematics, control panel labelling details and
equipment schedules for the complete works.
5.9.4 Provide detailed electrical wiring diagrams of all equipment supplied showing all
interconnections between equipment to enable all necessary wiring to be undertaken.
5.9.5 Provide installation model.
5.9.6 Provide installation drawings.
5.9.7 Provide builders’ work details.
5.9.14 Provide operating and maintenance manuals. Identify specialist author for production
5.9.15 Provide as-built model or final project information model (as per PAS 1192-2) incorporating
all changes made during installation.
5.9.16 Provide record drawings incorporating all changes made during installation.
| 95
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 95 06/06/2018 16:27:43
STAGE 5
96 |
Some activities that start in the project’s technical design stage may continue in parallel with this stage.
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
5.9.17 Provide building manual(s) and/or building user guide(s) and/or building log book(s) in Including system completion certificates
accordance with the requirements of the specification and the Building Regulations. and instructions on controls, energy
saving and water saving features.
5.9.18 Provide planned preventative maintenance schedules.
5.9.19 Provide operation and maintenance information in accordance with the specified
requirements.
5.9.20 Provide comments on draft record information and operating and maintenance manuals.
5.9.21 Provide technical guide for the facilities management team.
5.9.22 Provide recorded water, gas and electricity meter readings on completion of the works.
5.9.23 Provide pre-handover defects schedule. Usually these defects are expected to be
rectified before handover
5.9.24 Provide site visit reports.
5.9.25 Provide comments on proposals submitted by the building services contractors and/or
trade-contractors.
5.9.26 Sign off design and equipment changes proposed.
5.9.27 Provide comments on programmes.
5.9.28 Provide as-installed information to the Environmental Assessment Method Assessor.
5.9.29 Provide report on agreed outcomes following participation in any Soft Landings process.
Amended and additional activity descriptions
5.10.1 <insert text here>
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 96 06/06/2018 16:27:43
©BSRIA
Typical object parameters to include along with geometry at this stage would include:
Typical object parameters from Stage 4 should be substituted with data relating to the installed objects.
Analysis The model may be analysed for performance of approved selected systems and components by
Estimating Costs are based on the actual costs of specific elements at purchase.
Programme The model may be used to show the time scale of installation of detailed systems and
components, including methods of construction and installation sequences.
BG 6/2018
| 97
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 97 06/06/2018 16:27:43
STAGE 5
98 |
Drawings based on the Technical Design drawings or coordinated working drawings with the primary purpose of defining that
information needed by the tradesmen on site to install the works.
The main features of installation drawings should be as per coordinated working drawings, plus:
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
•• Allowances should be made for inclusion of all supports and fixings necessary to install the works.
•• The drawing should make allowances for installation details provided from manufacturers’ drawings.
•• Allowances should be made for plant and equipment. This includes any alternatives to the designer’s original specified option that
have been chosen.
•• Space should be shown for associated support systems, installation methodologies and access for maintenance and replacement
Where no coordinated working drawings have been produced, the installation drawing should include coordination.
Unless agreed otherwise, the following builders’ work details can be marked out on site:
Builders’ work details carry forward and confirm or refine the structurally significant items from the builders’ work information, and also
introduce new items that are not structurally significant, such as plinth dimensions for the actual plant items ordered.
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 98 06/06/2018 16:27:43
©BSRIA
Tolerances for as-built models should be agreed between the recipient and the author before installation starts, with reference to other
members of the project team as appropriate. Different tolerances might be agreed for visible and hidden components.
Typical object parameters to include along with geometry at this stage would include:
•• Model numbers and serial numbers of actual components and equipment installed
•• Results from commissioning works (flow-rates or set points for all control equipment)
The model or associated information should indicate if any installed equipment is oversized from the original design intent, perhaps because of
supply problems, but where the originally specified size should be installed when the equipment is replaced at the end of its life expectancy.
| 99
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 99 06/06/2018 16:27:43
STAGE 5
100 |
Drawings showing the building and services installations as installed at the date of practical completion. The main features of
the record drawings should be as follows:
•• The drawings should be to a scale not less than that of the installation drawings.
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
•• The drawings should show locations of all the mechanical, electrical and public health systems and components installed
including ducts, pipes, cables, busbars, plant items, pumps, fans, valves, dampers, control devices, strainers, terminals,
electrical switchgear and components, security and fire sensors and control equipment.
•• The drawings should be labelled with appropriate pipe, duct and cable sizes, pressures and flow rates.
•• The drawings should have marked on them positions of access points for operating and maintenance purposes.
•• The drawings should not be dimensioned unless the inclusion of a dimension is considered necessary for location.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 100 06/06/2018 16:27:43
©BSRIA
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 101 06/06/2018 16:27:45
STAGE 5
102 |
1261
271
200ø
2107
SG3/149
1732
1460
SG3/148
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
1073
400x200
4618
193
SG3/147 200ø 40 mm LTHWR
50 mm CHWR
16 mm Condensate drain
1073
97
102
40 mm LTHWF
50 mm CHWF
200ø
2106
SG3/146
1060
200ø FCU3/77 1338 600x300 2000x1250
SG3/145
1061
782
400x200
200ø
193
SG3/144 252 453 940 1260 1160 1004 1491 164 1360 1860 1125 995 1360 2634 1011
1038
349
152 121
102
97
200ø 107 152 200ø 200ø
200ø 200ø 200ø 200ø 200ø 200ø 200ø
SG3/143 2106
1460
140ø
200ø 200ø
400x200
143
97
102
97
97
1692 79
15 mm CHWF
15 mm LTHWF
1693
1672
1
15 mm CHWR
003 15 mm LTHWR
200ø 243 243 530
608
1905
122
596
1467
667
FCU3/73 96
1854
122
200ø
918 546
1008
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 102 06/06/2018 16:27:52
©BSRIA
Raised Floor -7
26452
Level 7
152 136122122 597 122122 26250
245
Pipework main runs & crossover zones
182
through castellations in beams 15 mm CHWR
15 mm LTHWR
15 mm LTHWR
323
15 mm CHWR
Ductwork distribution below structural beams
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 103 06/06/2018 16:27:55
STAGE 5
104 |
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 104 06/06/2018 16:27:56
©BSRIA
5 6 7
D
200 850 1000 x 300
Supply
650
WC zone I.C.T. data
600 Lift 2
x Building information data
1500
600 x 400
555
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
650
90
350
300 1600 x 300
1300 x 300
600 1100 1100 700
x x 1450 x x
300
1450
1300 1300 1300 1300
1400
1200
400
400
E
STAGE 5
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 105 06/06/2018 16:27:56
STAGE 6
106 |
“The project team’s priorities during this stage will be facilitating the successful handover of the building
in line with the Project Programme and, in the period immediately following, concluding all aspects of the
Building Contract, including the inspection of defects as they are rectified or the production of certification
required by the Building Contract.
Other services may also be required during this period. These will be dictated by project specific Schedules
of Services, which should be aligned with the procurement and Handover Strategies. Tasks in relation to the
Handover Strategy can be wide-ranging and may include:
•• attending Feedback workshops − considering how any lessons learned might be applied on future
projects
•• undertaking tasks in relation to commissioning or ensuring the successful operation and management
of the building.”
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 106 06/06/2018 16:27:56
©BSRIA
A B C D E Z
General obligations, external liaison (statutory bodies, utilities)
6.2.3 On site attendance by aftercare team during first eight weeks of occupation.
6.2.4 Hold meetings/workshops with end-users/occupiers during the first eight weeks of
occupation.
6.2.5 Hold regular meetings with user representatives during Year 1 of occupation. Specify frequency, e.g. every 3-4 months
in Year 1
6.2.6 Review building performance against energy targets during Year 1 of occupation. Specify frequency, e.g. every 3 months
6.2.7 Hold end-of-year reviews of the general and environmental performance of the building.
6.2.8 Visit site to train and/or transfer information about the use of the building services to the
facilities management team and the building occupiers.
Mechanical design
BG 6/2018
Electrical design
| 107
STAGE 6
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 107 06/06/2018 16:27:56
STAGE 6
108 |
Allocated to …
Ref Design activity in connection with building services L=Lead, S=Support, R=Review Comments
A B C D E Z
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Commissioning
6.8.1 Carry out seasonal commissioning from practical completion including environmental Define timetable
testing and monitoring.
6.8.2 Attend seasonal commissioning activities carried out by others.
Deliverables – including drawings, specifications, reports
6.9.1 Provide a reviewed and updated list of defects identified during post completion audit.
6.9.2 Provide COBie tables for BIM Level 2 Information Exchange 6.
6.9.3 Provide written reviews of energy use and system performance (as defined in the Soft
Landings framework).
6.9.4 Provide outturn cost analysis.
6.9.5 Provide updated as-built/project information model incorporating defect rectification and
any changes resulting from Year 1 aftercare.
6.9.6 Provide updated record drawings incorporating defect rectification and any changes
resulting from Year 1 aftercare.
6.9.7 Provide lessons learned report.
6.9.8 Provide report on any defects reported during the liability period.
6.9.9 Provide comments on record information including operating and maintenance manuals.
6.9.10 Provide report on agreed outcomes following participation in any Soft Landings process.
Amended and additional activity descriptions
6.10.1 <insert text here>
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 108 06/06/2018 16:27:56
©BSRIA
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
STAGE 6
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 109 06/06/2018 16:27:56
STAGE 7
110 |
“This is a new stage within the RIBA Plan of Work. It acknowledges the potential benefits of harnessing the project design
information to assist with the successful operation and use of a building.
While it is likely that many of the handover duties will be completed during Stage 6, prior to conclusion of the Building Contract,
certain activities may be required or necessary afterwards. These should be confirmed in the relevant Schedule of Services.
While the end of a building’s life might be considered at Stage 7, it is more likely that Stage 0 of the follow-on project or
refurbishment would deal with these aspects as part of strategically defining the future of the building.”
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 110 06/06/2018 16:27:56
©BSRIA
Mechanical design
Electrical design
Commissioning
STAGE 7
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 111 06/06/2018 16:27:57
112 |
information production
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
The purpose of Appendix B is to provide a consolidated schedule of deliverables for the project. This proforma brings together all
the deliverables selected in the various Appendix A proformas and presents them in a single place. This proforma is in a spreadsheet
format to allow editing to suit the particular requirements, and modification of the format to provide more focussed elements to be
displayed.
As stated earlier in this document, it is essential that the deliverables identified in Appendix B match exactly those already selected
within the Appendix A proformas. A difference between the two could lead to conflict over who is required to deliver what.
This proforma is arranged into three areas, representing the types of deliverable to be produced – drawings, models and other
information, and this principle is shown in Figure 6. However, the actual proforma spreadsheet is too large to include here so is
available via the following link www.bsria.co.uk/goto/bg6.
When completing or reviewing a completed Appendix B proforma, look for any hidden columns or rows.
Step 1 Decide which classification of building services systems you wish to use for your project (BSRIA list, Uniclass 2015 or NRM)
and select the appropriate blank proforma.
Step 2 Complete the project-specific details in rows 3 to 5 and add any additional details, description, status needed, etc.
Step 3 Expand or condense the system breakdown using the + and – buttons in the outlining margin of the spreadsheet to show
the required amount of detail.
Step 4 Review the standard deliverables across rows 7 and 8. Any that are not required should be marked N/A (not applicable)
or similar in row 10. Any additional deliverables that are to be included should be described in the grey-shaded columns
at the right-hand edge of the spreadsheet.
Step 5 Complete the Responsible Party and Date columns for each deliverable for each relevant building services system.
©BSRIA
Any deliverable that is required for a particular system should be marked N/A or similar. LOD and LOI columns may be
completed for model deliverables if required.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 112 06/06/2018 16:27:57
©BSRIA
DELIVERABLES
Models Drawings Informa�on
1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7
Mechanical
S Electrical
T
E
M
S
Public Health
BG 6/2018
| 113
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 113 06/06/2018 16:27:57
114 |
Examples of using BG 6 in four design responsibility scenarios have been provided electronically at www.bsria.co.uk/goto/bg6. These
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
examples of proformas from appendices A and B should be used for guidance only. The user may need to complete their particular
proformas in a different way in order to reflect their desired allocation of design responsibilities.
Extracts from these examples are included here to illustrate some key principles in the completion of the proformas – indicated by notes
in green.
Example 1 A client commissioning a multi-disciplinary feasibility study for a prospective project (Stages 1 and 2 only)
Example 2 A design and build project with the client-appointed building services consultant delivering a Developed Design
at the end of Stage 3 and the building services contractor appointed between Stages 3 and 4. This contractor
appoints its own building services consultant to continue much of the Stage 4 design work and the client-appointed
building services consultant retains a reviewing role
Example 3 A project with the client-appointed building services consultant delivering a feasible-generic Technical Design
during Stage 4. The contractor prices this design and then when appointed takes responsibility for co-ordinating
the design on the basis of actual equipment selected for installation during the remainder of Stage 4 with the
consultant reviewing equipment proposals for compatibility with the building services design philosophy
Example 4 A project with the client-appointed building services consultant delivering a coordinated-generic Technical
Design during Stage 4. The contractor prices this design and then when appointed makes proposals for alternative
equipment, to be reviewed by the consultant. The contractor amends the coordinated generic design to
incorporate approved alternative equipment
Examples 3 and 4 are shown side-by-side in a modified version of Appendix A proforma 4 to illustrate the differences in allocation of
design activities in these 2 cases.
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 114 06/06/2018 16:27:57
©BSRIA
Example 1 – Appendix A
This item has been rewritten
in sub-section 10
A DESIGN FRAMEWORK FOR BUILDING SERVICES 5TH EDITION
Allocation of activity
leadership (L) and support (S)
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 115 06/06/2018 16:27:57
116 |
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 116 06/06/2018 16:27:57
©BSRIA
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 117 06/06/2018 16:27:57
118 |
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 118 06/06/2018 16:27:57
©BSRIA
Example 2 - Appendix B
BG 6-2018 A Design Framework for Building Services Portrait 180518 Part 2a.indd 119 06/06/2018 16:27:57
References
References
1. RIBA Plan of Work 2013
This is available as a pdf, an Excel spreadsheet, and a customisable online version. An
overview document is also available, which provides detailed guidance on each stage. All
can be downloaded for free from www.ribaplanofwork.com.
3. BIP 2207 Building information management. A standard framework and guide to BS 1192.
Available from shop.bsigroup.com
4. PAS 1192-2:2013 Specification for information management for the capital/delivery phase of
construction projects using building information modelling.
Available as a free download from shop.bsigroup.com
5. BSRIA BG 60/2015 The BIM Roadmap – A building owner’s guide to implementing BIM.
Available from www.bsria.co.uk (free download for BSRIA members)
7. Gower Handbook of Project Management Fourth Edition (2008) Edited by J. Rodney Turner.
9. BSRIA BG 27/2011 Pitstopping – BSRIA’s reality checking process for Soft Landings.
Available from www.bsria.co.uk (free download for BSRIA members)
120 | BG 6/2018 A DESIGN FRAMEWORK FOR BUILDING SERVICES 5th EDITION ©BSRIA
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 120 06/06/2018 16:24:01
Bibliography
Bibliography
The following publications are not referenced in this guide. However, they provide some useful
information for further reading.
BSRIA publications are available from www.bsria.co.uk, with free downloads for BSRIA members.
CIBSE publications are available from www.cibseknowledgeportal.co.uk.
BSRIA BG 9/2011 Rules of Thumb - Guidelines for building services (5th Edition)
BSRIA BG 37/2011 Utility Connections and Diversions – Planning, design and installation
BSRIA TN 9/92 Space and weight allowances for building services plant - inception stage design
Client liaison
BSRIA BG 9/2004 Choosing building services. A practical guide to system selection
Improving Public Services Through Better Construction (National Audit Office, 2005)
Team liaison
CIBSE Guide F Energy Efficiency in Buildings (2012)
BSRIA / Steel Construction Institute IEP 2/2003 Services Coordination with Structural Beams -
Guidance for a defect-free interface
©BSRIA A DESIGN FRAMEWORK FOR BUILDING SERVICES 5th EDITION BG 6/2018 | 121
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 121 06/06/2018 16:24:01
Bibliography
Mechanical design
CIBSE Guide A Environmental Design (2006)
BSRIA BG 4/2007 Design checks for HVAC - A quality control framework (Second edition)
Electrical design
CIBSE Guide K Electricity in Buildings (2005)
BSRIA BG 3/2006 Design Checks for Electrical Services - A quality control framework for electrical
engineers
BSRIA BG 2/2006 Design checks for Public Health Engineering - A quality control framework for
public health engineer
Commissioning
BSRIA BG 49/2013 Commissioning Air Systems
122 | BG 6/2018 A DESIGN FRAMEWORK FOR BUILDING SERVICES 5th EDITION ©BSRIA
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 122 06/06/2018 16:24:01
Full terms and conditions can be found at www.bsria.co.uk/terms.
Consent is granted to users of this publication to reproduce and modify the proformas in appendices A and B for use on their
projects and otherwise on and subject to the following terms:-
• You must not use any illustrations, photographs, or any graphics separately from any accompanying text.
• Our status as the owners of copyright in the content must always be acknowledged. In the case of this publication, unless
otherwise agreed with BSRIA, all extracts must carry the following acknowledgement: “Reproduced from BSRIA BG 6/2018 A
Design Framework for Building Services 5th edition”.
• You must not use any part of the content for any purpose(s) other than those set out above without first seeking a licence
to do so from BSRIA.
• If you reproduce and modify any such content in breach of these terms of use, or otherwise breach any of our intellectual
property rights, your rights under this Limited Licence will cease immediately.
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 123 08/06/2018 11:33:01
Engineering services: Test, compliance and consultancy support services for
clients, designers, constructors, manufacturers and facilities managers
Instrument solutions: Hire, sales and calibration of instruments
Market intelligence: Off the shelf reports, bespoke studies and management
consultancy for global markets
Information and membership: Bookshop, library, training, networks and events
Head Office: Old Bracknell Lane West, Bracknell, Berkshire RG12 7AH UK
T: 0800 254 5700 (UK) or +44 (0) 1344 465 600 | F: +44 (0) 1344 465 626
BSRIA North: 68 Walton Summit Road, Bamber Bridge, Preston PR5 8AQ UK
T: +44 (0) 1772 754 380
E: bsria@bsria.co.uk | W: www.bsria.co.uk
BG 6-2018 A Design Framework for Building Services - Part 1 and Part 3.indd 124 06/06/2018 16:17:16