The fair DPR has been checked in this office amounting

to Rs. 156.93 Lacs only on the basis of manuscript DPR already been
checked vide this office letter No. 9094-95 Dated 08.10.2021
amounting to Rs. 157.97 Lacs only.
If approved we may send the fair DPR in duplicate to
the E-in-c HPPWD Shimla-2 for accord of its approval from the
competent authority.
Placed below fair DPR in triplicate a/w drawings put up
for signatures/ further directions please.
The detailed status of the subject cited tender case is as
under:-
(i) Approval:- Rs. 1,89,44,800.00/- only vide E-in-C HPPWD Shimla letter
No. PW/PMGSY/WBP/AMP/2020-2021/4631-51 Dated 31.03.2021.
(ii) W/estimate:- Rs. 1,44,97,000.00/- only approved vide SE Hamirpur
letter No. 5094-95 Dated 26.07.2021.
(iii ) DNIT:- Rs. 1,44,97,000.00/- only
(iv) Date of opening of technical bid :-23.09.2021
(iiv) Date of opening of financial bid :-24.09.2021
The following 2 No. contractors/ firms have offered their
rated as under :-
Sr.No. Name of Contractor /firm Quoted
amount
1. Sh. Piar Chand Chauhan Govt. Contractor Rs.
1,28,72,300.00/-
i.e. 11.21%
below the
DNIT amount.
2. M/s S.S. Chauhans Pvt. Ltd. Govt. Contractor
Rs.1,39,30,000.00/-
3.91% below
The comparative statement has been checked and the rates/
overall amount quoted by the lowest contractor Sh. Piar Chand Chauhan
Govt. Contractor comes to Rs. 1,28,72,300.00/- only i.e. 11.21% below the
amount put to tender.
The justification statement has been checked in this office
amounting to Rs. 1,44,97,000.00/-only which is at par the amount put to
tender.
The rates/overall amount quoted by the lowest contractor is
well within the justification/sanctioned amount.
There is no unbalance amount quoted by the lowest
contractor.
If approved we may call the contractor for negotiation for
which time and date may kindly be fixed.
The complete original tender case a/w
justification/comparative statement put up for signatures/ further
directions please.
The status of the subject cited tentative financial
implication statement is as under:-
(i) A/A & E/S = Rs. 600.11 Lacs (Rs. 531.07 Lacs for construction part + Rs.
69.04
Lacs for maintenance part)
(ii)Awarded amount= Rs. 4,38,29,650.00/-( Rs. 3,94,92,814.00 for
construction
Part + Rs. 43,36,836.00 for maintenance
part)
Name of Contractor = Sh. Ashok Thakur Govt. Contractor
The tentative financial implication statement/extra item
statement including 2 No. extra items checked in this office amounting to
Rs. 4,85,32,695.00/- only having net variation in plus side for Rs.
(+)90,39,881.00/- only i.e 22.89% above the agreement amount of
construction part as well as extra item statement checked for Rs.
88,34,611.00/- only.
The rate for extra item No. (1) checked for Rs. 8544.20/-
only per cum and rate for item No.(2) checked for Rs. 3702.05/- only per
running meter.
The technical reason for variation in quantities as recorded
in the remarks column of the statement.
The undertaking of the contractor is not attached with the
statement.
The amount of the checked tentative financial implication
statement is well within the sanctioned amount of the work.
Placed below tentative financial implication statement in
duplicate a/w photocopy of agreement No. 11 of 2019-20 put up for
signatures/ further directions please.
The detailed status of subject cited DNIT as mentioned
below:-
(i) Approval :- The A/A has been accorded by the Pr. Secy. (PW) to the
Govt of H.P. vide letter No. PBW(B)F(5) 79/2016 Dated 17.08.2016 for Rs.
341.18 Lacs and E/S amounting to Rs. 50.00 Lacs only.
(ii) Working estimate :- The working estimate for said work has been
approved vide this office letter No. 9124-25 Dated 11.1.2021 amounting to
Rs. 2,99,00,304.00/- only.
The DNIT has been checked in this office amounting to Rs.
2,99,00,304.00/- only on the basis of approved working estimate.
Placed below DNIT in duplicate put up for signatures/ further
directions please.