TEST REPORT FOR 12-PM-102A

CLIENT HEAVY WATER PLANT (MANUGURU) PAGE NO. 1 of 2


PROJECT TESTING OF NUMERICAL RELAYS LOCATION MANUGURU DATE 01-04-2023

1. Location : SOUTH S/S PCC – 301 (SEC – B)


2. Tag No. & Panel No : 12-PM-102A & P15
3. Relay Details,

MAKE : EE
MODEL : CTMM58
SL.NO : M013738
SEC. CT RATIO : 5A
AUX. VOLTAGE : 220V DC/AC

4. Relay settings :

I1 40A
I2 10A
Io 1A
Ith 4A
Ith (Curve) 4(2tθ)
I1t 26.0A
I1t(Sec) 7.5 Sec

5. I1 & I2 Unit :

Set – I1 : 40A & I2 : 10A Time : Instantaneous


Unit Ref. Pickup (A) Injected (A) Opt. Time (Sec)
7,8 65.4 80.0 0.135
I1
9,10 65.0 80.0 0.106
7,8 15.3 20.0 0.110
I2
9,10 15.3 20.0 0.109

6. Io Unit :

Set : 1.0A Time : Instantaneous


Unit Ref. Pickup (A) Injected (A) Opt. Time (Sec)
Io 11,12 0.9 1.0 0.070

TESTED BY WITNESS/REVICED BY
M/S VOLTECH ENGINEERS PVT. LTD. M/S HEAVY WATER PLANT (MANUGURU)
NAME MUTHUSELVAM A NAME
DESIGNATION TESTING ENGINEER DESIGNATION
SIGN & DATE SIGN & DATE
TEST REPORT FOR 12-PM-102A

CLIENT HEAVY WATER PLANT (MANUGURU) PAGE NO. 2 of 2


PROJECT TESTING OF NUMERICAL RELAYS LOCATION MANUGURU DATE 01-04-2023

7. Ith Unit :

Set : 4A Time : 4(2tθ)


Thermal Curve Calculated Time (Sec)
Unit Ref. Selection Injected (A) Opt. Time (Sec)
Switch CTMM57 CTMM58
7,8 3(tθ) 16.35 4.0 16.0
Ith 7,8 4(2tθ) 16.35 8.0 32.0
7,8 5(4tθ) 16.35 16.0 64.0

8. I1(t) Unit :

Set : 26A Time : 7.50 Sec


Unit Ref. Injected (A) Opt. Time (Sec)
7,8 52.0 7.620
I1(t)
9,10 52.0 7.673

9. RESULT:
 Relay operations checked.
 Contacts were cleaned.
 Wire connections tightness checked.
 Relay module were cleaned.

TESTED BY WITNESS/REVICED BY
M/S VOLTECH ENGINEERS PVT. LTD. M/S HEAVY WATER PLANT (MANUGURU)
NAME MUTHUSELVAM A NAME
DESIGNATION TESTING ENGINEER DESIGNATION
SIGN & DATE SIGN & DATE