Engineering & Construction Project Management Expediting Unit
Engineering & Construction Project Management Expediting Unit
Project Management A5
Expediting Unit
PLANT/PROJECT AGRI
31060 (ENEL)
Supplier
Order/Contract no.
Sub-Supplier
4500929924/Version 0/ 2022-10-18 4211/MXJ
Order/Contract no.
Attachments (Att)
Nil
25/02/2023
(Signature)
1. Document control
Control of contract and related technical attachments and specifications, with attention to:
a) Purchase Order/Contract (shall be signed and supported by all necessary backup information);Available
b) Drawings (verify availability and state of approval); Available
c) Quality Control Plan;Available
Verify the presence of Change Orders, pending requests, derogations, or other points to clarify. Nil
3. Manufacturing progress
Verification and update of the Manufacturing Plan for every item, and check of the estimated production time for
each phase, internal and outsourced.
Verification, for every activity and item of the Manufacturing Plan, of the following information:
a) Current status and location; Details mentioned below
b) Baseline status and location; Details below
During expediting visit physically verified all items as per PO and also verified documentation of above Items.
Personal comments of expediter on the supplier’s declarations. Manufacturing (casting) may complete by 01-04-
2023 & further turbine assembly related works to be done at Voith India Baroda site . Actual delivery date to be
given by Voith India office to meet site delivery requirements.
Note: As per communication with sub vendor ATUL Precision Cast, they were not having details with them
manufacturing dates /details (Start ,FAT & delivery dates etc.)
5. Photographic report