TODATE PROJECT STATUS REPORT

PROJECT NAME 3+B+G+20 Mixed Apartment Building & Shoring Works


DATE OF
Location Wolo sefer, Addis Ababa Ethiopia April 7-2023
STATUS ENTRY
PROJECTED
PERIOD COVERED February 16-2023-April 7-2023 DATE OF April 30-2024
COMPLETION

PROJECT STATUS THIS WEEK

SHORING WORK
OVERALL
Shoring Pile Casting and Excavation
DRILING AND ON TRACK SUMMARY
Pyhisical Progress is 71.5% done
CONCRETE CASTING
STATUS
Master Schudele Approval
Complite the Remaining Pile Drilling and Casting
Completed Pile Foundation, Beginning of Excavation, and
UPCOMING MAJOR MILESTONES
Shotcrete Activity Continue
Excavation and Shotcrete work done
Mat Foundation
PROJECT COMPONENTS
COMPONENT STATUS NOTES
The cost of shoring is particularly high since construction
BUDGET OVER materials are always changing in price and renting a shoring
drill machine is very expensive.
For a Shoring Drilling Machine, the
RESOURCES Shoratage of Machinery
Rental Cost is Extremely High.

TIMELINE 50 Calender day Elapssed 23 Calander days delay as per the aggred Master schedule

We are commited to our revised internal Continually working night shifts and compensate for the time
SCOPE
plan that has passed.

WORK ACCOMPLISHED

TASK NUMBER DESCRIPTION Total No. of Pile Accomplishement

1 Pile Drilling/Excavation 67 74%


2 Pile Concete Casting 62 69%
3 Rebar Poduction for 85 Pile 85 95%
4 Top Tie Beam Formwork Started
Issues The Contractor Faced
RISK NUMBER DESCRIPTION OWNER / TEAM Remark
Prematurely Confronted Whether Case of the excavated hole collaps in
1
Condition some drilled holes
2 Design modification Shoring Layout Consultant Cose of the delay in the excavation

Consultant not provided the final The steel production activity for the mat
3 Consultant
structural design foundation and mat beam not yet begun.

Due to the weak soil in some areas, the


4 drilled hole collapses, which is the reason
for the delay.

UPCOMING WORK

Date STATUS DETAILS

Upto April 7 Top Tie Beam activity of work started


Upto April 11 The remaining 23 pile drilling
On internal Plan
Upto April 11 Bulk Excavation
Upto April 17 Shotcre & Ancouring by Full Capacity Started
Tue 5/2/23 Asper Aggred Master Schedule Mat Foundation activity of work Started
Sub Structure Activity work Done except hard core & 3rd
Sun 7/23/23 Asper Aggred Master Schedule
basment slab

MAJOR PROJECT MILESTONE TIMELINE


Shotcrte and Except for the hard
Excavation core of the third
Activity Done basement slab,
Top Tie Beam The remaining 23 substructure activity
Pile Casting work has been
Done completed.
Mat Foundation Done

Milstone Start Date


April /8/2023 April/13/2023
May /1/2023 June /8/2023

July 23/2023

Top Tie Beam 50% Done