Professional Documents
Culture Documents
IC Weekly Project Status Report 10673
IC Weekly Project Status Report 10673
IC Weekly Project Status Report 10673
SHORING WORK
OVERALL
Shoring Pile Casting and Excavation
DRILING AND ON TRACK SUMMARY
Pyhisical Progress is 71.5% done
CONCRETE CASTING
STATUS
Master Schudele Approval
Complite the Remaining Pile Drilling and Casting
Completed Pile Foundation, Beginning of Excavation, and
UPCOMING MAJOR MILESTONES
Shotcrete Activity Continue
Excavation and Shotcrete work done
Mat Foundation
PROJECT COMPONENTS
COMPONENT STATUS NOTES
The cost of shoring is particularly high since construction
BUDGET OVER materials are always changing in price and renting a shoring
drill machine is very expensive.
For a Shoring Drilling Machine, the
RESOURCES Shoratage of Machinery
Rental Cost is Extremely High.
TIMELINE 50 Calender day Elapssed 23 Calander days delay as per the aggred Master schedule
We are commited to our revised internal Continually working night shifts and compensate for the time
SCOPE
plan that has passed.
WORK ACCOMPLISHED
Consultant not provided the final The steel production activity for the mat
3 Consultant
structural design foundation and mat beam not yet begun.
UPCOMING WORK
July 23/2023