INSPECTION & TEST PLAN ITP NO APPROVED DATE DISCIPLINE:

BLINDING CONCRETE TSR-TRSDC-ITP-03 CIVIL


PROJECT TITLE: CONTRACTOR/SUBCONTRACTOR

R08-HE4C20 Shura Hotel (HE4) TAMEAR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE
TSR TRS ATKINS

1.0 DOCUMENT REVIEW

KCC - "RH" of Documents and "H" for Material


Raw Materials Sampling, Testing and Sampling and Testing.
1.1
Concrete Mix Design Approval
RH/ H RH/ H RH/ H TRSDC/Consultanats- "RH" of Documents and "H"
for Material Sampling and Testing.

MATERIAL
2.0
RECEIVING

2.1 Concrete, Polythylene Sheet H W W

3.0 INSTALLATION

Blinding Concrete concrete Formwork


3.1
Inspection
I W W

Blinding Concrete Sampling, Testing


3.2
& Placement Inspection
I W W TSR to Provide Applicable MEP clearance

3.3 Concrete finishing & curing Inspection W S S

PRE-
4.0
COMMISSIONING

4.1 Not Applicable

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by TRS/Consultant Site Inspection Personnel. After this
1 period, TRS/Consultant Inspection may adjust the levels of TRS/Consultant participation based upon the Contractor’s performance.

2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as
3 scheduled if the QA/QC organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC
4 organization representative in attendance.

5 If TSR delegates the assigned responsibility to the Subcontractor, then the TMR will have the same degree of responsibility as assigned to TRSDC.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% contractor's Inspection

Page 1 of 1