1 2 3 4 5
1.1 1)
2) .
1.2 1)
.
2)
3)
4)
1.3
1.4 1)
2)
1.5
1.6
HAV Ship Management NorRus AS ISM-ISO Manual Approved by: GM
Section 3 Version: 01.09.2015
The Company Structure Rev.: 01
and Programs Date: 26.04.2019
Integrated Management System 3.10 Maintenance of ship and Page: 1 of 5
equipment. Appendix 1
1 2 3 4 5
1.1 Stand-by Ch. Eng. 1) Testing is carried out by simulation of low Weekly
lubricating oil
pumps for ME pressure before relevant pressure sensor
and gear box
when engine idle running and in port. Alarm
1.2 Stand-by fuel oil Ch. Eng. 1) When engine is stopped, switch on pump and Weekly
pump and fuel
system check that proper pressure is reached.
has to sound.
fuel pipes.
1.3 Stand-by cooling Ch. Eng. Switch on the pump and check emergency cooling Weekly
pump system in operation.
1.4 Pneumatic Ch. Eng. 1) When engine is stopped, set control lever full Weekly
control system
ahead/astern on the bridge, starting lever in operating
1.5 Emergency Ch. Eng. Test to be carried out by Ch. Officer on the bridge in Weekly
telegraph cooperation with engineer in engine room. Ensure that
telegraph works properly, make lamp test.
1.6 Emergency stop Ch. Eng. Push relevant button on the bridge. Engine has to be Monthly
stopped. Test is conducted in port.
HAV Ship Management NorRus AS - : GM
: 01.09.2015
: 01
: 26.04.2019
:2 5
5.1
5.2
5.3
6.1 1)
2)
3)
.
6.2 1)
2)
3)
HAV Ship Management NorRus AS ISM-ISO Manual Approved by: GM
Section 3 Version: 01.09.2015
The Company Structure Rev.: 01
and Programs Date: 26.04.2019
Integrated Management System 3.10 Maintenance of ship and Page: 2 of 5
equipment. Appendix 1
4 Emergency Ch. Eng. Simulate blackout situation and check that emergency Weekly
lighting batteries provide emergency lighting in all relevant
places. Replace lamps if necessary.
5.1 Emergency Ch. Off. Responsible crew member switches on steering pumps Weekly
steering in steering gear room and follows Ch. Officer orders
from the bridge using communication system.
5.2 Power failure Ch. Eng. Remove relevant fuse from switchboard, power failure Monthly
alarm. alarm has to sound on the bridge.
5.3 Low oil level Ch. Eng. Simulate low level of hydraulic oil in circulation tank by Monthly
alarm drainage. Alarm has to sound on the bridge and in the
engine room.
6.1 General fire Ch. Eng. 1) Start fire pump from ER and insure that self Weekly
pump
priming and proper delivered pressure are provided.
6.2 Emergency fire Ch. Eng. 1) Start pump and make sure that self priming and Weekly
pump
proper delivered pressure are available.
7.1 1)
2)
7.2
7.3
7.4
8.1 1)
-
2)
3) -PPM
4)
.
8.2
SOPEP
10
10.1
.
HAV Ship Management NorRus AS ISM-ISO Manual Approved by: GM
Section 3 Version: 01.09.2015
The Company Structure Rev.: 01
and Programs Date: 26.04.2019
Integrated Management System 3.10 Maintenance of ship and Page: 3 of 5
equipment. Appendix 1
7.1 GMDSS system Ch. Off. 1) Check that portable VHFs are fully charged. Weekly
7.2 ER - bridge Ch. Off. Call engine room and establish communication. Weekly
communication
system
8 Anti-pollution equipment
8.1 Oily-water Ch. Eng. 1) Switch on separator. Check pressure of separated Monthly
separator
water (1-2 bar).
test buttons.
8.2 Spill prevention Ch. Eng. Check quantity according to checklist of Spare parts and Monthly
gears stores for critical systems.
9 Fire detection Ch. Off. Fire simulation to be carried out by inserting smoke from Weekly
alarm system testing spray into each sensor one by one. Alarm has to
sound each time.
10.1 Remote stop of Ch. Eng. Push relevant button in remote station. Weekly
ventilation and
fuel pumps
HAV Ship Management NorRus AS - : GM
: 01.09.2015
: 01
: 26.04.2019
:4 5
10.2
11
11.1 1)
2)
11.2 1)
2)
11.3
11.4
12
12.1 -
12.2 -
12.3 -
12.4
13 1)
2)
3)
14 CO2 1)
2) CO2
HAV Ship Management NorRus AS ISM-ISO Manual Approved by: GM
Section 3 Version: 01.09.2015
The Company Structure Rev.: 01
and Programs Date: 26.04.2019
Integrated Management System 3.10 Maintenance of ship and Page: 4 of 5
equipment. Appendix 1
10.2 Remote shut Ch. Eng. Test system by closing valves from remote station on Monthly
down of fuel deck.
supply
11.1 Ballast pumps Ch. Eng. 1) Start ballast pumps and ensure that proper capacity Weekly
No. 1, No. 2
is available by means of ballasting/ de-ballasting.
11.2 Ballast valves Ch. Eng. 1) Make sure pipes are leakage-free. Monthly
and pipes
2) Check proper operation of valves.
11.3 Hand drain Ch. Eng. Check in operation (in steering gear and forecastle Monthly
pumps and rooms)
systems
11.4 Bilge alarm Ch. Eng. Move up bubble sensor, alarm have to sound in 20 Weekly
system seconds.
12.1 Water tight doors Ch. Off. Check condition of closing arrangements and rubber. Weekly
12.2 Ventilation flaps Ch. Off. Check condition of closing arrangements and rubber. Weekly
12.3 Hatch covers Ch. Off. Inspection of rubber and quick acting cleats. Weekly
12.4 Overboard valves Ch. Eng. Make sure those are leakage-free Monthly
and pipes in ER
13 Anchor winch Ch. Off. 1) Check in operation by means of lowering an heaving Weekly
14 CO2 system Ch. Eng. 1) Visual inspection of bottles and system. Weekly
15
16
B-14
17 ECDIS 2-
,
.
HAV Ship Management NorRus AS ISM-ISO Manual Approved by: GM
Section 3 Version: 01.09.2015
The Company Structure Rev.: 01
and Programs Date: 26.04.2019
Integrated Management System 3.10 Maintenance of ship and Page: 5 of 5
equipment. Appendix 1
16 Pilot ladder Ch. Off. Visual inspection according check list B-14 Monthly
Cabling 4 Months