Rekapitulasi Hours Meter Wheel Loader (WL-032)

Tanggal Kode unit Unit Operator Shift HM Awal HM Akhir Total HM Kegiatan
16-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
16-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
17-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
17-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
18-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
18-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
19-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
19-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
20-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
20-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
21-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
21-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
22-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
22-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
23-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
23-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
24-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
24-Jan WL 032 Wheel Loader Ambar Night - - - Breakdown
25-Jan WL 032 Wheel Loader Agustinus Day - - - Ground Test dan kemudian BD kembali
25-Jan WL 032 Wheel Loader Agustinus Night - - - Breakdown
26-Jan WL 032 Wheel Loader Agustinus Day - - - Breakdown
26-Jan WL 032 Wheel Loader Agustinus Night - - - Breakdown
27-Jan WL 032 Wheel Loader Agustinus Day 5,510.60 5,512.40 1.80 Loading Coal ke DT
27-Jan WL 032 Wheel Loader Ambar Night - - - Standby (Rain and Slippery)
28-Jan WL 032 Wheel Loader Agustinus Day - - - Standby (Rain and Slippery)
28-Jan WL 032 Wheel Loader Ambar Night - - - Standby (Rain and Slippery)
29-Jan WL 032 Wheel Loader Agustinus Day - Standby (Rain and Slippery)
29-Jan WL 032 Wheel Loader Ambar Night 5,512.40 5,513.40 1.00 Prepare jalan di STP
29-Jan WL 032 Wheel Loader Ambar Night 5,513.40 5,516.60 3.20 Trimmimg di STP
30-Jan WL 032 Wheel Loader Ambar Day 5,516.60 5,524.60 8.00 Rehandling
30-Jan WL 032 Wheel Loader Night - - - Breakdown
31-Jan WL 032 Wheel Loader Ambar Day - - - Breakdown
31-Jan WL 032 Wheel Loader Night - - - Breakdown
1-Feb WL 032 Wheel Loader Ambar Day 5,524.80 5,531.40 6.60 Rehandling
1-Feb WL 032 Wheel Loader Ambar Night 5,531.40 5,534.90 3.50 Rehandling
2-Feb WL 032 Wheel Loader Ambar Day 5,534.90 5,535.90 1.00 Perbaikan jalan
2-Feb WL 032 Wheel Loader Ambar Day 5,535.90 5,541.50 5.60 Rehandling
2-Feb WL 032 Wheel Loader - Night - - - No Operator
3-Feb WL 032 Wheel Loader Wagiran Day 5,541.50 5,544.80 3.30 Rehandling
3-Feb WL 032 Wheel Loader - Night - - - No Operator
4-Feb WL 032 Wheel Loader Ambar Day 5,544.80 5,553.20 8.40 Support hopper JLU
5-Feb WL 032 Wheel Loader Ambar Day 5,553.20 5,562.10 8.90 Rehandling
5-Feb WL 032 Wheel Loader - Night - - - No Operator
6-Feb WL 032 Wheel Loader Ambar Day 5,562.10 5,570.80 8.70 Support hopper JLU
7-Feb WL 032 Wheel Loader Ambar Day 5,570.80 5,577.40 6.60 Support hopper JLU
7-Feb WL 032 Wheel Loader - Night - - - No Operator
8-Feb WL 032 Wheel Loader Ambar Day 5,577.40 5,585.80 8.40 Support hopper JLU
8-Feb WL 032 Wheel Loader - Night - - - No Operator
Total HM 75.00

Note :
Total Breakdown : 24 Shift / 12 Hari
No Operator : 5 Shift / 2,5 Hari
Total : 29 Shift / 14,5 Hari