ECA CO Procedure
ECA CO Procedure
ECA CO Procedure
4 Time required for complete changeover from HFO to LSMGO has been calculated Time ____________
Inform the time required for change over to Bridge so that Engine Room can be warned
5 when to commence the changeover . Write estimated date/time of notice in remarks Date/Time____________
column.
Reconfirm if lubricity improver has been added to LSMGO storage tank. If not done
6
carry out dosing through tank sounding pipe
7 Confirm Main and Aux Engine service tanks are appropriately filled with LSMGO
If equipped with NABTESCO governors confirm setting has been adjusted as per
8
procedure in Machinery Trouble Alert 13-2015
16 Lubricate and move the fuel pump racks to check they are free
C) Changing back to HFO from LSMGO after exiting ECA territorial line
S.No Item Y N N/A Remarks
Is the estimated date/time of change-over known to the OOW? Write the estimated
1 Date/Time____________
date/time in remarks column.
2 Keep HFO service tank heated sufficiently to about 90°C prior departing from port
3 Transfer ME control to Engine Room control from Bridge control
4 Gradually lower ME load to about 60% MCR or less (if on a higher load)
Carry out lubrication of all fuel pump racks of Main and Auxiliary Engines and move
5
them by hand several times
Open steam and slowly increase the fuel oil temperature at the rate of 2ºC / minute
6
maximum
When FO temperature is about 60°C commence changing over to HFO by gradually
7 opening the HFO service tank valve while simultaenously shutting off the LSMGO
service tank valve gradually
8 Closely monitor the pressure of FO supply and circulating line
Switch on viscosity controller and shut the by pass valve and monitor the viscosity on
9
the meter
Once the desired FO viscosity and temperature has been attained inform Bridge and
10
commence increasing engine load as required
D) Documentation
S.No Item Y N N/A Remarks
Fill form ENV11 (change over log) with following information for each change over &
retain in file CE23
a) Date and time the vessel entered / left each regulatory area
1
b) Vessel’s position, date and time fuel was changed over
c) Tank wise LSMGO bunkering quantities, grade used, and sulphur content
Make following entries in C/E log book to make whenever change over from HFO to
LSMGO and vice versa
a) Volume of low sulphur fuel in each tank
2 b) Date
c) Time
d) Position of the ship when any fuel change over operation is completed prior entry
into ECA or commenced after exit from such an area
If the vessel is a Panama Flag vessel applicable entry to make in Oil Record Book
3
about changeover
Remarks
If vessel is proceeding to ECA without distillate fuel notify owners/charterers to make necessary application to regulatory authorities like Air
1
Resources Board (ARB) in California and vessel's Master to keep the Flag State and local authorites informed
2 Master to coordinate with Superintendent and keep him informed immediately in case any difficulties being encounterd
Chief Engineer