AHA Ductbank Installation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Activity Hazard Analysis (AHA)

Activity/Work Task: Duck bank installation &


Core drilling

Overall Risk Assessment Code (RAC) (Use highest code)


Project Location: Ft McNair
Risk Assessment Code (RAC) Matrix
Contract Number: W912DR20C0055 Probability
12/7/2022 Frequen
Date Prepared: Severity t Likely Occasional Seldom Unlikely
Prepared by (Name/Title): Yug Dobariya Catastrophic E E H H M
APM Critical E H H M L
Reviewed by (Name/Title): Jeff Barhorst Marginal H M M L L
Superintendent Negligible M L L L L
Notes: (Field Notes, Review
Comments, etc.) Step 1: Review each “Hazard” with identified safety “Controls” and determine RAC (See above)
“Probability” is the likelihood to cause an incident, near miss, or
accident and identified as: Frequent, Likely, Occasional, Seldom RAC Chart
or Unlikely.
“Severity” is the outcome/degree if an incident, near miss, or E = Extremely High Risk
accident did occur and identified as: Catastrophic, Critical,
Marginal, or Negligible H = High Risk
Step 2: Identify the RAC (Probability/Severity) as E, H, M, or L for M = Moderate Risk
each “Hazard” on AHA. Annotate the overall highest RAC at the
top of AHA. L = Low Risk
Job Steps Hazards Controls RAC
Verify that all site employees have site orientation.
Site Orientation L
Keep area clear of unnecessary personnel.
Moving Equipment – personnel being struck by equipment Make sure you have eye contact with the Equipment Operator. L
Mobilization – Loading/Unloading
of Equipment & Material
Struck by objects/ Use both hands, slip-resistance gloves for grip. Use 2 persons
for lifts over 50 lbs. Use safety footwear. L
Musculoskeletal injuries
Wear appropriate clothing for hot or cold weather. Sun block,
Exposure to Hot / Cold weather Dehydration / Hyperthermia Drink at least ½ liter of water an hour and take scheduled L
breaks or break as needed. EM385-1-1 Code: 06.j
An “area of retreat” shall be established and all employees
must be informed where this location shall be.If warnings have
been issued or if there are indications that severe weather is in
the vicinity of the project, weather conditions will be monitored
Thunder/lightning storms If it is determined by SSHO that severe weather will impact the
Excavation: Severe Weather Tornados project either by monitoring the weather station and radar or by L
Hurricanes natural indications (i.e. lightning strikes), the project shall be
shut down and all employees and personnel shall relocate to
the “area of retreat” until it is determined that a threat of severe
weather no longer exists. EM385-1-1 Code: 06.j

If UXO are found during activity, stop what you are doing
UXO Hazards UXO exposure, uncovered safely, barricade area, recognize, retreat and report to XL L
Construction. Contact number on hard hat decal.
If you encounter areas with high volumes of insects and/or
animals that carry fleas or disease carrying insects, wear
personal protection equipment such as netted hoods, leather
work gloves, and high top work boots in conjunction with
trousers and long sleeved shirts. If you encounter areas prone
to poisonous snakes or lizards wear snake chaps or high
Exposure to Ticks, snake boots with trousers and long sleeved shirts. All
Wildlife, Plant Hazards Snakes, Poisonous Snakes, employees shall be trained in recognition of the snakes and M
Poisonous Plants their nesting habits. Employees are to be trained in first aid for
the treatment of snake bites. If you encounter an area where
you are exposed to poisonous plants remove and/or destroy
the poisonous plants if practical. Wear protective gloves when
handling areas prone to poisonous plants. Apply protective
ointments and wash exposed body parts with soap and water.

a. Watch for any loose debris or uneven surfaces that could


cause you to twist your ankle. If rain should occur, clean
equipment steps which could cause slippery conditions. b.
a.Slips/Trips/Falls Stretch first. Use following lifting techniques, Bend knees, keep
Site Preparation b.Back Strains back straight, keep the load close to your body. If over 40lbs, L
c.Pinch Points get help. c. Watch hand placement at all times. Position hand
where fingers will not get caught 100% gloves (level 1 cut
resistant) EM385-1-1 Code: 24.A.07, 14.A.04, 05.A.08

a. Prior digging make sure contact Miss Utility have an active


ticket and complete the GC excavation permit. b. Inspect
Digging small pit to install sile markings and sounding areas for signs of underground
fench, or orange fence, other Striking underground utility utilities. c. Dig a test pit by hand prior digging trench. If unmark L
construciton signs. underground utilities are found document and report them
immediately.
Use proper lifting techniques and body positioning. Use
multiple employees for heavy or awkward loads. Use
mechanical means when possible. a. Wear hand protection as
necessary. Inspection of Sediment & Erosion weekly or in
event of rainy condition. All hand/ power tools shall be
Installation of erosion/ sediment inspected prior to use. Any damaged/ unsafe tools shall be
Sprains/ strains when handling/ installing erosion/ sediment tagged and removed from service and it shall comply with the
controls, silt fencing / super silt
measures, Cuts/ scrapes when handling/ install Sediment & manufactures recommendations. All guards shall be in place L
fencing, orange fence, other
Erosion measures. Slips/trips/falls and lacerations. and serviceable. All cords/ power tools shall have a current
construction sign.
assured grounding inspection. Work area shall barricade or
shields utilized if other workers are exposed to hazard.
Employees shall wear high visibility vests. Employees shall
avoid pinch points. Verify proper utilization of PPE especially
on hands.
Utilize 411, identify any underground utilities, trained operator
of mini excavator, inspect before use, spotter & back-up
alarms. Avoid structures and evaluate for overhead power
Trench excavation (shallow) w/ lines. Competent person designated to oversee operations.
Underground utility strike. Excavation hazards, cave-in
mini excavator and shovels & Keep trench excavations depth less than 4 feet, evaluate soil L
Cuts, lacerations, punctures. Strains and sprains
other hand tools. conditions. If depth exceeds 4 feet, provide safe means of
egress: ladder or ramp within 25 ft. Use proper lifting
techniques. Use gloves when using hand tools.

Use proper lifting techniques. Do not bend at the waist, team


lift if needed. Ask for the help of more workers if the load is
very. Use leather gloves when handling forms. Minimum two
workers should lift the form - one worker must lift one side, and
Strains, Cuts/Punctures, Slips/Trips/Falls. second worker must lift other side.Avoid Pinch points. Wear L
gloves to protect from cuts. Properly dispose of unusable
material. Utilize proper PPE during re-bar cutting operations
Install forms if required. including safety glasses and face shield. Goggles may be
utilized in conjunction with face shields.
OSHA states that formwork shall be designed, fabricated,
erected, supported, braced and maintained so that it will be
capable of supporting without failure all vertical and lateral
Form blow out while placing concrete. loads that may reasonably be anticipated to be applied to the L
formwork. Tranined employees should install formwork. It must
be inspected before placing the concrete.

Review SDS (safety data sheet), use hand & eye protection
Install conduit/PVC pipe by hand Chemical exposure(cement) when necessary. Allow for proper ventilation. Keep L
sparkproducing equipment away.
Use gloves, safety glasses/face shields and wash off
splattered concrete asap with fresh water. Use power screet
whenever possible to eliminate constant bending and pulling
motion required by hand screed. Use chute man to swing
Chemical/ Concrete Burns, Strains/Sprains, Back strain; concrete chute back and forth and signal concrete truck driver.
Cast in place concrete Chute man needs to commute with rest of crew when moving M
pulled muscles
chutes or repositioning trucks. Use a spotter for concrete
trucks and all vehicles in tight or congested areas. Inspect
work area, move material that may cuase trips prior to
performing work.
Obtain special instructions before use. Do not handle until all
safety precautions have been read and understood. Wash any
exposed body parts thoroughly after handling. Avoid breathing
dust. Contaminated clothing must not be allowed out of the
SKIN SENSITIZATION, CARCINOGENICITY, SPECIFIC workplace. Wear protective gloves/protective clothing/eye
TARGET ORGAN TOXICITY, SKIN protection/face protection. If exposed or concerned: Get
Dealing with Ready-Mix-Concrete. H
CORROSION/IRRITATION, SERIOUS EYE DAMAGE/EYE medical advice/attention if irritation or rash occurs. If on skin:
IRRITATION Take off immediately all contaminated clothing. Rinse/wash
skin with plenty of water/shower. Wash contaminated clothing
before reuse. If in eyes: Rinse continuously with water for
several minutes. Remove contact lenses, if present and easy
to do.
Stepping on protruding nails while removing forms.Trip Remove or bend nails over while removing forms. Keep
Remove forms, if required. hazards. supplies and debris picked up and out of working and walking L
areas. Wear PPE.
Use both hands, slip-resistance gloves for grip on tools and
Struck by compactor. Use 2 persons for lifts over 50 lbs. Use safety
Musculoskeletal injuries footwear. Trained operator of equipment, use spotter/backup L
Cuts, lacerations, punctures alarm, avoid structures, and evaluate for overhead power
Lay burial ID tape, compact, and lines.
backfill trench with mini excavator a Watch for any loose debris or uneven surfaces that could
and shovel. cause you to twist your ankle. If rain should occur, clean
Slips, Trips, Falls equipment steps which could cause slippery conditions.
b.Rotate compaction tasks to minimize worker exposure to L
Vibration
equipmentvibration
EM385-1-1 Code: 24.A.07
Holes will be wet drilled using locally supplied water which will
prevent exposure to silica dust. Employee shall stand clear of
the drill bit while the tool in in motion. Cut resistant gloves will
be worn during drilling operations.Personnel not involved
Exposure to silica dust shall be kept clear while performing the task. Keep hands, feet
Cuts from drilling/pinch points.3.c. Injury from faulty equipment and loose clothing clear of rotating equipment. Operator shall L
Foreign object in eye verbally alert employees and ensure that all are clear prior to
Drilling core holes in concrete starting equipment. The core drill shall be inspected for
damage and tested to ensure proper operation prior to use.
Eye protection to be worn at all times. Eye wash station is
located at south west corner of Echo Pier Berth.
Ensure that a utility survey has been completed for all areas to
Risk of hitting underground utilities. be cored drilled. Call miss utitlity to mark out all underground M
utilities before commencing the work.
Install plywood covers over core holes immediately after
drilling. Identify plywood covers with “Caution Hole”. Secure
Cover core hole openings Slips/Trips/Falls L
plywood covers with concrete screws.

Inspect work area, move material that may cause trips prior to
Clean up Slips, trips and falls performing work. Use proper lifting techniques. L

Training Requirements/Competent or Qualified Personnel


Equipment to be Used Inspection Requirements
name(s)
Hand tools, mini excavator, shovels, hand Competent/Qualified Personnel Inspect wet saw daily. Also, inspect prior to use any time.
tools, wheel borrow, chute, hammer, Nailer,
Rake, core driller, extension cord,
Required PPE: Safety glasses and face
shield, Dust mask, Cut resistant gloves,
Hearing protection

You might also like