Speen-1 Mari – RIG 4

OBJECTIVE: RIH 13 3/8” CSG.


PRESENT OPERATION: POOH bit to surface.

 Cont. POOH to surface. Rack back all HWDPs and DCs. L/D jar, stabs, bit and MWD tool.
 Hold PJSM. Remove TDS saver sub to rig up CRT. R/U CRT & TRS Equipment for 13 3/8”CSG running
Job. Function test all equipment. Try to do it offline as much as possible.
 P/U 13 3/8” 1st casing joint (72 ppf, P-110, Vam top) already M/U with reamer shoe. Torque up
connection. Check integrity of floats. RIH same
 P/U, M/U and RIH 2nd 13 3/8” casing joint
 P/up 3rd casing joint already M/U with Float collar. Torque up connections. Check integrity of floats.
RIH same
Apply thread locking compound on all shoe track connections.
Keep circulation swage (Vam top x 1502 WECO connection) at R/Floor all the time.
 Install FMS. Resume RIH 13 3/8” CSG joints as per tally (84 more joints of 13 3/8”, 72ppf, P-110 + 46
joints of 13 3/8”, 68 ppf, L-80)
Make sure CRT properly aligned with center of rotary to avoid cross threading.
Fill up after every five joints through CRT. Break circulation at casing shoe for 15 minutes @ 6
bl/min (250 gpm) (Joint run#85). Record Weights, torque and Pressure
P/U Slack off Torque @ 30 rpm 40 rpm, 50 rpm .
Max slip-to-slip speed to be 1-3 min/joint in open hole. In case of losses, reduce the speed to 1.5
minute or 2 minute per joint according to loss rate. Surge pressure should not exceed 1.91 sg at
casing shoe
In case of any obstruction, do not push. Wash down, ream only if necessary
Max allowable slack 15 tons. While reaming, torque limit is 19 ft.klb (80% of the M/U torque)
Driller & mud logger should prepare Trip sheet & inform Company man & Mud engineer
immediately in case of loss/gain. In case of any doubt of displacement cross check closed end
displacement thru trip tank.
Wednesday, 26 April 2023
 Max allowable surge is 1.91 SG (42 psi with MW 1.88SG) Mud logger should show on the screen in
psi or SG. Driller to adjust the running speed accordingly
 During RIH, monitor metal displacement. If observe losses, reduce running speed.
 Break circulation slowly and tag bottom with circulation to confirm tally depth. P/U casing and
adjust the shoe with ̴1m stick up above rig floor. Land casing in FMS and slack casing weight
 Increase flow rate stepwise to 8 BPM while monitor losses/pack off. Circulate at least 1.5 bottoms
up
During circulation, reduce mud rheology ALARP
Break circulation slowly and pick up string while starting the pump. Stop once returns observed
at surface.
Once the circulation is resumed and pressure stabilized, start preparing mixed fluid. Continue
circulation to condition mud @ 340 GPM (8 bbl/min).
 Stop circulation and R/U cementing head. Hook up cementing lines with cementing head with one
line connected to stand pipe through a Y connection and P/T same at 4,000 psi.
 Resume circulation through cementing head at same rate as before

Casing Capacity = 0.496/0.498 bbl/m, Total Joints to RIH = 133 (87+ 46). Joints remaining on rack: 42 (9 +
33)

GOOD LUCK AND WORK SAFE. STICK TO GOOD DRILLING PRACTICES-NO SHORT CUTS

COMPANY MAN