RENCANA
HARGA
JUMLAH
NO URAIAN QYT SATUAN JUMLAH HARGA
HARI
(Rp)
KERJA
1 Exca PC 3 Unit 40
4,125,000.00 Rp 165,000,000.00
200
2 Bomag 1 Unit 5 1,250,000.00 Rp 6,250,000.00
3 Grader 1 Unit 10 2,000,000.00 Rp 20,000,000.00
4 Dozer 1 Unit 20 1,500,000.00 Rp 30,000,000.00
5 DT 10 roda 4 Unit 40 5,000,000.00 Rp 200,000,000.00
8 Solar 21750 Liter 40 20,000.00 435,000,000.00
Jumlah Rp 856,250,000