FIELDBUS TECHNOLOGY ON A LARGE SCALE MINERAL PROCES - 2007 - IFAC Proceedings Vo

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

FIELDBUS TECHNOLOGY ON A LARGE SCALE MINERAL PROCESSING PROJECT

Sudhir Jain1 , Jack Murray1


Manoj Pandya2

1
Emerson Process Management
2
Alcan Engineering Pty Ltd

Abstract: In 2004, Alcan decided to use fieldbus communication for process control
equipment on their AUD 2.8 billion expansion of the Alcan Gove Alumina Refinery in
Australia’s Northern Territory. To reduce project risk Alcan used elements of the PEpC
model developed by CII. (Construction Industry Institute).

This paper outlines Alcan’s implementation of fieldbus technology on the expansion


project and its use of a construction process known as pre-assembled modules (PAM) to
meet the aggressive schedule targets.
Copyright © 2007 IFAC

Keywords: Fieldbus, Digital communications, Planning, Process control, Project


management

INTRODUCTION work done in the previous five years. Over that


time Alcan had made the decision to shift its I&C
Alcan’s Gove bauxite mine and alumina refinery is systems from the traditional 4-20 mA loops to
located at Nhulunbuy on the Gove Peninsula in the modern digital fieldbus technology.
east Arnhem Land region of Australia’s Northern This technological shift was made in stages,
Territory. In 2004 Alcan made the decision to beginning with conversion of a selected portion of
expand the facility; the result was the AUD2.8 the existing facility, with the objective of gaining
billion Gove Expansion Project (G3), intended to both technical and managerial experience with the
increase the processing capacity of the company’s new technology, mitigating risk, and finding the
Gove alumina refinery from 2.0 Mtpa to 3.8 Mtpa, best means of implementation.
provide significant improvements in efficiency and
environmental impact over the existing plant, and
increase the company’s overall alumina capacity. THE ADVANTAGES OF FIELDBUS
Engineering, procurement and construction kicked TECHNOLOGY
off in Q4 of 2004. By Mid-March of 2006, 95
percent of engineering work was complete, 76 Over the past few decades the processing industry
percent of the PAM fabrication and assembly work has come to understand the benefits to be realized
was complete, and 54 percent of all on-site from digital communications for process
construction was complete. instrumentation and control. At one time process
communications was done primarily with 4-20 mA
One of the contributing factor for the success of the current loop and similar systems; while useful, 4-
G3 project, however, depended to a great extent on 20 allows only one variable to be communicated
from each instrument to the control room or from accurate, up-to-date calibration and maintenance
the control room to each actuator, and it requires records.
that each instrument or actuator be connected via a
separate pair of wires. In the 1980s a way was After due consideration and study of existing
found to piggy-back digital signals on top of the 4- fieldbus installations Alcan settled on two bus
20 mA dc process signals. This method, called systems. For process measurement and control the
Highway Addressable Remote Transducer choice was FOUNDATION Fieldbus; for
(HART), began a revolution in process intelligent discrete devices like motor control
instrumentation; it allowed two-way centers and variable speed drives the pick was
communication between field devices and control Profibus DP. One advantage of these protocols was
room, remote diagnostics and even re-ranging that they are within public domain and controlled
without physical examination. HART enabled field by dedicated non-profit organizations, rather than
devices to become intelligent. particular vendors.

HART does, however, have a significant limitation: Once the choice of bus protocols was made, the
it still requires an individual set of wires for each next step was implementation at Gove, but rather
field device. The alternative is a fieldbus system, in than rush in and install fieldbus throughout the
which all communication is in digital form and facility, Alcan worked incrementally on existing
multiple intelligent field devices are connected to a facilities, with the intention of not only determining
single cable, each with its own digital address. This if fieldbus would really do what was expected of it
saves considerable expense in cabling, I/O but also to gain experience with the project and to
cabinets, field junction boxes and more. In develop the appropriate practices for making
addition, fieldbus-connected field devices can not maximum use of it and preparing for
only be checked and diagnosed remotely, they can implementation on a larger scale. A small pilot
be programmed via function blocks to re-range and project with a small number of I/O was
more; it is even possible to set up local control commissioned with an eye to gaining experience in
loops between transmitters and actuators with the all aspects of fieldbus technology before
role of the plant’s control system reduced to simply proceeding to the next phase.
monitoring and intervening in case of problems.
Experience with the various legacy I&C
There are many of these systems, and while today equipment, and an extensive technical evaluation,
two families of protocols -FOUNDATION led Alcan to realize that the facility’s existing I&C
Fieldbus and Profibus - dominate the process system was poorly suited to a fieldbus-equipped
control field, in 1999 when Alcan began assessing world. Experience gained through the study of the
its current and future instrumentation & control available fieldbus technologies led Alcan to choose
requirements, there was considerable disagreement the DeltaV distributed control system (DCS) from
as to which, if any, fieldbus protocols would come Emerson Process Management as a replacement for
out as a winner. the legacy systems, based on a combination of
Emerson’s experience in fieldbus, its ability to
Alcan began to investigate the advantages and risks provide support in Australia, and its ability to work
of adopting fieldbus technology. Any solution with the wide variety of fieldbus standards and
adopted would have to conform with the equipment.
company’s EHS -FIRST management policy and
not compromise environmental health and safety. It Equally important was Alcan’s decision to engage
would have to be compatible and integrate with Emerson’s Fieldbus experts early in the project to
existing business management systems; and it assist in the required segment design, training of
would have to provide at least as much key personnel and development of standards &
interoperability as the existing 4-20 mA system. It procedures.
was also important to obtain the in-house expertise
to ensure operational security, and to make sure
that I&C equipment would be compatible with FIELDBUS IMPLEMENTATION
more than one fieldbus technology and still be
capable of integration with current systems. The pilot phase of fieldbus implementation at the
Grove facility was to be done in an area in which
The decision to employ digital fieldbus technology little damage would occur if things did not work as
on such a large scale was based on Alcan’s well as hoped. Accordingly, the company, after
substantial projected cost savings in engineering, appropriate study, chose 20 points to implement
purchasing, installation, commissioning, and start- fieldbus whose temporary loss would not cause
up and predictions of on-going cost savings serious hazards, deliberately choosing equipment
associated with improved operations from from a number of different manufacturers in order
additional process and device diagnostics, and to obtain the greatest breadth of experience.
reduced efforts to gather, assemble, and maintain
The results of phase 1 were positive, providing
company engineers with good training and
allowing them to develop the appropriate wiring
practices and standards as well as giving them
experience in commissioning and maintenance. It
also showed that the cost-saving promises of
fieldbus were indeed possible. The pilot plant
outcomes were instrumental in Alcan’s decision to
use fieldbus technology in the upcoming G3
expansion project, which would involve about 5000
field devices, plus variable-speed drives and on/off
motor control, for a total of about 15,000 I/O points
using the two fieldbus technologies previously
mentioned. Fig. 2. PAM being delivered to Gove
included process vessels and piping, pumps,
An important element of the use of fieldbus instrumentation and valves; all assembled and pre-
technology in the G3 expansion project was the wired using fieldbus technology. PAMs were
development and use of new hazard analysis assembled in Thailand and Vietnam and
procedures to ensure that failure of any segment of transported to the northern coast of Australia.
the fieldbus system would not leave any critical
part of the plant unmonitored or uncontrolled. The use of PAMs provided multiple benefits,
Segment segregation practices were developed to including improved safety, better control of project
make sure that if one segment failed, readings from schedule, better efficiency and quality due to use of
other devices on a different segment would controlled factory environments to produce the
continue. PAMs, improved EHS, and less need for relocating
large numbers of workers to the Australian remote
Other areas reviewed as part of the CHAZOP site.
(Control Hazards and Operability) approach were
interface design for smart motor control equipment
plus design, installation, testing, and the COMMISSIONING AND TESTING
completeness of maintenance documentation.
The combination of PAMs and fieldbus technology
with the DeltaV system facilitated testing and
USE OF PAMS commissioning, as each PAM was to a greater or
lesser extent a self-contained unit with all
An important element of the G3 project was components installed. This not only speeded
modular construction through the use of pre- factory acceptance testing but made it simpler to
assembled modules (PAMs). Assembled and fitted connect it to the DCS, both for testing and
out off-site, these plant modules included all commissioning and later for actual operation.
required electrical & instrumentation equipment
and were delivered to the Gove site fully pre-
commissioned and ready for installation. Alcan also developed a series of test procedures for
individual field devices, fieldbus segments, and
Alcan’s Gove project assembled more than 300 PAMs, and the appropriate record-keeping and
PAM units, of which 36 were so-called reporting mechanisms. The portable DeltaV system
SuperPAMs, ranging in size from 200 to 3000 was also used directly to test field devices and
tonnes. These PAM and SuperPAM designs fieldbus segments within PAMs as part of
commissioning.

THE PEpC MODEL

The traditional sequence followed in engineering


and construction projects is engineering,
procurement and construction, otherwise known as
the EPC model. It has worked reasonably well for
many years and for many projects, but has
significant shortcomings when it comes to projects
that involve high levels of technology, particularly
with complex control and/or communication
systems. The traditional model assumes that the
engineering staff chosen for the project is
Fig. 1: Fully fitted-out PAM. sufficiently familiar with all aspects of all available
solutions to complex problems that it can select the Although the PEpC was not formally adopted as a
correct vendor, or at least generates appropriate project model for the execution of the G3 project,
bidding specifications, before any procurement is the decision to choose both the fieldbus technology
undertaken. and DCS supplier early, confirms the application &
benefits of the PEpC model. This made it possible
Unfortunately, the world of technology changes at sufficiently to plan and develop the Gove project’s
a dizzying pace, and it is difficult or impossible for detailed I&C network architecture so as to create a
an engineering team to have the intimate familiarity robust, easily maintained, and tightly integrated
with every technological option to create a perfect I&C solution.
or even a practical specification; the result tends to
be errors in procurement and design, delays, BENEFITS
changes in scope, cost overruns and less-than-
optimal results. The use of fieldbus technology over conventional
4-20 mA technology reduced the number of
In recent years a new model has been proposed. systems cabinets by 40 percent, I/O cards by 42
Originated by the Construction Industry Institute percent, marshalling cabinets by 93 percent,
(CII) and called PEpC (pronounced Pepsi), it terminations by 73 percent, and commissioning
involves bringing in the vendors of the high-tech time by 72 percent.
equipment and software that will be needed for the
project before any actual procurement is done. It
recognizes that the vendors of high-tech solutions,
as specialists in their respective technologies, are
more likely to have the in-depth knowledge
required for a successful project.

CII developed the PepC model — and opened its


membership to include suppliers — in large part
due to its realization that suppliers “can and should
play a significant role in the pursuit of CII goals.”
(Executive summary of ECC RS130-1 —
Reforming Owner, Contractor, Supplier
Relationships: A Project Delivery System to
Optimize Supplier Roles in EPC Projects).
Fig 4 Digital Fieldbus Implementation Expected
In the new model procurement transactions for the Costs Savings.
most critical elements of the project (indicated by
capital P) happen first and to a large extent define
the next step, the main body of the engineering The value proposition of soft ROI entities, such as
effort for the rest of the project (Capital E). This is improved operations resulting from additional
followed by procurement of the materials for the process and device diagnostics, can be difficult to
rest of the project (small p), followed by the actual quantify. However, according to a report by
construction (capital C). independent industry experts at ARC Advisory
Group (www.arcweb.com), operations and
Such a model not only takes advantage of the maintenance are the very areas where fieldbus
expertise of the vendors, but it more closely aligns technology provides its greatest benefits. In other
with the increasingly-common practice of words, the introduction of fieldbus technology
distributed engineering and procurement, with becomes the enabler to achieving a heightened
significant portions of any given project designed level of production effectiveness.
and assembled off-site and then delivered as pre-
assembled modules (PAMs).
REFERENCES
Another factor making the PEpC model attractive Pandya, Manoj (2006), Digital Fieldbus
is that it comports with the steadily-shrinking Implementation for Mineral Processing,
supply of engineering talent available to both Presented at TMS 2006, March 15, 2006, San
engineering firms and their customers. Competitive Antonio, TX.
pressures have ensured that customers must The Construction Industry Institute Reforming
outsource engineering tasks for all but the most Supplier Relationships Research Team (1998).
rudimentary and routine work; it is no longer Reforming Owner, Contractor, Supplier
economical to maintain strong engineering staffs, Relationships: A Project Delivery System to
and companies that attempt to do so can endanger Optimize Supplier Roles in EPC Projects,
their competitive positions. Research Summary 130-1. Construction
Industry Institute, the University of Texas at
Austin.

You might also like