Professional Documents
Culture Documents
FIELDBUS TECHNOLOGY ON A LARGE SCALE MINERAL PROCES - 2007 - IFAC Proceedings Vo
FIELDBUS TECHNOLOGY ON A LARGE SCALE MINERAL PROCES - 2007 - IFAC Proceedings Vo
FIELDBUS TECHNOLOGY ON A LARGE SCALE MINERAL PROCES - 2007 - IFAC Proceedings Vo
1
Emerson Process Management
2
Alcan Engineering Pty Ltd
Abstract: In 2004, Alcan decided to use fieldbus communication for process control
equipment on their AUD 2.8 billion expansion of the Alcan Gove Alumina Refinery in
Australia’s Northern Territory. To reduce project risk Alcan used elements of the PEpC
model developed by CII. (Construction Industry Institute).
HART does, however, have a significant limitation: Once the choice of bus protocols was made, the
it still requires an individual set of wires for each next step was implementation at Gove, but rather
field device. The alternative is a fieldbus system, in than rush in and install fieldbus throughout the
which all communication is in digital form and facility, Alcan worked incrementally on existing
multiple intelligent field devices are connected to a facilities, with the intention of not only determining
single cable, each with its own digital address. This if fieldbus would really do what was expected of it
saves considerable expense in cabling, I/O but also to gain experience with the project and to
cabinets, field junction boxes and more. In develop the appropriate practices for making
addition, fieldbus-connected field devices can not maximum use of it and preparing for
only be checked and diagnosed remotely, they can implementation on a larger scale. A small pilot
be programmed via function blocks to re-range and project with a small number of I/O was
more; it is even possible to set up local control commissioned with an eye to gaining experience in
loops between transmitters and actuators with the all aspects of fieldbus technology before
role of the plant’s control system reduced to simply proceeding to the next phase.
monitoring and intervening in case of problems.
Experience with the various legacy I&C
There are many of these systems, and while today equipment, and an extensive technical evaluation,
two families of protocols -FOUNDATION led Alcan to realize that the facility’s existing I&C
Fieldbus and Profibus - dominate the process system was poorly suited to a fieldbus-equipped
control field, in 1999 when Alcan began assessing world. Experience gained through the study of the
its current and future instrumentation & control available fieldbus technologies led Alcan to choose
requirements, there was considerable disagreement the DeltaV distributed control system (DCS) from
as to which, if any, fieldbus protocols would come Emerson Process Management as a replacement for
out as a winner. the legacy systems, based on a combination of
Emerson’s experience in fieldbus, its ability to
Alcan began to investigate the advantages and risks provide support in Australia, and its ability to work
of adopting fieldbus technology. Any solution with the wide variety of fieldbus standards and
adopted would have to conform with the equipment.
company’s EHS -FIRST management policy and
not compromise environmental health and safety. It Equally important was Alcan’s decision to engage
would have to be compatible and integrate with Emerson’s Fieldbus experts early in the project to
existing business management systems; and it assist in the required segment design, training of
would have to provide at least as much key personnel and development of standards &
interoperability as the existing 4-20 mA system. It procedures.
was also important to obtain the in-house expertise
to ensure operational security, and to make sure
that I&C equipment would be compatible with FIELDBUS IMPLEMENTATION
more than one fieldbus technology and still be
capable of integration with current systems. The pilot phase of fieldbus implementation at the
Grove facility was to be done in an area in which
The decision to employ digital fieldbus technology little damage would occur if things did not work as
on such a large scale was based on Alcan’s well as hoped. Accordingly, the company, after
substantial projected cost savings in engineering, appropriate study, chose 20 points to implement
purchasing, installation, commissioning, and start- fieldbus whose temporary loss would not cause
up and predictions of on-going cost savings serious hazards, deliberately choosing equipment
associated with improved operations from from a number of different manufacturers in order
additional process and device diagnostics, and to obtain the greatest breadth of experience.
reduced efforts to gather, assemble, and maintain
The results of phase 1 were positive, providing
company engineers with good training and
allowing them to develop the appropriate wiring
practices and standards as well as giving them
experience in commissioning and maintenance. It
also showed that the cost-saving promises of
fieldbus were indeed possible. The pilot plant
outcomes were instrumental in Alcan’s decision to
use fieldbus technology in the upcoming G3
expansion project, which would involve about 5000
field devices, plus variable-speed drives and on/off
motor control, for a total of about 15,000 I/O points
using the two fieldbus technologies previously
mentioned. Fig. 2. PAM being delivered to Gove
included process vessels and piping, pumps,
An important element of the use of fieldbus instrumentation and valves; all assembled and pre-
technology in the G3 expansion project was the wired using fieldbus technology. PAMs were
development and use of new hazard analysis assembled in Thailand and Vietnam and
procedures to ensure that failure of any segment of transported to the northern coast of Australia.
the fieldbus system would not leave any critical
part of the plant unmonitored or uncontrolled. The use of PAMs provided multiple benefits,
Segment segregation practices were developed to including improved safety, better control of project
make sure that if one segment failed, readings from schedule, better efficiency and quality due to use of
other devices on a different segment would controlled factory environments to produce the
continue. PAMs, improved EHS, and less need for relocating
large numbers of workers to the Australian remote
Other areas reviewed as part of the CHAZOP site.
(Control Hazards and Operability) approach were
interface design for smart motor control equipment
plus design, installation, testing, and the COMMISSIONING AND TESTING
completeness of maintenance documentation.
The combination of PAMs and fieldbus technology
with the DeltaV system facilitated testing and
USE OF PAMS commissioning, as each PAM was to a greater or
lesser extent a self-contained unit with all
An important element of the G3 project was components installed. This not only speeded
modular construction through the use of pre- factory acceptance testing but made it simpler to
assembled modules (PAMs). Assembled and fitted connect it to the DCS, both for testing and
out off-site, these plant modules included all commissioning and later for actual operation.
required electrical & instrumentation equipment
and were delivered to the Gove site fully pre-
commissioned and ready for installation. Alcan also developed a series of test procedures for
individual field devices, fieldbus segments, and
Alcan’s Gove project assembled more than 300 PAMs, and the appropriate record-keeping and
PAM units, of which 36 were so-called reporting mechanisms. The portable DeltaV system
SuperPAMs, ranging in size from 200 to 3000 was also used directly to test field devices and
tonnes. These PAM and SuperPAM designs fieldbus segments within PAMs as part of
commissioning.