Professional Documents
Culture Documents
TP-GT01 Generator
TP-GT01 Generator
Consultant : “10721026/00”
Contractor : BEMCO
Subject : Testing Procedure Doc. No: TP-GT01,
Generator Page 1 of 5
Equipment :
Date:13 Feb,09 Revision: 0
TABLE OF CONTENT
1. Task
a. Work Status-------------------------------------------------------------------------2
b. Documentation---------------------------------------------------------------------2
c. Personnel----------------------------------------------------------------------------2
d. Measuring Instrumentation------------------------------------------------------2
2. Preconditions-------------------------------------------------------------------------------2
3. Precautions----------------------------------------------------------------------------------2
4. Scope------------------------------------------------------------------------------------------3
5. Execution-------------------------------------------------------------------------------------3
a. Visual Checks----------------------------------------------------------------------3
b. Testing of Generators
1. Resistance measurements through bolted----------------------------3
2. Insulation-resistance tests-------------------------------------------------4
3. Stator resistance test phase-to-phase----------------------------------4.
4. Insulation-resistance test on bearing pedestal-----------------------4
5. Resistance tests on Reds. If Applicable-------------------------------4
6. Commissioning of Heater Circuit. If applicable-----------------------5
7. Insulation-resistance tests on the main rotating field winding,
the exciter-field winding and the exciter-armature winding------- 5
6. Documents-----------------------------------------------------------------------------------5
7. Reference-------------------------------------------------------------------------------------5
8. Attachment-----------------------------------------------------------------------------------5
The above contents may not be reproduced, transmitted, or Originator: BEMCO Services
distributed to any form or by any means with out prior permission of Prepared by :M AH
the originator
Client : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Subject : Testing Procedure Doc. No: TP-GT01,
Generator Page 2 of 5
Equipment :
Date:13 Feb,09 Revision: 0
1. Task
This instruction comprises a complete description of the testing of the MV and LV
Generators.
2. Preconditions
2.1. Work Status
• Erection has been completed.
• Labelling of the equipment and designation of live enclosed plant sections has
been carried out.
2.2. Documentation
• The circuit diagrams of Motor is available
• Test Sheet TS-GT01 is available
• Product manual of the Motor
2.3. Personnel
• Commissioning engineer: - (1) engineer with experience in commissioning of
Motors and its control.
• Technician or helper:- (2) skilled worker with adequate on -the-job training
• Witness from the client‘s concern department
3. Precautions
The work will only proceed when a Permit to Work (PTW) in work permit area has been
obtained. The PTW will be kept on site for consultation during the testing works.
• Observe the rules for handling electronic components sensitive to electrostatic
discharge (ESD measures).
• Special safety arrangements shall be made for all areas which are not explicitly
designated as” electrical operating areas” when performing tests at voltages in
excess of 50V.
• Closing of the work permit after completion of the work (if the test area is to be
considered in work permit area) is necessary.
• Before test voltages are applied a check shall be carried out to ensure that no
unauthorized persons are working at the corresponding load-where ever necessary
barriers should be provided
4. Scope
• Testing of Generator
• Checking RTD’s and Thermocouple
• Checking of the mounting pad,
• Checking of correct Earthing,
The above contents may not be reproduced, transmitted, or Originator: BEMCO Services
distributed to any form or by any means with out prior permission of Prepared by :M AH
the originator
Client : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Subject : Testing Procedure Doc. No: TP-GT01,
Generator Page 3 of 5
Equipment :
Date:13 Feb,09 Revision: 0
5. Execution
5.1. Visual Inspection.
Prior to carrying out electrical tests, a visual check of the transformer should be
carried out paying particular attention to the following points
1. Compare equipment nameplate data with drawings and specifications.
2. Inspect physical and mechanical condition.
3. Inspect anchorage, alignment, and grounding.
4. Inspect air baffles, filter media, cooling fans, slip rings, brushes, and brush
rigging.
5. Verify the unit is clean.
6. Inspect bolted electrical connections for high resistance using one of the following
methods:
1. Use of low-resistance ohmmeter.
2. Verify tightness of accessible bolted electrical connections by calibrated
torque-wrench
7. Verify correct application of appropriate lubrication and lubrication systems.
8. Verify the absence of unusual mechanical or electrical noise or signs of
overheating during initial test run.
9. Verify that resistance temperature detector (RTD) circuits conform to drawings.
10. Verify that metering or relaying devices utilizing RTDs have the correct rating.
The above contents may not be reproduced, transmitted, or Originator: BEMCO Services
distributed to any form or by any means with out prior permission of Prepared by :M AH
the originator
Client : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Subject : Testing Procedure Doc. No: TP-GT01,
Generator Page 4 of 5
Equipment :
Date:13 Feb,09 Revision: 0
5.2.2.1. Generator Larger than 150 KVA: Test duration shall be for ten
minutes. Polarization index.
The insulation resistance measurement is done from 15 seconds to 1
minute with 15 seconds interval and then for every one minute up to
ten minutes. Value obtained at 10 minute divided by value at 1 minute
gives polarization index
5.2.2.2. Generators 150 KVA and less: Test duration shall be for one
minute. Dielectric-absorption ratio.
The insulation resistance measurement is done from 15 seconds to 1
minute with 15 seconds interval and then for every one minute up to
ten minutes. Value obtained at 60 seconds divided by value at 15
seconds gives Dielectric absorption ratio
The above contents may not be reproduced, transmitted, or Originator: BEMCO Services
distributed to any form or by any means with out prior permission of Prepared by :M AH
the originator
Client : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Subject : Testing Procedure Doc. No: TP-GT01,
Generator Page 5 of 5
Equipment :
Date:13 Feb,09 Revision: 0
6. Documents
Test sheet TS-GT01 shall be completed for Generator
7. Reference
8. Attachment
The above contents may not be reproduced, transmitted, or Originator: BEMCO Services
distributed to any form or by any means with out prior permission of Prepared by :M AH
the originator
TEST SHEETS
Customer : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Testing of Form No: TS-MT01,
Generator Page 1 of 4
Date:13/02/09 Revision: 0
1. Information
1.1 Motor Name Plate Details…………………………………………………..
Power:……………….kW (HP) Voltage……………V
Current………………A Speed……………..Rev..min-1
Serial No……………… Type of Motor……………………..
Make…………………………….. No of RTDS……………………….
Type of RTDs Space heater …………………KW/Volts
Visual Checks
1. Equipment nameplate data is matching with drawings and specifications.
2. Physical and mechanical condition is good.
3. Anchorage, alignment, and grounding is good
4 air baffles, filter media, cooling fans, slip rings, brushes, and brush rigging are ok.
5. Overall unit is clean.
6. Bolted electrical connections was verified by
1. Using low-resistance ohmmeter.
2. checking the tightness by calibrated torque-wrench
7. Application of lubrication and lubrication systems verified.
8. Unusual mechanical or electrical noise or signs of overheating during initial test
run is verified.
9. Resistance temperature detector (RTD) circuits are matching with the drawings
drawings.
10. Metering or relaying devices utilizing RTDs were checked for it is correct rating
Name:
Signature:
Date:
Customer : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Testing of Form No: TS-MT01,
Generator Page 2 of 4
Date:13/02/09 Revision: 0
3 Electrical Testing
3.1 Insulation Resistance Test:
Test Voltage:………………..Volts DC Minimum Accepted Value:……………MΩ
Time Insulation Resistance In MΩ
L1-L2+L3+G L1-L2+L3+G L2+L3+G
15 sec
30 sec
60 sec
2 Min
3 Min
4 Min
5 Min
6 Min
7 Min
8 Min
9 Min
10 Min
3.1
1 Dielectric Absorption Factor for Generators Less then 150KVA
DAF = R60/R15
U-V+W+G V-U+W+G W-U+V+G
Name:
Signature:
Date:
Customer : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Testing of Form No: TS-MT01,
Generator Page 3 of 4
Date:13/02/09 Revision: 0
Name:
Signature:
Date:
Customer : SEC-COA Riyadh Power plant # 10
Consultant : “10721026/00”
Contractor : BEMCO
Testing of Form No: TS-MT01,
Generator Page 4 of 4
Date:13/02/09 Revision: 0
IR @ 250v dc
Measurement L1-L2 L2-L3 L3-L1 L1-L2 L2-L3 L3-L1 L1-L2 L2-L3 L3-L1
of Voltage in
volts
Measurement L1 L2 L3 L1 L2 L3 L1 L2 L3
of current in
amps
Name:
Signature:
Date: