Professional Documents
Culture Documents
.P'ig . LF L : Docketelj
.P'ig . LF L : Docketelj
. .. , '
ORDER
Total Unserved
To Date
Installed Contracted Generation Energy
IPP's Actual
Capacity Energy/Mo. (2012) (2012)
Capacity
(kWh) (kWh)
NPCI
Cummins
11 MW 8MW 1,500,000.00 6,793,759.30 -
Power One 5.5MW 4.2MW 1,500,000.00 8,920,170.00 9,079,830.00
Ormin 6.4 MW 5.4 MW 3,800,000.00 39,858,798.00 5,471,202.00
Linao
Cawayan 2.1 MW 1.9MW - 7,336,048.00 -
Mini Hydro
Dulangan
Mini Hydro
1.6MW 1.6MW - 9,645,183.80 -
Global 7.5MW 3.0MW 3,600,000.00 37,972,980.00 5,227,020.00
TOTAL 34.1 MW 24.1 MW . 171,670,771.10 (6,416,771.10)
Installed/Dependable 8 MW /4.4 MW
Capacity
6. Generation Fees
Where:
TGF = Total Generation Fee
ED = Energy Delivered during billing period
ICP = Initial Contract Price
SCPlo = Sase CPI: CPI for the period a month
before the contract was signed
CPln = CPI for period a month before the
anniversary date of contract signing of
the current year
7. Force Majeure
DISCUSSION
- . .. - - - -- --
I
.. _."
_.._.fppl_i~~b~e_R.~teJ~t~eginning of ~016 - J
... ,~
..
~ ~ijl,itt:m!Jil
~;.j~~_Wrh
v'
iiw i,..{.\!iY.D1rr;Iuf1itU:o-mfl
" , ,;_,' y>t'h" ;'/'N ,<'---', ')!
From the above table, the FIT is lower than the CRF with
tunnel cost by PhP1.0222/kWh and higher than without the
tunnel cost by PhPO.819/kWh
WACC
Debt Element
Cost of Debt Net of tax shield 6.5%
Wei ht of Debt 70%
4.55%
18%
30%
5.40%
WACC 9.95%
" .
.~
, ERC CASE NO. 2013-164 RC
ORDER/October 7,2013
Page 9 of 15
Debt Element:
Pre-Tax Cost of Debt - 7.00%
Post-Tax Cost of Debt 6.50% 6.30%
Weight of Debt 70% 70%
4.55% 4.41%
Equity Element
Cost of Equity 18.00% 14.95%
Weight of Equity 30% 30%
5.40% 4.49%
Post-tax WACC 9.95% 8.90%
Pre-tax WACC 14.20% 9.88%
2,010,652,050.00
9.88%
25 Years
219,525,477.97
PhP380,562.26
219,906,040.22
38,544,000
5.7053
Note: Return on Working Capital was computed using the recommended WACC
multiplied to 2 months of Working Capital Requirements for Operation &
Maintenance Expense
@t!l!iliThlID
~
ROMELCO
~~
~
2010-052 RC
~" ..
CHPC
~
~
Luzon 0.900
~
1.1228
NUVELCO 2010-126 RC Smith Bell Luzon 1.800 1.5200
AURELCO 2011-013 RC San Luis MHEPP Luzon 0.800 1.0079
ORMECO 2013-164 RC Catuiran HEPP Luzon 8.000 1.7441
SCPC's
Commission's
Proposed Rates
Approved Difference
Particulars (PhP/kWh)
Feed-In-Tariff (PhP/kWh)
Per TCGR PerPSA
(PhP/kWh)
Calculation Rate
Capacity Fee 6.8751 - - -
O&M Fee 1.7436 - - -
ICP/TCGR 8.6187 6.55 5.90 (0.65)
, ,
ERC CASE NO. 2013-164 RC
ORDER/October 7,2013
Page 12 of 15
B. Rate Impact
SO ORDERED.
(On Leave)
ZENAIDA G. CRUZ-DUCUT
Chairperson
~ DO ~
ALFR GL~ICTORIA
,if~
~
tYAP-TARUC
Commissioner Commissioner
Copy furnished:
5. Commission on Audit
Commonwealth Avenue
Quezon City, Metro Manila