Professional Documents
Culture Documents
Design Criteria and Assumptions
Design Criteria and Assumptions
Design Criteria and Assumptions
A project implemented by
DATE SIGNATURE
04/02/2016
Incidentals/Reimbursables
Activity Outputs/Deliverables Incidentals/Reimbursables
Component 1…..
Comments on Report
Section in Comment by the Contracting Accepted
text Authority/Beneficiaries Yes No Comment
Disclaimer
The contents of this report are the sole responsibility of IDOM and its consortium partners and
can in no way be taken to reflect the views of the European Union.
TABLE OF CONTENTS
1 INTRODUCTION 8
10 DESIGN GUIDE FOR OVERHEAD CONTACT LINE, POWER DISTRIBUTION AND POWER
SUBSTATIONS 71
Codes and standards 71
Operating Conditions 71
10.2.1 General - Ambient Conditions 71
10.2.2 Vehicle requirements 72
10.2.3 Track parameters 72
Electrical parameters for the 25 kV AC network 72
Pantograph – Rolling stock - Track data 73
10.4.1 Rolling stock – Track data 73
10.4.2 Track 73
10.4.3 Pantograph contact forces and uplift 73
Catenary 74
List of tables
Table 4. Comparative Table with TER Standards and Parameters versus AGC and AGTC 33
List of figures
1 INTRODUCTION
The objective of this document is to provide a design guide considering all the different railways
guides of appliance and the Terms of Reference.
The document is structured in order to define the parameters included in each guide of
appliance for each area such as: alignment, geotechnical and tunnel design, tunnel safety,
security and telecommunications, bridges design, signalling and interlocking devices,
telecommunications and overhead contact line.
For all of this areas it is also defined those parameters stablished as requirements on the Terms
of Reference.
TSI
ASPECT TSI SPECIFICATIONS CONTRACT SPECIFICATIONS SELECTED PARAMETER
SECTION
TSI CATEGORIES OF LINE
TSI
4.2.1 Performance parameters for
Categories of
(Table 2) passenger and freight traffic
Line
A. LINE LAYOUT
A. LINE LAYOUT
A. LINE LAYOUT
Minimum radius The minimum horizontal design curve radius for new Minimum radius:
4.2.3.4. R min = 500 m
of horizontal curve lines shall not be less than 150 m. R min = 500 m
A. LINE LAYOUT
B. TRACK PARAMETERS
Nominal track European standard nominal track gauge shall be 1435
4.2.4.1. 1435 mm 1435 mm
gauge mm.
Freight and mixed traffic ballasted track design cant =
Maximum cant value:150 mm Maximum cant value: 140 mm
160mm.
The design cant on tracks adjacent
Cant 4.2.4.2. The design cant on tracks adjacent to station platforms
to station platforms where trains
where trains are intended to stop in normal service
are intended to stop in normal
shall not exceed 110 mm.
service shall not exceed 110 mm.
B. TRACK PARAMETERS
y = ((TG-SR)-1)/2 if 5mm ≤ (TG – SR) < 7mm
y = 2 mm, if (TG – SR) < 5mm
Where TG is the track gauge and SR is the distance
between the flange contact faces of the wheelset.
No assessment of equivalent conicity is required for
switches and crossings.
Design values of track gauge, rail head profile and rail
inclination for plain line shall be selected to ensure that
the equivalent conicity limits set out in Table 10 are not
exceeded. [Limit 0.25].
B. TRACK PARAMETERS
The design of railhead profiles for plain line shall
comprise:
(a) a lateral slope on the side of the railhead angled to
between vertical and 1/16 with reference to the
vertical axis of the railhead;
(b) the vertical distance between the top of this lateral
slope and the top of the rail shall be less than 20 mm;
(c) a radius of at least 12 mm at the gauge corner;
(d) the horizontal distance between the crown of the
rail and the tangent point Shall be between 31 and 37,5
mm.
B. TRACK PARAMETERS
The rail shall be designed to be either vertical or
inclined (from the range 1/20 to 1/40).
Rail inclination.
Requirements for Either vertical or inclined (from the
4.2.4.7.2. n/a
switches and The inclination can be given by the shape of the active range 1/20 to 1/40).
crossings part of the rail head profile.
Use of swing nose For speeds higher than 250 km/h switches and
4.2.5.2.
crossing. crossings shall be equipped with swing-nose crossings.
Maximum
The design value of the maximum unguided length of
unguided length
4.2.5.3. fixed obtuse crossings shall be in accordance with the n/a
of fixed obtuse
requirements set out in Appendix J to this TSI.
crossings.
Resistance of new
The nosing force shall be taken into account in the
bridges to traffic See Eurocode 1: Actions on
4.2.7.1.4. design of structures as set out in EN 1991-2:2003/ n/a
loads. Nosing structures
AC:2010 point 6.5.2.
forces
Resistance of new
bridges to traffic
Traction and braking forces shall be taken into account
loads. Actions due
in the design of structures as set out in EN 1991- See Eurocode 1: Actions on
to traction and 4.2.7.1.5. n/a
2:2003/AC:2010 paragraphs 6.5.3 (2)P, (4), (5), (6).and structures
braking
(7)P.
(longitudinal
loads)
Resistance of new
The maximum total design track twist due to rail traffic
bridges to traffic
actions shall not exceed the values set out in paragraph See Eurocode 1: Actions on
loads. Design 4.2.7.1.6. n/a
A2.4.4.2.2(3)P in Annex A2 to EN 1990:2002 issued as structures
track twist due to
EN 1990:2002/A1:2005.
rail traffic actions
Immediate action
The immediate action limits for isolated defects in
limits on track
alignment are set out in point 8.5 of EN 13848-
geometry defects.
4.2.8.1. 5:2008+A1:2010. Isolated defects shall not exceed the n/a
The immediate
limits of wavelength range D1 as set out in Table 6 of
action limit for
the EN Standard.
alignment
Immediate action
The immediate action limits for isolated defects in
limits on track
longitudinal level are set out in point 8.3 of EN 13848-
geometry defects.
4.2.8.2. 5:2008+A1:2010. Isolated defects shall not exceed the n/a
The immediate
limits of wavelength range D1 as set out in table 5 of
action limit for
the EN Standard.
longitudinal level
The maximum cant allowed in service is 180 mm. Maximum cant value:
Immediate action
limits on track
geometry defects.
4.2.8.5. The maximum cant allowed in service is 190 mm for
The immediate 150 mm
action limit for dedicated passenger traffic lines.
cant
G. PLATFORMS
According tom the
Usable length of
requirements of PERI:
platforms where
The usable length of a platform shall be defined Length of platforms in main stations: Length of platforms in Kriva
trains are 4.2.9.1.
according to point 4.2.1. 400 m (220 m for the halts). Palanka station: 170 m
intended to stop
Length of platforms in Zidilovo
in normal service
halt: 100 m
The nominal platform height shall be 550 mm or 760
mm above the running surface for radius of 300 m or
more.
The nominal platform height
Platform height 4.2.9.2. For platforms where trains, which are outside the
adopted is 550 mm
scope of the locomotives and passengers TSI, are
intended to stop, different provisions for the nominal
platform height might apply.
The distance between the track centre and the
platform edge parallel to the running plane (bq), as
defined in chapter 13 of EN 15273-3:2013, shall be set
on the basis of the installation limit gauge (b qlim). The
Platform offset 4.2.9.3. installation limit gauge shall be calculated on the basis
of the gauge G1.
The platform shall be built close to the gauge within a
maximum tolerance of 50 mm.
Track adjacent to the platforms for new lines shall
Track layout preferably be straight, but shall nowhere have a radius
alongside 4.2.9.4 of less than 300 m.
platforms No values are specified for an existing track alongside
new, renewed or upgraded platforms.
In addition, to clarify the requirements of AGC and AGTC, table below shows an overview of parameters of TER Standards and Parameters versus for
AGC and AGTC lines:
Table 4. Comparative Table with TER Standards and Parameters versus AGC and AGTC
The railway tunnels will use a classical two-pass lining system: Initial lining + final lining.
The initial lining will be design designed to work during tunnel construction. It will fulfil the
following functions:
Provide immediate support to the excavation
Restrict tunnel deformations to acceptable levels
Safely stabilize the excavation until the execution of the final lining
On the other hand, the final lining will be designed to work during the service life of the tunnels,
providing waterproofing and ground support. It will fulfill the following:
Act as permanent tunnel lining and fulfil the environmental constraints
Ensure permanent compliance with tunnel operating clearances
Provide support for fixed permanent services and mobile equipment
Withstand seismic loads
Water tightness as per specifications
Fire resistance
A comprehensive design approach will be used to provide a detailed and robust design for the
SEM tunnels. Preliminary Design of the initial lining will be based on empirical methods while
the soil-structure interaction will be addressed by means of numerical models during the Final
Design stage. The following flow chart shows the design approach proposed to design
SEM/NATM tunnels:
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
Prevent Unauthorised access to technical rooms shall be prevented.
unauthorised access
4.2.1.1. Where emergency exits are locked for security purposes, it shall always
to emergency exits
and technical rooms be possible to open them from inside.
In the event of fire, the integrity of the tunnel lining shall be maintained
for a period of time that is sufficiently long to permit self-rescue,
evacuation of passengers and staff and intervention of the emergency
response services. That period of time shall be in accordance with the
evacuation scenarios considered and reported in the emergency plan.
Fire resistance of
4.2.1.2. In the cases of immersed tunnels and tunnels which can cause the
tunnel structures
collapse of important neighbouring structures, the main structure of
the tunnel shall withstand the temperature of the fire for a period of
time that is sufficient to allow evacuation of the endangered tunnel
zones and neighbouring structures. This period of time shall be
reported in the emergency plan.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
This specification applies to all tunnels of more than 1 km in length.
A safe area shall allow the evacuation of trains that use the tunnel. It
shall have a capacity corresponding to the maximum capacity of the
trains planned to be operated on the line where the tunnel is located.
The safe area shall maintain survivable conditions for passengers and
staff during the time needed for the complete evacuation from the safe
Safe area 4.2.1.5.1. area to a final place of safety.
The lay-out of an underground safe area and its equipment shall take
into account the control of smoke, in particular to protect people who
use the self-evacuation facilities.
Access to the safe One of the following solutions shall be selected for access points from
4.2.1.5.2. a train to the safe area:
area
(1) Lateral and/or vertical emergency exits to the surface. These exits
shall be provided at least every 1 000 m.
(2) Cross-passages between adjacent independent tunnel tubes, which
enable the adjacent tunnel tube to be employed as a safe area. Cross-
passages shall be provided at least every 500 m.
39 Design criteria and assumptions
13 December, 2016
Preparation of Detailed design and tender documentation for construction of new railway
This project is funded by the European Union section Kriva Palanka – Border with Republic of Bulgaria, as part of Corridor VIII:
EuropeAid/136050/IH/SER/MK
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
(3) Alternative technical solutions providing a safe area with a
minimum equivalent safety level are permitted. The equivalent level of
safety for passengers and staff shall be demonstrated using the
Common Safety Method on risk assessment.
Doors giving access from the escape walkway to the safe area shall
have a minimum clear opening of 1.4 m wide and 2.0 m high.
Alternatively it is permitted to use multiple doors next to each other
which are less wide as long as the flow capacity of people is
demonstrated to be equivalent or higher.
After passing the doors, the clear width shall continue to be at least 1.5
m wide and 2.25 m high.
The way in which the emergency response services access the safe area
shall be described in the emergency plan.
This specification applies to all tunnels of more than 1 km in length.
Communication Communication shall be possible, either by mobile phone or by fixed
4.2.1.5.3.
means in safe areas connection from underground safe areas to the control centre of the
Infrastructure Manager.
This specification applies to all tunnels of more than 0.5 km in length.
Emergency lighting shall be provided to guide passengers and staff to a
safe area in the event of an emergency.
Illumination shall comply with the following requirements:
Emergency lighting
4.2.1.5.4. (1) Single-track tube: on the side of the walkway.
on escape routes
(2) Multiple-track tube: on both sides of the tube.
(3) Position of the lights: Above the walkway, as low as possible, so as
not to interfere with the free space for the passage of persons, or built
into the handrails.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
(4) The maintained illuminance shall be at least 1 lux at a horizontal
plane at walkway level.
Autonomy and reliability: an alternative power supply shall be available
for an appropriate period of time after failure of the main power
supply. The time required shall be consistent with the evacuation
scenarios and reported in the Emergency Plan.
If the emergency light is switched off under normal operating
conditions, it shall be possible to switch it on by both of the following
means:
(1) Manually from inside the tunnel at intervals of 250 m.
The escape signage indicates the emergency exits, the distance and the
direction to a safe area.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
(2) The minimum vertical clearance above the walkway shall be 2.25 m.
(2) Handrails shall be angled at 30° to 40° to the longitudinal axis of the
tunnel at the entrance to and exit from an obstacle.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
For the purpose of this clause, two or more consecutive tunnels will be
considered as a single tunnel unless both of the following conditions
are met:
(1) The separation between tunnels in open air is longer than the
maximum length of the train intended to be operated on the line + 100
m and
(2) The open air area and track situation around the separation
between tunnels allow passengers to move away from the train along
a safe space. The safe space shall contain all passengers of the
Fire fighting points 4.2.1.7. maximum capacity of the train intended to be operated on the line.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM INFRASTRUCTURE
(2) The intended stopping position of the affected train shall be
indicated to the train driver. This shall not require specific on-board
equipment (all TSI compliant trains must be able to use the tunnel).
(3) The fire fighting points shall be accessible to the emergency
response services. The way the emergency response services access
the fire fighting point and deploy equipment shall be described in the
emergency plan.
(4) It shall be possible to switch off the traction energy supply and earth
the fire fighting points electrical installation, either locally or remotely.
Requirements for fire fighting points outside the portals of the tunnel:
In addition the open air area around the fire fighting point shall offer a
minimum surface of 500 m2.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM ENERGY
This specification applies to tunnels of more than 5 km in length.
The traction energy supply system in tunnels shall be divided into
sections, each not exceeding 5 km. This specification applies only if the
signalling system permits the presence of more than one train in the
Segmentation of tunnel on each track simultaneously.
overhead line or 4.2.2.1.
conductor rails Remote control and switching of each ‘switching section’ shall be
provided.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM ENERGY
Subsystem Energy.
Reliability of Electrical installations relevant for safety (Fire detection, emergency
4.2.2.5. lighting, emergency communication and any other system identified
electrical
installations by the Infrastructure Manager or contracting entity as vital to the
safety of passengers in the tunnel) shall be protected against damage
arising from mechanical impact, heat or fire.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM ENERGY
The distribution system shall be designed to enable the system to
tolerate unavoidable damage by (for example) energizing alternative
links.
CONTRACT
ASPECT TSI SECTION TSI SPECIFICATIONS SELECTED PARAMETER
SPECIFICATIONS
SUBSYSTEM ROLLING STOCK
Material requirements
Measures to prevent
4.2.3.1. Specific measures for flammable liquids
fire
Hot axle box detection
Measures to detect Automatic fire fighting system for freight diesel units
4.2.3.2.
and control fire
Fire containment and control systems for passenger rolling stock
Running capability
Figure 3. Cross section for tunnels L<500 m Figure 4. Cross section for tunnels L>500 m
Applied parameters
Materials
CONSTRUCTION MATERIALS
Superstructure: 3.5cm
4.2.6.3. Longitudinal track resistance. Lateral track resistance (including switches and
crossings).
Shall take into account at least the following forces:
(a) Lateral forces; Maximum lateral forces exerted by a wheel set on the track for defined test
conditions are defined in EN 14363:2005 point 5.3.2.2.
(b) Quasi-static guiding forces; Maximum quasi-static guiding forces Yqst for defined radii and
test conditions are defined in EN 14363:2005 point 5.3.2.3.
Rails
The following specifications are found in the Infrastructure subsystem TSI:
4.2.6.3. Longitudinal track resistance. Lateral track resistance (including switches and
crossings).
Shall take into account at least the following forces:
(a) Lateral forces; Maximum lateral forces exerted by a wheel set on the track for defined test
conditions are defined in EN 14363:2005 point 5.3.2.2.
(b) Quasi-static guiding forces; Maximum quasi-static guiding forces Yqst for defined radii and
test conditions are defined in EN 14363:2005 point 5.3.2.3.
4.2.8.6. Immediate action limits on track geometry defects. The immediate action limits for
switches and crossings.
(1) The technical characteristics of switches and crossings shall comply with the following in-
service values:
(a) Maximum value of free wheel passage in switches: 1 380 mm.
This value can be increased if the infrastructure manager demonstrates that the actuation and
locking system of the switch is able to resist the lateral impact forces of a wheelset.
(b) Minimum value of fixed nose protection for common crossings: 1 392 mm. This value is
measured 14 mm below the running surface, and on the theoretical reference line, at an
appropriate distance back from the actual point (RP) of the nose as indicated in Figure 2.
For crossings with point retraction, this value can be reduced. In this case the infrastructure
manager shall demonstrate that the point retraction is sufficient to guarantee that the wheel
will not hit the nose at the actual point (RP).
(c) Maximum value of free wheel passage at crossing nose: 1 356 mm.
(d) Maximum value of free wheel passage at check rail/wing rail entry: 1 380 mm.
(e) Minimum flangeway width: 38 mm.
(f) Minimum flangeway depth: 40 mm.
(g) Maximum height of check rail: 70 mm.
(2) All relevant requirements for switches and crossings are also applicable to other technical
solutions using switch rails, for example side modifiers used in multi-rail track.
Ballast
The following specifications are found in the Terms of reference:
Ballast: Crushed stone in accordance with EN13450. Ballast prism with minimum depth
of 33 cm under lower plane of sleepers.
Sleepers
The following specifications are found in the Terms of reference:
Sleepers: Pre-stressed mono-block concrete sleepers, it shall be one-piece compliant
with UIC recommendations and local regulations. Wooden sleepers may be foreseen on
bridges and viaducts, in tunnels and on turnouts, if found technically unavoidable or
justifiable, but as an exception only.
Slab track should be envisaged in the construction of bridges and tunnels if it is better
solution.
Sleeper spacing: 60 cm.
Fastenings
The following specifications are found in the Terms of reference:
Fastening: Elastic fastening system, contemporary and adapted to approved prestressed
concrete sleeper supplied with elastic (rubber) rail pad and adequate elastic spring.
Rails
The following specifications are found in the Terms of reference:
Rails: UIC-60/or 60E1, required quality of steel 900A (R260), CWR-rails welded in
continuous railway track. Higher steel grade may be used if deemed necessary.
Buildings
6.2.1 Codes and standards
The codes and standards selected are:
Infrastructure subsystem TSI.
Persons with reduced mobility TSI.
EN 1991-2:2003/AC:2010: Eurocode 1: Actions on structures. Part 2: Traffic loads on
bridges.
EN 81-70:2003+A1:2004: Safety rules for the construction and installations of lifts -
Particular applications for passenger and good passenger lifts - Part 70: Accessibility to
lifts for persons including persons with disability
EN 115-1:2008+A1:2010: Safety of escalators and moving walks. Construction and
installation.
EN 12464-2:2014: Light and lighting. Lighting of work places. Outdoor work places.
EN 12464-1:2011: Light and lighting. Lighting of work places. Indoor work places.
4.2.1.1. Parking facilities for persons with disabilities and persons with reduced mobility.
Where a station specific parking area exists, there shall be sufficient and adapted parking spaces
reserved for persons with disabilities and persons with reduced mobility eligible to utilise them
at the nearest practicable position, within the parking area, to an accessible entrance.
Ramps shall be installed for persons with disabilities and persons with reduced mobility unable
to use stairs where lifts are not provided. They shall have a moderate gradient. A steep gradient
is allowed for ramps on short distances only.
Stairs and ramps shall be provided with handrails on both sides and at two levels.
Lifts shall be provided where ramps are not available and shall be at least of type 2 in accordance
with the specification referenced in Appendix A, index 1. [Appendix A index 1 specifies the use
of EN 81-70:2003+A1:2004. Point 5.3.1, table 1].
Escalators and moving walks shall be designed in accordance with the specification referenced
in Appendix A, index 2. [Appendix A index 2 specifies the use of EN 115-1:2008+A1:2010].
Level track crossings can form part of an obstacle-free route when they comply with the
requirements of point 4.2.1.15. [Point 4.2.1.15. is included in this document.]
On each platform where passengers are allowed to wait for trains, and at every waiting area,
there shall be a minimum of one area fitted with seating facilities and a space for a wheelchair.
When this area is weather protected, it shall be accessible by a wheelchair user.
4.2.1.9. Lighting.
The illuminance level of the external areas of the station shall be sufficient to facilitate way
finding and to highlight the changes of level, doors and entrances.
The illuminance level along obstacle-free routes shall be adapted to the visual task of the
passenger. Particular attention shall be paid to the changes of levels, ticket vending offices and
machines, information desks and information displays.
The platforms shall be illuminated according the specification referenced in Appendix A, index 3
and index 4. [Appendix A index 3 specifies the use of EN 12464-2:2014 Table 5.12, except points
5.12.16 and 5.12.19. and Appendix A index 4 specifies the use of EN 12464-1:2011 Point 5.53.1.]
Emergency lighting shall provide sufficient visibility for evacuation and for identification of fire-
fighting and safety equipment.
The minimum width of the platform without obstacles shall be the width of the danger area plus
the width of two opposing freeways of 80 cm (160 cm). This dimension may taper to 90 cm at
the platform ends. It is permitted to have obstacles inside this freeway of 160 cm. Equipment
required for the signalling system and safety equipment shall not be considered as obstacles in
this point. The minimum distance from obstacles to the danger area shall be according to the
following table:
If there are auxiliary facilities on-board trains, or on the platform, to allow wheelchair users to
board on or alight from trains, a free space (no obstacles) of 150 cm from the edge of the facility
towards the direction where the wheelchair boards/lands at/to the platform level, shall be
provided where such facilities are likely to be used. A new station shall meet this requirement
for all trains that are planned to stop at the platform.
The boundary of the danger area, furthest from the rail side edge of the platform, shall have a
visual marking and tactile walking surface indicators.
The visual marking shall be a contrasting, slip resistant, warning line with a minimum width of
10 cm.
Tactile walking surface indicators can be one of the two types:
An attention pattern indicating a hazard at the boundary of the danger area.
A guiding pattern indicating a path of travel at the safe side of the platform.
The material at the rail side edge of the platform shall contrast with the darkness of the gap.
o The ramp surface shall be slip resistant and shall have an effective clear width of a
minimum of 760 mm.
o Ramps having a clear width of less than 1 000 mm shall have raised edges on both sides
to prevent mobility aid wheels from slipping off.
o The upstands at both ends of the ramp shall be bevelled and shall not be higher than 20
mm. They shall have contrasting hazard warning bands.
o The ramp shall be equipped with a mechanism to securely locate the ramp so that it is
not subject to displacement when in use for boarding or alighting.
o The ramp shall be provided with self-contrasting markings. ]
If a platform lift is used, it shall comply with the requirements of point 5.3.1.3. [Those
requirements are:
o Lifts shall be designed and assessed for an area of use defined by the maximum vertical
gap they can overcome.
o Lifts shall accommodate a wheelchair with characteristics as detailed in appendix M.
o Lifts shall withstand a weight of at least 300 kg, placed at the centre of the device
distributed over an area of 660 mm by 660 mm.
o The lift platform surface shall be slip resistant.
o At surface level, the lift platform shall have a minimum clear width of 800 mm and a
length of 1200 mm. According to appendix M, an additional length of 50 mm shall be
available for feet above a height of 100 mm above the lift platform, considering both
inboard and outboard orientations of the wheelchair user.
o The bridging plate overriding the gap between the lift platform and the carriage floor
shall have a minimum width of 760 mm.
o Where provided, each control for deploying, lowering to ground level, raising and
stowing the lift shall require continuous manual pressure by the operator and shall not
allow an improper lift sequencing when the lift platform is occupied.
o The lift shall incorporate a method of deploying, lowering to ground level with a lift
occupant, and raising and stowing the empty lift if the power to the lift fails.
o No part of the lift platform shall move at a rate exceeding 150 mm/second during
lowering and lifting an occupant, and shall not exceed 600 mm/second during deploying
or stowing (except if the lift is manually deployed or stowed).
o The maximum lift platform horizontal and vertical acceleration when occupied shall be
0.3 g.
o The lift platform shall be equipped with barriers to prevent any of the wheels of a
wheelchair from rolling off the lift platform during its operation.
o A movable barrier or inherent design feature shall prevent a wheelchair from rolling off
the edge closest to the vehicle until the lift is in its fully raised position.
o Each side of the lift platform which extends beyond the vehicle in its raised position shall
have a barrier a minimum 25 mm high. Such barriers shall not interfere with
manoeuvring into or out of the aisle.
o The loading-edge barrier (outer barrier) which functions as a loading ramp when the lift
is at ground level, shall be sufficient when raised or closed, or a supplementary system
shall be provided, to prevent a power wheelchair from riding over or defeating it.
o The lift shall permit both inboard and outboard orientation of the wheelchair user.
o The lift shall be provided with self-contrasting markings.]
A secure storage method shall be provided to ensure that boarding aids, including portable
ramps, when stored on a platform, do not cause an obstruction or pose any hazard to
passengers.
Where:
Q = (m3/s); the discharge
1/n=K; the roughness coefficient depending on the wall properties
A = (m2); the wet cross-sectional area
V = (m/s); the flow velocity
R = (m); the hydraulic radius where R = A/ Π
Π = (m); the wetted perimeter
S; the slope of the energy line in absolute arithmetic units. For uniform flow the slope
Sis equal to the bed slope.
The roughness coefficient n of the Manning - Strickler formula shall be taken equal to:
0.016 for concrete sewer pipes and lined external ditches.
0.018 for box culverts
0.025 for training works with gabions
0.030 for natural streambed
The freeboard of new box and pipe culverts can be 0 when the calculations are carried out with
a return period of critical rainfall - T=100 years.
When the calculations of the new transverse drainage work are carried out with a return period
of critical rainfall event equal to 50 years the freeboard is as following:
For culverts with a width of B <= 4.0 m, Freeboard = 0.50 (m)
For culverts with a width of B >= 4.0 m and bridges, Freeboard = 1.00 (m)
The maximum allowable capacity ymax/D for pipes and pipe culverts is:
For pipes and pipe culverts with D≤400mm, ymax/D≤50%
For pipes and pipe culverts with 400<D≤600mm, ymax/D≤60%
For pipes and pipe culverts with D>600mm, ymax/D≤70%
Operating Conditions
10.2.1General - Ambient Conditions
The electrification system to be implemented for the Overhead Contact Line System is single
phase 25 kV, AC 50 Hz.
The design of the catenary system has to be such that the pantograph of a traction vehicle can
safely collect the traction current from the contact wire at maximum speed 120 km/h for the
following ambient conditions:
minimum temperature -20° C
maximum temperature +40° C
ambient average temperature +15° C
frost creation temperature -5° C
atmospheric pollution level “medium”
relative humidity level “low”
force caused by wind on the OCLS components 60 daN/m2
Mechanical calculations will be based on the following temperature range of the Contact –
Messenger Wire.
Lowest temperature without ice -20° C
Lowest temperature with ice -5° C
Highest temperature: +70° C
Average temperature: +25° C
Additional force on the poles 0.18 daN/m
10.2.2Vehicle requirements
The traction current for each unit of an Electric Locomotive is to be taken from the contact wire
by one pantograph, equipped with two parallel carbon strips.
Lowest permanent voltage (EN 50163) 19.0 kV
Highest permanent voltage (EN 50163) 27.5 kV
Lowest non-permanent voltage (EN 50163) 17.5 kV
Highest non-permanent voltage (EN 50163) 29.0 kV
pantograph pressure (TSI 2011/274/EU) 6-9 daN
10.2.3Track parameters
Gauge nominal at open track 3.00 m
Gauge minimal (TSI requirement) 2.50 m
Gauge minimal inside stations 2.25 m
minimum distance between the center lines of two tracks 4.00 m
minimum distance to allow poles to be placed between tracks 4.70 m
min clearance between live parts of the catenary and earthed structures 0.26 m
In any case, the structure gauge has to be considered for all tracks, also at critical cross sections.
10.4.2Track
Permissible maximum
aerodynamic contact force at 120 N TSI Energy, EN 50119, UIC 794
maximum speed
Catenary
The following table summarises the main catenary design parameters. The values apply to all
types of tracks (open track, main and secondary lines in stations).