Gantt Chart DEMOLITION & CONSTRUCTION WORKS 2PERIODS
Gantt Chart DEMOLITION & CONSTRUCTION WORKS 2PERIODS
Location
: Penong's Restaurant
: GF GMall, Bajada, Davao City
GANTT CHART
Owner : Mr. Joel Asis
Schedule : 2-Months Construction Works
ITEM WEIGHT PHYSICAL Week I Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
SCOPE OF WORKS AMOUNT
NO. (%) TARGET 7 14 21 28 35 42 49 56
PLANNED
1.0 Demolition Works
ACTUAL C
PLANNED
2. 0 Ceiling Works
ACTUAL
PLANNED
3.0 Carpentry Works
ACTUAL
PLANNED
4.0 Steel & Metal Works
ACTUAL
PLANNED
5.0 Tile Works
ACTUAL
PLANNED
6.0 Plumbing Works
ACTUAL
PLANNED
7.0 Electrical Works
ACTUAL
PLANNED
8.0 Painting Works
ACTUAL
PLANNED
9.0 Glass Works
ACTUAL
PLANNED
10.0 Cleaning and Clearing
ACTUAL
D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7 D1 D2 D3 D4 D5 D6 D7
Total
VAT
Cash Flow Requirement Weekly
Total Project Cost