Professional Documents
Culture Documents
Interview Questions (Concrete Related)
Interview Questions (Concrete Related)
Based on the type of work to be done, there are four concrete types;
a. Dry Concrete Mix
b. Ready Concrete Mix
c. Bulk Dry Materials
d. Transit Mix
What are different type of tests performed when concrete reaches at site?
Following tests are performed on site to check if concrete delivered on site is as
per specifications or not;
1. Slump Cone Test
2. Temprature Test
3. Filling of Cube and Cylinder Molds on site for compressive strength test.
4. Dry Shrinkage Test
What is guniting?
It is a process in which a mixture of cement & sand in the proportion of 1:3 is
shooted on a concrete surface with the help of a cement gun under a pressure of
2 to 3 kg/cm2. It is a highly effective process for repairing concrete walls or
damaged surfaces.
What is the cement sand & aggregate ratios for various grades of concrete
mix?
• M10 – 1:3:6
• M15 – 1:2:4
• M20 – 1:1.5:3
• M25 – 1:1:2
• M30 – 1:1:1
Per ACI 306 - For Cold Weather Concreting: For Cold Weather Concreting:
True slump marks a uniform decrease in the mass of concrete in all directions
without any signs of disintegration, retaining the overall shape.
Shear slump shows that a concrete mixture does not have any cohesion, which
results in the shearing of the top portion and a sideways breakdown.
A collapse slump happens when the concrete has excessive water in it. It results
in bleeding and collapses easily because it is unable to hold any kind of shape."
● Start slump test 5 minutes after the production of fresh concrete sample.
Prepare the strength specimens 15 minutes after the production of new
concrete batch.
● If the on-site slump test fails, the site engineer may use his/her contractual
power and reject the concrete and suspend the concreting process.
● The engineer may argue that it is better to refuse the concrete and prevent
future repair works and possibly demolish the structure if the concrete fails
to reach the designated strength.
● When the concrete slump is more than the maximum limit, and concrete
durability is of high importance, it is better to reject the concrete.
● If the slump value is low, add water according to the guidelines in Table-1,
or superplasticizer, in measured amounts, to make concrete more
workable and reach the designated range of slump value. After that, place
the concrete into its position.
● The addition of water to the concrete mix should not increase the
water-cement ratio above the maximum permitted limit as per
specifications.
● If the concrete slump value is too high, the site engineer may allow the
mixer to revolve for 8 to 10 minutes to reduce the slump. If the test still
fails, one may add cement to the concrete mix to minimize slump value.
● After adding water or cement to the concrete mix, remix the batch for 30
revolutions to make sure the additional material is correctly blended with
the fresh concrete.
● Sometimes, the site engineer may decide to mix a concrete batch with a
very high slump value with the concrete batches that have acceptable
slump value during concrete pouring to reduce the former batch's
detrimental effect.
● Sometimes, the concrete slump value, which is less than the minimum
limit, is the indicator for the late concrete placement after its arrival on the
construction site
What are the types of a slump?
True Slump: The concrete mass after the test when slumps evenly all around
without disintegration is called the true slump.
Shear Slump: When one-half of the concrete mass slide down the other is called
the shear slump. This type of slump is obtained in a lean concrete mix.
Collapse Slump: When the sample is collapsed due to adding excessive water, it
is known as collapse slump.
Zero Slump: For very stiff or dry mixes it does not show any changes of the
slump after removing the slump cone.
1) Wrong Mix Poured: The concrete mix prepared is not as per the approved mix
design for that particular strength.
2) Wrong Mix Design: There is a mistake in the concrete mix design. It is not
properly designed and its strength is not properly calculated.
3) Improper Sample Collection: Sometimes concrete sample for the cube test is
not collected by a skilled worker or it may not be checked by a technical person
on site.
So, there may be a possibility that the collected concrete sample is not truly
representing the fresh concrete supplied at the site.
4) Improper Cube Preparation: The concrete cure must be prepared as per the
guidelines given in IS 516.
Improper filling of the moulds: This may result in a weak zone in concrete leaving
only mortar without aggregate
The curing of the concrete cube must be as per the guidelines given in IS 516.
Once the concrete cube is prepared the cubes must be covered with wet gunny
bags for the least period of 24hrs from the time when water is first added to the
concrete.
Then after removed the concrete cube from the molds and kept it under clean
water until the time of the test. Make sure the temperature of curing is between
24˚C to 26 ˚C.
6) Testing Wrong Samples: Properly identify the cube preparation marking on the
cube. Sometimes wrong cube sample test.
7) Errors During Testing: This includes improper placing of moulds over the
CTM, cleaning the surface, seating the cube properly, rate of load application,
etc.
8) Errors With the Testing Apparatus: This may include errors with reading
display, loading or hydraulic systems, or a manual error in reading and
interpreting the displayed value.
11) Batching Plant Error: There may be the possibility of batching plant error
wrong materials quantity added in the mix, due to any mechanical / software
error, which went unnoticed.
However, the suitability of this method depends on other factors also. There are
many options to strengthen a weak concrete member if a concrete cube fails in
the test
6. Concrete Jacketing
The concrete Jacketing involves covering the structural member at any or all
sides with skillfully placed reinforced concrete.
Concrete Jacketing increases the cross-section area of the member and thereby
improves its structural performance.
Conclusion
From the above Solution option, 6 would seem to be the easiest one to overcome
the situation of Concrete Cube Fails in Tests, but there are several impediments
with this method, like disposal of debris, and the practical difficulty in demolition
without damaging other members.
There is also the risks to the safety of the workmen, practical difficulty in
shuttering and casting new member in the original position, quality control, etc
are a few hurdles to mention with this option.
The failure result of a concrete cube is a serious issue. You need to analyze why
the cubes have failed.
By finding out a proper reason for failure, we may avoid further reoccurrences of
the same. concrete cube fails in test after 28 days
When we are doing concreting on site and collecting Samples for the test there
are four possible combinations behind Concrete cube fails in a test as listed
below.
1. It may be, Concrete is strong; the cube is also strong.
Generally, we focus on the first two possibilities while analyzing cube test results,
the third and fourth possibilities are generally neglected.The 3rd option does not
harm the structure. But option four….well…it is better to be optimistic in such
situations.
While you get reports showing that the 28th-day cube tests are failed, remember
that it is something serious. This test result of the 28th day cannot be treated just
like in the case of the 7th-day test failure.
As we know we must attain 99 % strength on the 28th-day cube test result and
tests are considered the deciding criterion for acceptance of the concrete.
Before considering that our 28th-day cube test is failed or passed and going
deep into our scenario of cube failure, let us quickly see how the cube results are
generally interpreted as per IS code.
There are two conditions are to be met for accepting a concrete after cube test
as per IS 456 2000 Cl 16.1,
The average strength of a group of four consecutive test results should not be
less than the greater of fck(20)+ 4 N/mm2 or fck+0.825σ where σ is the standard
deviation established Individual cube strength should not be less than fck – 4
N/mm2
We must consider the following before any decision is taken by the site engineer
on discarding concrete
● cubes filled by a trained supervisor?
● In many cases, I have experienced horrible results from a few labs but the
site engineer should have his own judgment about the place of concrete
failure and taking risks.
● The contractor shall always be happy if reduced rates are paid for such
works but always note any failures needs your pre-action reports as
suggested above and that only a site person can decide to discard
concrete
Spraying water on the fabric regularly, while ensuring there are no pools of water
getting created
Spreading polyethylene sheets on top and fastening their corners and edges to
lock the moisture beneath. Repeating the moistening process for five to seven
days to get the best results"
If you answered the curing procedure correctly, the panel members might ask for
reasons for performing some of the steps in a specific manner. This is an
example of a typical follow-up question designed to test in-depth knowledge of
concrete curing.
Example: "Water pools or ponds on concrete are only suitable in warm weather
where it can evaporate at a sustained rate. In cold weather, the water pools can
freeze and expand, affecting the concrete's overall strength. Moreover, creating
ponds results in wastage of water. In windy areas, polyethylene sheets can be
blown away, increasing the risk of desiccation in the concrete."
M10 = 1:3:4
M15 = 1:2:4
M20 = 1:1.5:3
M25 = 1:1:2
M30 = 1:1:1
Example: "The three different types of slumps are true slump, shear slump, and
collapse slump. True slump marks a uniform decrease in the mass of concrete in
all directions without any signs of disintegration, retaining the overall shape.
Shear slump shows that a concrete mixture does not have any cohesion, which
results in the shearing of the top portion and a sideways breakdown. A collapse
slump happens when the concrete has excessive water in it. It results in bleeding
and collapses easily because it is unable to hold any kind of shape."
Why are steel plates inserted inside bearings in the elastomeric bearing?
What is prestressing?
Some hiring managers can ask this question to check if you know the difference
between ordinary RCC and prestressed concrete. A good way to answer this
question is to define prestressing and then stating the reinforcements. When
listing the techniques, try to mention a brief overview of the processes.
Example: "First, we are required to take future traffic into account based on
existing and projected figures and update the design accordingly. During
construction, we place reinforced cement/rebar stanchions over the freeway to
accommodate the bridge. Off-ramp and on-ramp are constructed to and from the
freeway and bridge. Then, cement slabs are required to be built and placed on
the underlying platform."
Example: "I dealt with a problem on the site of a bungalow construction. While we
were constructing an upper slab, I heard a slight cracking noise. I checked the
supporting structure immediately and found that it was shaking under the weight
of a worker who was standing on top of it. I cautioned him to stop working
immediately, get down, and reinforce the wooden supports, preventing a major
accident."
Example: "I believe that a civil engineering job involves giving better
infrastructure and shelter to people, keeping environmental issues and public
health in mind."
What is the least concrete cover provided for different RCC Members?
• Footing = 50 mm
• Column = 40mm
• Beam = 25mm
• Slab = 20mm
The crank length in Slab is 0.42 D. Where D is Depth of Slab- Top cover –
Bottom Cover.
Generally in the fixed R.C.C. ended Slabs, means column at the ends of the
supports. Those slabs face Two types of moments develop which are called.
The positive moment which is called (Sagging) develops at mid of the span.
Negative moment which is called (Hogging) develops at the supports.
The continuous beam, overhanging beam, etc. all face two types of bending
moments positive and negative so to resist these moments beams and slabs, we
provide bars and give a technical name which we discuss in detail below.
BENT-UP BARS:
1. Bent-up bars or known as Crank bars. We provide in the ends on the top of the
slab or also at the top of the mid supports (if any type of mid support is present)
to counter the negative moment called (Hogging) which produces at that sections
of the slabs and beams.
2. Different Angles on the crank bar (Means bends) are provided in the slabs. In
some cases, we just provide Straight Bars at the end on the top of the slab and in
some cases, we provide angles on the crank bars which is 45°. In some cases,
the 30° bent is provided when shallow beams are present at the end of the slabs.
3. Normally the length of the crank bar is a minimum of 300 millimeters and the
slope or bend on the crank bars (Bent up bars) is 1: 10.
4. By providing crank bars in the R.C.C slabs, The Strength of the slab will be
increased very much from those of the slabs in which crank bars are not present.
CONCLUSION:
The crank bars or bent up bar are very important in R.C.C beam or slab
construction because without countering the Hogging (Negative moment) the
structure will fail or the strength of the structure will reduce. The hogging bending
moment will develop at the supports of the slabs and beams.
How do you check the quality of cement on the site?
• Color: The color should be grey with a light greenish shade and it should be
uniform. Color gives an indication of excess lime or clay.
• Float test: A good cement won’t float if you throw a cement in water.
• When you put your hand in a cement bag you should feel cool.
The unit weight of concrete depends on the type of aggregates and the amount
of voids. As per IS : 456-200 Unit weight of PCC is 24KN/m3 and RCC is
25KN/m3.
Honeycomb, also known as airpocket, is nothing but the air voids in concrete. It
is usually formed during concrete casting.
What is the initial and final setting time of ideal cement mix?
Initial setting time for ideal cement mix is around 30 minutes for almost all kind of
cements. For masonry cement it can be 90 minutes. Final setting time of ideal
cement mix should be 10 hours at max. For masonry cement it shouldn’t exceed
24 hours.
• Ponding.
• Steam curing.
Bleeding is one form of segregation, where water comes out to the surface of the
concrete, being the lowest specific gravity among all the ingredients of concrete.
There are various types of cement which are: Ordinary Portland Cement (OPC),
White Portland Cement (WPC), Portland Pozzolana Cement (PPC), Low Heat
Portland Cement, Coloured Portland Cement, Hydrophobic cement, Rapid
Hardening Cement, Portland Slag Cement, Sulphate resisting Portland Cement,
etc.
A pile foundation is adopted when the Soil bearing capacity is less than
24KN/M3.
Stirrups are provided to handle the shear force and to hold the rebars (main bars)
in position.
What do you know about “TMT”?
TMT stands for “Thermo Mechanically Treated”. Generally, we use TMT bars and
sheets for construction purposes for the reason that they have high strength and
high corrosion resistance compared to normal steels.
There are basically two types of foundation: Shallow & Deep foundations. Again
shallow foundations can be classified as spread footing, combined footing, strap
or cantilever footing and finally mat or raft footing. Deep foundations can be
classified as pile footing, pier footing, caissons footing, and well foundation.
• Site Engineer.
• Contractor.
• Mistri.
•Mason/labor.
What is grouting?