RAW MATERIAL STEP 1

Pipe 2" x 16Ga Wall Lenght: 20'2" min. Cut to lenght 11-15/16"
1.226 lbs/ft 2 pcs per assembly
250 section/month 6,200 lbs/month 5000 pieces required/month
Cut by package, 25section x 20pcs/section
Requirement: 20 cuts x 5 min = 120min
10 package 25pcs 250 pcs/hour = 20 hours required

Time to procces 5000 pcs: 20 hours x 80% efficiency=


25 hours
2.5 days-one person

Pipe 1-7/8" x 16Ga Wall x 20'2" min. Cut to lenght 11-15/16"


1.16 lbs/ft 5 pcs per assembly
500 section/month 11,700 lbs/month 10,000 pieces required/month
Cut by package, 25section x 20pcs/section
Requirement: 20 cuts x 5 min = 120min
10 package 25pcs 250 pcs/hour = 40 hours required

Time to procces 10,000pcs: 40 hours x 80% efficiency=


50 hours
5 days-one person

Sheet metal coil 12Ga x 6.800Width" Cut to lenght 18"


2.26 lbs/ft 1 pcs per assembly
8,475 lbs/month 2500 pieces required/month
7 coils of 1250 lbs max Straightener and cut to lenght
10 cuts x min = 250 min
600 pcs/hour = 4. 2hours required

Time to procces 2500 pcs: 4.2 hours x 80% efficiency=


5.2 hours
.52 days-one person
STEP 2 STEP 3
Chamfer bot sides external
Manually put in a sort of chamfering machine
One sibe by time aprox 10 seconds per side,
10 seconds to manipulate and 10 seconds to other side
2 pcs/minute=2,500 minutes required

Time to proccess 5000 pcs: 42 hours / 80%efficiency=50


hours
5 days-one person

Chamfer bot sides external


Manually put in a sort of chamfering machine
One sibe by time aprox 10 seconds per side,
10 seconds to manipulate and 10 seconds to other side
2 pcs/minute=5000 minutes required

Time to proccess 10,000 pcs: 83 hours /


80%efficiency=104 hours
10 days-one person

Punch 9 holes 3/8" diameter