CHANGE OVER & ACETIC ACID PILL PLACEMENT PLAN, 14.10.

2022

 MAKE SURE 1000 BBL 9.2 PPG BRINE IS READY IN PITS.


 PREPARE 50 BBL HI-VIS PILL (80-90 SEC: DRILL WATER+XC OR PAC RG) IN SLUG PIT.
 PUMP ALL HI-VIS FROM SLUG PIT. START DISPLACING WELL WITH BRINE FROM PIT#4.
DUMP RETURNING SEA WATER.
 TOP UP PIT#4 BY USING BRINE FROM GEL PIT, THEN PIT#1, THEN PIT#2.
 PUMP CALCULATED STROKES AND CHECK IF HI-VIS IS AT SURFACE.
 START TAKING RETURN 9.2 PPG BRINE IN PIT. BYPASS SAND TRAPS.
 PREPARE ACETIC ACID PILL IN SLUG PIT: [DRILL WATER 40 BBL+10 JERRYCAN ACETIC
ACID]
 MEANWHILE C&C MUD 01 CYCLE OR TILL IN-OUT MUD WT IS SAME [~9.2 PPG]. MUD
SHOULD BE HOMOGENEOUS OTHERWISE THERE MAY BE WET P/OUT.
 PLACE 30 BLL ACETIC ACID PILL AT BOTTOM [PLACE BALANCED PILL].
 POOH.
 DURING POOH, CLEAN MUD PIT#3 & SAND TRAPS (IF REMAINING). DUMP & CLEAN
THE DEAD VOLUME OF ACETIC ACID PILL FROM SLUG PIT ALSO.