Professional Documents
Culture Documents
5.3 Processing 2 Jobs K Machines
5.3 Processing 2 Jobs K Machines
machines
1
Introduction
• Let there be two jobs 1 and 2 each of which is to processed on k
machines say M1, M2, --- , Mk in two different orders.
• The exact or expected processing time on all the given machines are
known.
• Step II: Mark the processing time for jobs 1 and 2 on the horizontal
and vertical lines respectively according to the given order of
machines.
• The horizontal segment of this line indicates that first job is under
process while second job is idle.
• Similarly, The vertical segment of this line indicates that second job
is under process while first job is idle.
• The diagonal segment of this line shows that both the jobs are under
process simultaneously.
4
• Step V: An optimum path is one that minimizes the idle time for
both the jobs. Thus, we must choose the path on which diagonal
movement is maximum.
• Step VI: The total elapsed time is obtained by adding the idle time
for either job to the processing time for that job.
5
Problems
1. Two jobs are to be performed on five machines A, B, C, D, and E.
Processing times are given in the following table.
6
Solution
• Mark the processing times of job 1 & job 2 on X-axis & Y-axis
respectively.
7
• Starting from origin O, move through the 450 line until a point
marked finish is obtained.
• The elapsed time can be calculated by adding the idle time for
either job to the processing time for that job.
• In this illustration, idle time for job 1 is 5 i.e., (2+3) hours.
• Elapsed time = Processing time of job 1 + Idle time of job 1
= (3 + 4 + 2 + 6 + 2) + 5 = 17 + 5 = 22 hours.
• Likewise, idle time for job 2 is 2 hours.
• Elapsed time = Processing time of job 2 + Idle time of job 2
= (5 + 4 + 3 + 2 + 6) + (2) = 20 + 2 = 22 hours.
8
2. Use graphical method to minimize the time needed to process the
following jobs on the machines shown below, i.e., for each machine
find the job which should be done first. Also calculate the total time
needed to complete both the jobs.
Machine
Job 1 Sequence A B C D E
Time 2 3 4 6 2
Job 2 Sequence C A D E B
Time 4 5 3 2 6
9
Solution
• Mark the processing times of job 1 & job 2 on X-axis & Y-axis
respectively.
10
• Starting from origin O, move through the 450 line until a point
marked finish is obtained.
• The elapsed time can be calculated by adding the idle time for
either job to the processing time for that job.
• In this illustration, idle time for job 1 is 3 hours.
• Elapsed time = Processing time of job 1 + Idle time of job 1
(2 + 3 + 4 + 6 + 2)= 17 + 3 = 20 hours.
• Likewise, idle time for job 2 is 0 hours.
• Elapsed time = Processing time of job 2 + Idle time of job 2
= (4 + 5 + 3 + 2 + 6) + (0) = 20 = 20 hours.
11
Practice Problems
1. Use graphical method to minimize the time needed to process
the following jobs on the machines shown below, i.e., for
each machine find the job which should be done first. Also
calculate the total time needed to complete both the jobs.
Machine
Job 1 Sequence A B C D E
Time 6 8 4 12 4
Job 2 Sequence B C A D E
Time 10 8 6 4 12
12