Site Name: Kokar

20/3/2021
D. L. R.
Details
Mason 24 Nos
Helper 17 Nos
Reja 11 Nos
Total 52 Nos
Work Description Qty Unit
3nd Mazenine floor Ceiling and wall palster work in progress
Sand and chaips shifting work progress
Plaster work progress in ground floor
Store room side dismantling work in progress
Car lift area Shuttering work in progress front side
shuttering work in progress in front side of ground floor
Car lift up side area reinforcement of beam work Complete

Material Received Qty Unit


Cement 100 bag mahadev steel
chips 3/4" (20 mm -15ton 880kg) 1 Dumper Sharawan garodia
Welding rod 2 packet from office
Nail 1.5" 4.77 kg from office
Nail 2.5" 3.3 kg from office
welding cable with holder 1 nos from office
new Patra 190 Nos Bajrangbali timber
Hire Equipment
Site Name:Anantpur
20/3/2021
D. L. R.
Details
Mason 2 Nos
Helper 0 Nos
Reja 3 Nos
Total 5 Nos
Work Description Qty Unit
Plaster work progress in outer side wall
Window Jam

Material Received Qty Unit

Hire Equipment
Site Name:Ketaribagan
20/3/2021
D. L. R.
Details
Mason 0 Nos
Helper 1 Nos
Reja 0 Nos
Total 1 Nos
Work Description Qty Unit
Curing work in progress

Material Received Qty Unit


Site Name:Meera
20/3/2021
D. L. R.
Details
Mason 5 Nos
Helper 3 Nos
Reja 4 Nos
Total 12 Nos
Work Description Qty Unit
Shuttering and casting of 2 nos columndone
lapping of 2 column
2 Stater layout & Casting
steel cutting and ring making
Chips and sand shifting
Material Received Qty Unit
Chips 1 Turbo Dinesh Jee

Hire Equipment
Site Name:Station Road
20/3/2021
D. L. R.
Details
Mason 1 Nos
Helper 1 Nos
Reja 2 Nos
Total 4 Nos
Work Description Qty Unit
Plaster of Door Slab and Kopls
stagging work in back side
Room wall plater work done
Outer side Window wall plaster complete
Dismantling work in progress

Material Received Qty Unit

Hire Equipment
Site Name:Bariatu
20/3/2021
D. L. R.
Details
Mason 4 Nos
Helper 1 Nos
Reja 0 Nos
Bazar Reja 3 Nos
Total 8 Nos
Work Description Qty Unit
Retaing Wall reinforcement work progress
Retaing wall shuttering work in progress
Retaing wall Deshuttering work in progress
Soil filing work in progress

Material Received Qty Unit

Hire Equipment
Site Name:Ormanjhi
20/3/2021
D. L. R.
Details
Mason Nos
Helper Nos
Reja Nos
Total 0 Nos
Work Description Qty Unit
No Work

Material Received Qty Unit

Hire Equipment