Professional Documents
Culture Documents
1 s2.0 S0967070X17301099 Main
1 s2.0 S0967070X17301099 Main
Transport Policy
journal homepage: www.elsevier.com/locate/tranpol
A R T I C L E I N F O A B S T R A C T
Keywords:: This paper investigates financial risk associated with highway infrastructure projects by identifying parameters
NPV-at-risk such as traffic flow and project cost; and further models the risk by analysing real-world PPP based highway
PPP projects in India. It applies the Net Present Value (NPV)-at-risk model tool which uses Monte Carlo Simulation
Uncertainties taking into account the probability distributions for different input parameters, and gives uncertainty associated
Highway infrastructure with NPV. Further, the model is applied to 30 real-world BOT highway projects to identify critical risks and
Monte Carlo Simulation
discuss mitigation strategies. The critical contribution of the paper is towards applying a standard risk-analysis
Project cost
Investment risk
model (NPV-at-risk tool supported by Monte Carlo Simulation) to the real-world PPP based highway infrastruc-
Financial analysis ture projects. The application of the developed model can be used as a decision tool to judge the profitability of a
project and make investment decisions in the bidding phase by the private investors. It also helps in identifying
which source of uncertainty has the most influence on the project’s financial returns and what is the actual
relationship between the critical influencing parameters and associated NPV; this will be helpful to government
agencies and public authorities to identify the factors that have largest impacts and consider the corresponding
mitigation strategies.
1. Introduction sector authority and a private party, in which the private party is
responsible for providing and operating a public service or a project and
India is one of the world’s biggest markets for PPP with over 1300 collect revenues (Delmon, 2011). Because of this, a substantial part of the
major national level infrastructure projects as on 31st March 2014; financial, technical and operational risk associated with the project is
moreover, half of them are road infrastructure projects and have been vested with the private party. The Government of India is looking for-
operated under various models such as BOT, BOT Annuity and Engi- ward to huge investments in infrastructure from private investors and has
neering Procurement and Construction (EPC). (PPP India Database, been focusing on the development of tools and activities to attract more
2014). In India, National Highways Authority of India (NHAI) is a gov- investments through PPP format (Ernst and Young, 2012). The main
ernment agency responsible for the administration and maintenance of a advantages to government from PPP arrangements are in two folds.
network of over 70,000 km of national highways. Indian policy makers Firstly, they can use the private funds to finance their infrastructure
have realized that national highways form the economic backbone of the projects. This is especially very important if the government is facing
country; and a wide gap lies between the demand of the infrastructure fiscal constraints. Secondly, through PPP, they may benefit from the
and the supply available (Shetty, 2012). Therefore, it is crucial to make expertise and experience of a private entity to build and operate a facility
plausible efforts for substantial raise in infrastructure investment and in a more cost-effective way (Delmon, 2011).
improve the quality of infrastructure facilities. Some of the problems Build-Operate-Transfer (BOT) model is a form of PPP which has
associated with transportation infrastructure development include extensive applications in infrastructure projects. In a typical BOT high-
financing, land acquisition and delays in construction. way project, a private entity is authorized to construct and operate a
Public-Private-Partnership (PPP) is a project delivery system that can transportation infrastructure facility and in return, is allowed to collect
address some of these issues. PPP involves a contract between a public tolls for a specified period of time to recover all the costs and earn a
☆
Note: This paper was presented in the E Session, Transport Economics and Finance, at the 14th WCTR in Shanghai in July 2016.
* Corresponding author.
E-mail addresses: velaga@civil.iitb.ac.in, n.r.velaga@iitb.ac.in (N.R. Velaga).
https://doi.org/10.1016/j.tranpol.2017.03.010
Received 1 October 2015; Received in revised form 1 December 2016; Accepted 6 March 2017
Available online 11 March 2017
0967-070X/© 2017 Elsevier Ltd. All rights reserved.
L. Kumar et al. Transport Policy 62 (2018) 2–11
reasonable profit. PPP-BOT projects typically involve high financial risks (WACC) and dual risk-return methods which gives NPV within a confi-
because of their long-term nature and uncertainties associated with dence interval using a Monte Carlo Simulation (MCS) technique (Ye and
projected future cash flows, traffic forecast, delay in construction and Tiong, 2000). Attarzadeh et al. (2011) used different techniques like
cost overrun. One of the major unanswered questions is the risk assess- Fuzzy set theory, probability modelling for decision making using
ment and modelling of these uncertainties for road transport infrastruc- insufficient data about parameters and complete information about their
ture projects. In India, many of the past BOT projects have either been probability.
delayed or abandoned and had to be bailed out by the government due to Wibowo et al. (2012) provided methods for quantifying payments of
inefficient financial risk management and strategy planning. For guarantees given to protect project sponsors from skyrocketing costs of
example, the ‘Vadodara-Halol Toll project’ in Gujarat state which has acquiring land, delays in scheduled toll adjustment, and compensation
been operational since 2000 is currently under loss due to wrong traffic payments in case of nationalization events. Nemuth (2008) implemented
projections, thereby raising both policy and revenue risks for the a two stage model, identifying and analysing the risks and then evalu-
involved parties (Raghuram, 2003). ating using MCS and discussed alternative actions. Further details of
This paper investigates the investment risk associated with a BOT existing state-of-the-art research are illustrated in Table 1.
highway infrastructure project with the help of 30 real-world highway One of the major uncertainties involved in calculating NPV for a
projects. It applies Net Present Value (NPV)-at-risk model providing a highway project is associated with estimating future traffic flow. Bagui
cumulative probability distribution curve for NPV by considering a range and Ghosh (2011) proposed a method to determine lower and upper
of associated parameters and corresponding suitable distributions. The limits of traffic/revenue at risk. Iyer and Sagheer (2011) proposed a
developed model after appropriate customizations can be used as a de- traffic band using binomial lattice method which was combination of
cision tool to judge the profitability of a project and make investment both upper and lower limits of traffic which ensure certainty through an
decisions in the bidding phase by the private investors. It also helps in equitable risk and revenue sharing mechanism. Pathan and Pimplikar
identifying which source of uncertainty (e.g., traffic projections or con- (2013) represented the risk of financing during the post construction
struction delay) has the most influence on the project’s financial returns period due to fluctuation in prime lending rate (PLR) through a case
and what is the actual relationship between the critical influencing study and provided a reasonable agreement to change concession period
parameter and associated NPV. Towards the end of the paper, various corresponding to the change in prime lending rate.
mitigation strategies and its applications have been discussed. The risk associated with a project is the probability of investment’s
actual return being different from the estimated return (Krishnamurthi,
2. Literature review 2008). Risk includes the possibility of losing some or all of the original
investment. Different versions of risk are usually measured by calculating
Prior research endeavours have focused on the analysis of various the standard deviation of historical returns or average returns of a spe-
options like NPV within a confidence interval, binomial lattice, govern- cific investment. Various valuation methods have been used to estimate
ment guarantees and fuzzy set theory to analyse the uncertainties with a the profitability and risk of a project which can be broadly categorized
BOT projects (Iyer and Sagheer, 2011; Attarzadeh et al., 2011; Ashuri into two categories – Discounted cash flow (DCF) models and
et al., 2012; Ye et al., 2013). NPV-at-risk can be used for incorporating Non-Discounted cash flow models. Former gives importance to the time
the risk profile by combining the Weighted Average Cost of Capital value of money and calculates the present value of future and past cash
Table 1
Review of project risk assessment models.
Ye and Tiong Evaluation of investment Monte Carlo Simulation Developed a new method – NPV-at-Risk - by combining the Weighted Average
(2000) decision in infrastructure project Cost of Capital (WACC) and dual risk-return methods which incorporates
confidence interval.
Nemuth Implement risk assessment in estimation Monte Carlo Simulation Implemented a two stage model - Stage 1 includes identifying and analysing the
(2008) procedure and tender process risks and Stage 2 uses Monte Carlo Simulation to evaluate the risks followed by
close monitoring of the risks.
Bagui and Traffic and Revenue Forecast at Risk for a Monte Carlo Simulation, Lower and upper limit of traffic/revenue at risk can be determined using proposed
Ghosh BOT Road Project Regression Analysis method. Regression equations are developed for different confidence limits
(2011) varying standard deviation/mean ratio to determine revenue at various level of
risks.
Iyer and Real options based traffic risk mitigation Binomial lattice Only one risk variable (traffic volume) was considered. NPV was calculated by
Sagheer model for BOT highway projects in India incorporating the traffic guarantee option.
(2011)
Attarzadeh Risk management of Long Term Uncertainty, probabilistic and Decision making based on incomplete or insufficient data and complete
et al. Infrastructure PPP-BOT projects stochastic model, fuzzy set information about the probability
(2011) theory
Ashuri et al. Evaluating BOT Highway Projects with Real options analysis, Risk This approach treats the risk of overestimating future traffic demands internally
(2012) Government neutral valuation method with and adjusts for the traffic market risk in the valuation of MRG options.
Minimum Revenue Guarantee (MRG) MCS
Options
Wibowo et al. Modelling Contingent Liabilities Arising Monte Carlo Simulation, WACC, Provided methods for quantifying payments of guarantees given to protect project
(2012) from Government Capital Asset Pricing Model sponsors from skyrocketing costs of acquiring land, delays in scheduled toll
Guarantees in Indonesian BOT/PPP Toll (CAPM) adjustment, and compensation payments in case of nationalization
Roads
Kokkaew and Modelling Government Revenue Multi Least Squares Monte Carlo Proposed a new model of government revenue guarantees in which key
Chiara Guarantees in PPP road project- a risk method, Variance model parameters are evolved over time to reflect the inter-temporal risk profiles and
(2013) adjusted approach evaluated revenue guarantee, Guarantee period is assumed to be shorter than the
operating period
Ye et al. Venture evaluation of highway BOT Fuzzy Analytic Hierarchy Proposed a step by step process for risk rating by combining AHP with fuzzy set
(2013) project Process model theory. Risk factors considered are independent to each other.
Pathan and Risk Assessment of BOT Road Projects Examines financial risks through Represented the risk of financing in operation period due to fluctuation in prime
Pimplikar a case study analysis lending rate which can be overcome by change in concession period.
(2013)
3
L. Kumar et al. Transport Policy 62 (2018) 2–11
Fig. 1. Methodology.
flows using a discount rate. It includes tools like NPV, internal rate of interpreted and analysed. The steps shown in Fig. 1 summarize the whole
return (IRR) and modified IRR. On the other hand, the latter focuses on methodology used in this paper for developing the NPV-at-risk model.
the time required to recover the initial cost of investment without ac-
counting for the time value of money and includes methods like payback 3.1. Risk identification and assigning probability distribution
period and accounting rate of return. (Atrill and McLaney, 2014).
Time value of money is an important aspect of every investment as all A highway BOT project is influenced by various types of risks and
projects deal with cash flows over a long period of time; thus DCF models each risk is associated with a different parameter as shown in Table 2.
are a better valuation method (IFAC report, 2012). Among different DCF Uncertainties associated with these parameters become a major dif-
models, NPV is the most commonly used valuation method which is ficulty for the investors while analysing profitability of these projects.
calculated as the “difference amount” between the sums of discounted Probability distributions are thus assigned to each parameter as it gives a
cash inflows and outflows. It compares the amount invested today to the probability to various values of a parameter and is very helpful in fore-
present value of the future cash receipts from the investment, taking casting the actual value of parameter. Some of those uncertain parame-
inflation and rate of return into account. The decision rule to be followed ters which have been incorporated in the model developed in this paper
is that a project is acceptable if the NPV is positive. However, this deci- are stated below along with their distributions:
sion rule fails to provide decision-makers with a confidence level.
Therefore, the concept of NPV-at-risk is developed which computes NPV 3.1.1. Traffic
at some specific confidence levels. It mathematically and objectively Annual Average Daily Traffic (AADT) data is used to measure traffic
computes the risk associated with different possible future scenarios and and is calculated in terms of Passenger Car Units (PCU) by using con-
keeps a track of these results. version units shown in Table 3. Revenue from a highway project is
Extensive research has been done for the success and improvement of directly proportional to the number of vehicles passing through it. Thus
BOT projects like including risks associated with future traffic flow, growth in traffic is one of the most critical parameter and prone to risk
lending rate and project cost, but in individualistic approaches. A wide more than any other parameter. This paper focusses on highly congested
gap still persists when it comes to combining uncertainties associated traffic conditions, hence growth in traffic is assumed to have normal
with different parameters in one model while estimating future cash probability distribution with a COV (Coefficient of Variation) of 0.1 (Ye
flows. Further application of such models for real-world PPP based and Tiong, 2000).
highway projects in India is yet to explore. This paper aims to narrow
down the gap by outlining a standard NPV-at-risk tool (supported by 3.1.2. Discount rate
Monte Carlo Simulation) to analyse PPP highway projects and apply such The discount rate refers to the interest rate used in discounted cash
powerful tools for 30 real-world projects. In this paper, probability dis- flow (DCF) analysis to determine the present value of future cash flows.
tributions have been assigned to different parameters which affect the The discount rate in DCF analysis takes into account not only just the time
NPV of the project; and Monte Carlo Simulation is applied which in- value of money, but also the risk or uncertainty of future cash flows; the
corporates uncertainties associated with different parameters to give greater the uncertainty of future cash flows, the higher the discount rate
NPV within a certain confidence interval. Also, the critical influencing (Kelly et al., 2015). Grimsey and Lewis (2004) have argued about the
parameter (parameter which affects output the most) is determined and need for incorporating uncertainty in the Discount rate. Since there are
appropriate risk mitigation efforts are discussed. multiple ways to calculate discount rate for a project, it has been taken as
an uncertain parameter in the paper. Due to unavailability of data, this
3. Methodology paper assumes discount rate to be the same as interest rate given by
Reserve Bank of India (RBI). For getting probability distribution, mean
A highway BOT project is influenced by a number of parameters; and and the standard deviation of interest rate for the past 10 years’ data is
uncertainties associated with those parameters are one of the major used; and the results conclude it to be normally distributed.
complications with the investors. In this paper, various risk categories
influencing a BOT highway project and the associated parameters are 3.1.3. Toll rate
first identified. Then, a corresponding probability distribution is assigned National Highways Authority of India (NHAI) has laid out a set of
to each parameter to forecast the actual value of parameter. Then data is fixed criteria for calculation of toll fee to be levied on customers. Formula
fed into a model developed in @Risk after which the results have been for determining the applicable rate of fee (GoI Report, 2009):
4
L. Kumar et al. Transport Policy 62 (2018) 2–11
Table 3
Discount rate
Inflation rate
WPIA WPIB
TollRate ¼ BaseRate⋅ 1 þ 0:4⋅
WPIB
Where, A and B are two consecutive years and WPI is wholesale price
index which is “the price of a representative basket of wholesale goods”.
The projected revenues and consequently the achievement of the designated rate of return would be adversely affected in case the inflation rate is lower than
It is a measure of inflation; the rate at which the general level of prices for
goods and services is rising, and, subsequently, purchasing power is
falling. The uncertainty associated with toll rate is directly proportional
to WPI which follows a normal distribution as seen from analysing the
Determination of project viability is predicated on the existing interest rate scenario prevailing in the country. A drastic increase in the interest
Risk Identification
first step towards developing model is dividing all the parameters into
Traffic revenue
Risk Category
Debt servicing
Cost overrun
Economical
5
L. Kumar et al. Transport Policy 62 (2018) 2–11
standard deviation. NPV is set as the desired risk output and the re- India’s (NHAI) website. The parameters which are not specific to one
lationships between different parameters and their effects on NPV project are obtained from different Government sites. There are a number
are examined. of methods to calculate discount rate but due to unavailability of data,
Costs include initial project cost for the construction period and op- discount rate is assumed to be same as the interest rate for past 10 years,
erations and maintenance cost for the subsequent years till the end of given by Reserve Bank of India (RBI). Also, to calculate the change in toll
concession period. Revenue starts only after construction period is fee every year, Wholesale Price Index values for the past ten years have
completed and it is calculated on the basis of AADT (Annual Average been taken from Ministry of Commerce and Industry, Government of
Daily Traffic) and toll rate taking into account the net increase in reve- India website.
nue. The base revenue is calculated as follows:
X 4.1. Project specific characteristics and data
BaseRevenue ¼ ðVehiclecount⋅TollrateÞ⋅365
The 30 projects considered in this paper are Build-Operate-Transfer
For subsequent years, revenue is calculated using net increase in projects and all are widening projects involving widening to 4 lanes or
revenue. Traffic is assumed to be linearly increasing throughout the 6 lanes. The considered case studies cover a wide range of projects with
concession period until it reaches the highway capacity. For the projects length of stretch varying from 19.5 to 291 km. Thus, the base toll for each
with multiple toll plazas, the final revenue is calculated as the sum total project is set differently on the basis of their length using Table 4 (GoI
of individual revenues. Formulas used are: Report, 2009). The toll revenue from only 13% of these projects are
collected by NHAI Agency; for other projects, concessionaire has the right
ΔR ¼ ðΔTr Þ⋅ð1 þ ΔTÞ Ir ¼ Inflation Rate
n ¼ Year b – Year a to collect tolls. Among these, around 17% of the projects are in con-
ΔTr ¼ ð1 þ 0:4⋅Ir Þ
C ¼ Concession Period struction phase and remaining are operational.
PCUb PCUa
ΔT ¼ Ri ¼ Revenue for year i The traffic flow (Annual Average Daily Traffic) for different type of
n⋅PCUa Ci ¼ Cost for year i vehicles for few years is also obtained from NHAI’s website and is con-
X
C
Ri Ci Dr ¼ Discount rate
NPV ¼
ΔT ¼ Growth in Traffic
verted to Passenger Car Unit (PCU) when used in the model. Information
i¼1 ð1 þ Dr Þi
ΔR ¼ Net Increase in Revenue factor about all 30 projects and few of the input parameters are mentioned
ΔTr ¼ Increase in Toll Rate factor in Table 5.
PCUb ¼ PCU value for year b
PCUa ¼ PCU value for year a
After the model is created in @Risk, static values for all parameters
are fed in the model, cash flows throughout the concession period are Table 4
Base rate of fee per km.
calculated, number of iterations are fixed at 1000 and MCS is done to
obtain the cumulative probability distribution graph and tornado chart Type of Vehicle Base rate of fee per km for the
for NPV. year 2006–2007 (in Rs.)
concession period) is obtained from National Highways Authority of (Source: GoI Report 2009)
6
L. Kumar et al. Transport Policy 62 (2018) 2–11
Table 5 Table 6
Details of 30 projects considered in this paper. Input Data for NH-7 Katdal to Armoor.
Project Information Input Data Parameter Mean Value Probability Distribution COV
S Project Name Nature of Project O&M Concession Concession Period 20 years Constant –
No. Project Cost (in Cost Period Construction Period 2 years Constant –
(widening) Crorea (in (Years) Number of lanes 8 Constant –
Rs) Crore Project Cost Rs 273.1 Crore Lognormal 1
Rs) O&M Cost per year Rs 3.2145 Crore Normal 0.1
Inflation (WPI) 4.88% Normal 0.4
1 AP Adloor 2 lane to 4 546.16 9.58 20
Discount Rate 7% Normal 0.2
Yellareddy to lane
Gundla
Pochampali
2 AP Hyderabad - 2 lane to 4/6 2269.00 49.98 15 Table 7
Vijaywada lane AADT and Toll data for NH-7 Katdal to Armoor.
3 AP Hyderabad - 2 lane to 4 388.00 2.01 23
Yadgiri lane Type of Vehicle 2011–2012 2012–2013 2013–2014
4 AP Katdal to 2 lane to 4 271.73 3.21 20
Count Toll Count Toll Count Toll
Armoor lane
Rate Rate Rate
5 AP MH-AP Border- 2 lane to 4 360.42 5.36 20
Islam Nagar lane Car / Jeep/Van or LMV 816 45 921 30 1199 30
6 AP Vijayawada - 4 lane to 6 675.38 12.00 15 Light Commercial Vehicle, 318 70 413 50 514 50
Chilakaluripet lane Light goods vehicle, Mini
7 GJ Vadodara to 4 lane to 6 660.00 15.68 15 bus
Bharuch lane Bus or Truck (2 Axles) 712 140 689 100 944 105
8 HR-Ambala- 2 lane to 4 298.00 5.50 20 Three Axle Commercial 725 210 314 110 1321 115
Chandigarh lane Vehicle
9 HR-PB-HP- 2 lane to 4 295.00 9.00 20 Heavy Construction 725 210 1263 160 611 170
Zirakpur- lane machinery (HCM), Earth
Parwanoo- moving equipment
Parwanoo bypass- (EME) or Multi axle
Pinjore-Kalka vehicle (MAV) 3–6 Axles
10 HR-PB-Panipat- 2/4 lane to 6 2747.50 140.84 15 Oversized vehicle (7 or 0.4 270 1 195 1 205
Jalandhar lane more axles)
11 KT-AP border- 2 lane to 4 402.87 4.72 20
Nandi lane
12 KT-Banglore 2/4 lane to 6 450.00 19.20 20
Elevated lane Table 8
13 KT-Banglore- 2/4 lane to 6 445.00 11.81 20 Cash Flows for the simulation (in Crore Rs).
Neelamangla lane
14 KT-Bijapur- 2 lane to 4 748.00 4.70 20 Year Cost Revenue Cash flows Present Value
Hungad lane 1 163.038 0.000 163.038 152.372
15 KT-Hyderabad- Upgradation 680.00 5.13 20 2 108.692 0.000 108.692 94.936
Banglore of 6 lane 3 3.215 12.314 9.099 7.428
16 KT-Neamangla- 2 lane to 4 441.00 2.95 25 4 3.215 14.430 11.215 8.556
Devihalli lane 5 3.215 16.909 13.695 9.764
17 KT-Tumkur- 4 lane to 6 1142.00 14.73 26 6 3.215 19.815 16.600 11.062
Chitradurga lane 7 3.215 23.220 20.005 12.458
18 MH-Kondhali- 2 lane to 4 212.00 13.21 17 8 3.215 27.210 23.995 13.966
Talegaon lane 9 3.215 31.885 28.671 15.595
19 MH- 2 lane to 4 835.00 7.51 18 10 3.215 37.365 34.150 17.360
MP&Maharashtra lane 11 3.215 43.785 40.571 19.275
Border Dhule 12 3.215 51.309 48.095 21.355
20 MH- 2 lane to 4 1170.52 9.16 27 13 3.215 60.126 56.911 23.616
MP&Maharastra lane 14 3.215 70.458 67.243 26.078
Border Nagpur 15 3.215 82.565 79.350 28.760
21 MH-Nagpur- 2 lane to 4 168.00 10.78 20 16 3.215 96.752 93.538 31.685
Kondhali lane 17 3.215 113.378 110.163 34.875
22 MH-Pimpalgaon- 2 lane to 4/6 944.00 5.10 20 18 3.215 132.860 129.646 38.358
Nashik-Gonde lane 19 3.215 155.691 152.476 42.161
23 MH-Pune Satara 2/4 lane to 6 1724.55 24.00 24 20 3.215 182.444 179.229 46.316
lane Total 329.591 1172.515 842.924 161.359 (NPV)
24 MH-Pune Solapur ( 2 lane to 4 1371.10 18.90 21
Package-I) lane
25 MH-Satara-Kagal 2 lane to 4 724.90 45.49 20
5. Analysis with example
lane
26 MH-Vadape-Gonde 2 lane to 4/6 579.00 8.21 20
lane Though 30 projects are considered in this research, a detailed analysis
27 PB-Kurali-Kiratpur 2 lane to 4 368.00 5.52 20 of a project titled “Andhra Pradesh - from Katdal to Armoor National
lane Highway-700 , is presented here for thorough understanding of the model.
28 RJ Bharatpur- 2 lane to 4 250.00 4.50 25
It provides detailed information on input data (Table 6 and Table 7). The
Mahua lane
29 RJ Jaipur-Gurgaon 4 lane to 6 1896.25 42.43 12 complete model outcome of 30 projects has been summarized in the
NH-8 lane next section.
30 WB Dhankuni- 4 lane to 6 1396.18 29.44 25 The project started on 4th May 2007 and the revenue collection began
Kharagpur lane
from 21st August 2009 and has collected Rs 64.85 Crore (with dis-
a
1 Crore ¼10 million. counting) as on 31st March 2015. The average traffic was 17,000 PCU/
day as on 30th November 2013. The project also involved construction of
7
L. Kumar et al. Transport Policy 62 (2018) 2–11
2 major bridges and has a tollable length of 31.77 km road. the profitability of a project and make the go-no-go decision. At α%
Traffic data and the corresponding toll rate for the project are out- confidence level, NPV-at-risk is the value at which α% of the possible
lined in Table 7. This data is used to calculate the growth in traffic be- values are smaller and 1-α% are larger. For example, in above case, NPV
tween the years 2011–2012 and 2013–2014 by converting traffic count at 95% confidence level is Rs 44.64 Crore ($0.45 Billion as in Fig. 3)
into PCU values. which means that there is a 95% chance that the concessionaire will
Since the construction period of the project is 2 years, costs include obtain a NPV greater than this. It also provides a Tornado chart which
initial project cost for the first 2 years and then a constant operations and ranks input by their effect on NPV through which effect of different pa-
maintenance cost for the subsequent years till the end of concession rameters on NPV can be examined. For example, discount rate is the
period. Revenue starts after 2 years and base revenue is calculated from critical influencing parameter for the above case study project (Fig. 4).
the above data using traffic count of the year 2011–2012. Thereafter,
revenue keeps increasing due to increase in traffic count and toll rate. 6. Results and findings
Also, PCU per lane is calculated for each year and as it reaches the
limiting value of 700 PCU per hour per lane capacity (i.e. 16,800 PCU per The above model is applied to all the 30 projects using Excel-VBA to
day) (Kadiyali, 2013), there is no further growth in traffic flow and net decrease the computational time. A summary of results obtained for all
increase in revenue is only due to increase in toll rate. For this project, 30 projects which includes static NPV, NPV-at-risk for 95% confidence
cash flows throughout the concession period and final NPV are shown interval, critical influencing parameter and probability of positive NPV
in Table 8. are provided in Table 9. From the table, it can be concluded that discount
This project was completed 100 days ahead of the scheduled rate has the maximum influence on NPV, as in 56% projects (i.e. 17 out of
completion date and has been under operation since 2009. Similar pro- 30 projects), discount rate is the critical influencing factor. This shows
cess of evaluation has been applied to other 29 projects. the importance of arriving at an accurate Discount Rate while doing
After the simulation is completed, @Risk provides a series of graphs financial feasibility studies for a PPP project by private investors. The
and charts which can be used to analyse the results. One of such graphs is percentage of each parameter in having the maximum influence on NPV
the Cumulative Probability Distribution curve of NPV (Fig. 3) through is shown in Fig. 5.
which the probability of occurrence of different values of NPV can be It has been observed that 6 out of 30 projects have zero probability of
computed. Based on the obtained probabilities, concessionaire can judge getting a positive NPV. Also, it is seen that project cost is the critical
8
L. Kumar et al. Transport Policy 62 (2018) 2–11
Table 9
Output Data of 30 Projects.
S No. Project Name Static NPV (in cr Rs) NPV-at-risk (in cr Influencing Probability of positive
Rs) Parameter NPV
9
L. Kumar et al. Transport Policy 62 (2018) 2–11
Table 10
Risk Mitigation and Allocation.
Table 11
Risk Mitigation strategies for Indian scenario.
1 Discount Yes Avoid using static discount rate throughout the concession period while doing the analysis
Rate Borrowing can be done by government which might reduce the interest rate as guarantee is more
2 Growth in Yes Yes Yes Clause to be included in contract to renegotiate toll rates at later point in time if the traffic count is below a
Traffic certain level
Guarantees by government in form of traffic floor and ceiling
3 Inflation Yes Yes This directly affects the toll rate so provisions should be given to ensure that the toll rate doesn’t get too high
Rate which discourages people from using the road
4 O&M Cost Yes Increase the concession period
5 Project Cost Yes Partial investment by government; for instance Hybrid Annuity Model in which government pays 40% of
project cost and concessionaire bears remaining 60%
10
L. Kumar et al. Transport Policy 62 (2018) 2–11
Atrill, P., McLaney, E., 2014. Accounting and Finance: An Introduction. Pearson Kokkaew, N., Chiara, N., 2013. A modelling Government revenue Guarantees in privately
Education, United Kingdom. built transportation projects: a risk adjusted approach. Transport 28 (2), 186–192.
Attarzadeh, M., Chua, D., Beer, M., 2011. Risk management of long term infrastructure Krishnamurthi, K., 2008. Business Management. S Global Vision Publishing House, India,
projects “PPP-BOT projects” by using uncertainty, probabilistic and stochastic p. 442.
methods and models. Vulnerability Uncertain. Risk 360–367. Nemuth, T., 2008. Practical Use of Monte Carlo Simulation for Risk Management within
Bagui, S., Ghosh, A., 2011. Traffic and revenue forecast at risk for a BOT road Project. the International Construction Industry. In: Proceedings of the 6th International
KSCE J. Civ. Eng. 16 (6), 905–912. Probabilistic Workshop, Darmstadt.
Delmon, J., 2011. Public-Private Partnership Projects in Infrastructure: An Essential Pathan, R., Pimplikar, S., 2013. Risk assessment of BOT road Projects. IOSR-JMCE 5 (6),
Guide for Policy Makers. Cambridge University Press, United Kingdom. 26–32.
Ernst, Young, 2012. Public Private Partnership the Next Continuum. Available from: < PPP India Database, 2014. March 31, Available from: <〈http://pppindiadatabase.com〉>.
〈http://www.ey.com/publication/vwluassets/ey-public-private-partnership-the- [18 December 2014].
next-continuum/$file/ey-public-private-partnership-the-next-continuum.pdf〉>. [20 Raghuram, G., 2003. The Case of the Vadodara–Halol Toll Road. India Infrastructure
September 2015]. Report. Indian Institute of Management, Ahmedabad (Available from: <http://
Government of India report (GoI), 2009. Report of the Committee of Secretaries on www.iitk.ac.in/3inetwork/html/reports/IIR- 2004/Chap%2011%202003.pdf>. )(20
Review of Toll Policy for National Highways. Available from: 〈www.infrastructure. September 2015).
gov.in〉. [15 October 2014]. Shetty, R., 2012. Urban Infrastructure Development in India - An Overview. Electrical and
Grimsey, D., Lewis, M.K., 2004. Discount debates: rates, risk, uncertainty and value for Electronics Engineering, Bangkok, Thailand, pp. 226–229 (ICCEEE’2012:
money in PPPs. Public Infrastruct. Bull. 1 (3) (Article # 2). International Conference on Civil).
IFAC report, 2012. Project and Investment Appraisal for Sustainable Value Creation. Wibowo, A., Permana, A., Kochend€ orfer, B., Kiong, R., Jacob, D., Neunzehn, D., 2012.
Available from: <〈http://www.ifac.org/system/files/publications/files/PAIB-IGPG- Modeling contingent liabilities arising from government guarantees in Indonesian
ED-Project-and-Investment-Appraisal-for-Sustainable-Value-Creation_0.pdf〉>. [20 BOT/PPP toll Roads. J. Constr. Eng. Manag. 138 (12), 1403–1410.
September 2015]. World Bank report, 2008. PPP in Infrastructure Resource Center for Contracts, Laws and
Iyer, K., Sagheer, M., 2011. A real options based traffic risk mitigation model for build- Regulations (PPPIRC). Available from: 〈http://ppp.worldbank.org/public-private-
operate-transfer highway projects in India. Constr. Manag. Econ. 29 (8), 771–779. partnership/sites/ppp.worldbank.org/files/documents/roadriskmatrix_1.pdf〉. [27
Kadiyali, L.R., 2013. Traffic Engineering and Transport Planning. Khanna Publishers, February 2016].
India. Ye, S., Tiong, R., 2000. NPV-AT-RISK method in infrastructure project investment
Ke, Y., Wang, S., Chan, A.P.C., Cheung, E., 2011. Understanding the risks in China’s PPP evaluation. J. Constr. Eng. Manag. 126 (3), 227–233.
projects: ranking of their probability and consequence. Eng. Constr. Archit. Manag. Ye, T., Yun P., Bo C., 2013. Ventures of highway BOT projects based on the combination
18 (5), 481–496. of fuzzy theory and AHP. ICTE 2013: proceedings of the 4th International Conference
Kelly, J., Male, S., Graham, D., 2015. Value Management of Construction Projects. John on Transportation Engineering, pp. 1383–1387.
Wiley and Sons, United Kingdom. Zatar, M., 2014. Pitfalls of Public Private Partnership in Toll Roads, Master’s Thesis. The
University of Texas at Arlington.
11