Ceiling M&E Inspection (Common Area)

L13 L12 L11 L10 L9 L8 L7 L6 L5 L4 L3 L2 L1


Electrical
Lighting point 
EL Light point
Keluar Sign point
Motion sensor point
Megger test  & Continuity test

ELV
PA speaker point
CCTV point
Card access wiring
Megger test

ACMV
FCU Installation
Supply air duct
Fresh air duct
Toilet exhaust duct
Chilled water pipe 
Chilled water pipe control valve 
Pressure test
FCU drain pipe installation
Drain pipe leak test
Drain pan for FCU valves
Volume control damper (FAD)
BMS wiring & termination
Motorize damper point
Megger test

Fire Protection
Sprinkler pipe
Pressure test
Flow switch and butterfly valve wiring & termination
Strobe light point
Smoke detector
Megger test

Plumbing
Cold water pipe
Pressure test
Soil & waste pipe
Leak test