CBI system is Computer-based interlocking system which detects signalling objects and controls wayside
objects via an Object controller system (OCS) and control block operation through interlocking to
interlocking (ITI) to CBI stations and relay interface to Non-CBI stations.
Onboard system receives the data from track using pick-up coil and electrical map ID from Balise.
CBI controls wayside objects via OCS while block operation through interlocking to interlocking
Onboard system calculate speed in real time by pick up coil (speed sensor) and electrical map id
Excel counter
Traffic control system or Local control console is EBIScreen which provide the layout of wayside objects
and handle the operators command. LCC is connected to CIS via Ethernet network.
CIS performs interlocking function, receive and evaluate commands from operator via LCC send orders
to OCS, receive status information from OCS and send indication to LCC.
Ruggedized Vital Platform Unit (VPU_R) is used in this project which is fully electronic and computer
based system which perform interlocking function with high calculation capacity. VPU_R consist of
redundant of two VCS_R (Ruggedized Vital computer system) installed with same interlocking site
software (ILS).
OCS950 System
OCS control and monitors the states of wayside objects of both fail safe and non-fail safe nature. OCS is
connected to CIS via Ethernet cable. It receive and execute the order from CIS, monitor objects status
and send status information back to CIS.
OCS consist of mainly Communication controller unit (CCU) and Object controller (OC). CCU controls
communication between IPU and OCs. OCs receive order from CIS via CCU and execute them and also
monitor the wayside objects and send status back to CIS.
Track Circuit
The 25 Hz phase sensitive track circuit is adopted in station to detect train occupation.
AC track circuit with 25Hz frequency has been used for yard operation
Coded track circuit XPW-2000A used for block operation
Cab Signalling
The locomotive information and the line data are pre-stored in the onboard computer; the
onboard equipment will measure and calculate the train speed through the speed sensors in
real time, verify the absolute train position through the wayside Balise, and finally calculate the
safe braking curve by calling the pre-stored line database to supervise the safe running of the
train.
The BTM system receives the fixed messages from the wayside Passive Balise through the Balise
antenna and transmitted to the LKJ system.
The objective of correspondence is to ensure that the controls and indications of the Local
Control Workstation (LCW) with the wayside equipment without train movement. These tests
will be done under the supervision of the customer
We verify status of each objects by checking its variable using maintenance terminals in all
possible conditions.
Manila MRT-L3 (CITYflo 350 (CBI): STO Metro system, Non CBTC, Fixed Block )
CBI system consists of CIS, which includes EBILock950, a computer system which is the brain of system
and OCS950, which send command and receive the status of wayside objects
Radio Block Center (RBC). This function handles the position reports from vehicle and send
movement authority for locked train routes.
This test is part of SAT, and it’s performed to check the Data Test Functionality for depot
interoperability.
This test will verify that RATP properly processes the wayside conflict points to VATC. It will also verify
and validate the design Map Data.
The purpose of this report is to document the completion of System Acceptance Test (SAT) for System
Integration Field Test Vehicle Automatic Train Control System Map Verification
Automatic train control (ATC) radio system acceptance field test report
This test has been done to all locations to verify that communication is provided by the ATC Radio
System in all required locations. This pure also includes the RAP radio checking procedure for detecting
failed radio units.
The purpose of this test is to verify that the communications link between the wayside and train-borne
equipment provides a level of successful message exchange (Packet Success) to support automatic train
operation.
This procedure also demonstrates proper functionality and configuration of the Networked Radio Data
Requests for inspection or Testing (RFI) and outstanding item list (O.I.L) report of the project.
RFI supposed to be generated by site team for every location before to visit site. Later when work is
completed RFI must be closed.
Then at each specific site there are multiple test or tasks are ongoing. For each task a separate O.I.L list
was generated. After completion of work O.I.L must be closed.
Failure reporting and corrective action system (FRACAS) report
The purpose of this report is to demonstrate results of the Data Test for ATC Regions and to verify Line
depot interoperability– System Integration Field Test.