Knauf Wall Liner

Installation Procedures
Knauf Wall Linings are designed to be simple and fast to install. Knauf Technical Services
are on hand should you have any questions or unusual situations to deal with.

General
Knauf Wall Liner must be installed in accordance Offer up the Knauf ‘C’ Channels to engage with
with Knauf ’s recommendations and the the Knauf Universal Brackets and with the floor
recommendations of BS 8212: 1995 and BS 8000: and head tracks. Extend the length of Knauf ‘C’
Part 8: 1994. Channels where necessary by using Knauf ‘C’
Channel Connectors. Adjust the studs for position
Preparation and alignment.
Mark guidelines on the floor and soffit to establish
the positions of floor and head tracks relative to the Secure the Knauf ‘C’ Channels to the Knauf
stand-off distance required. Universal Brackets using two Knauf Wafer Head
Screws per side, per bracket. Depending on the
Mark vertical guidelines on the background stand-off distance, bend back the legs of the
to establish the Knauf ‘C’ Channel positions at crimped universal brackets so as not to obstruct the
maximum 600mm centres for 12.5mm Knauf fixing of the board.
Plasterboard.
Fix Knauf Angle Sections at external corners and
Depending on the required storey height, mark reveals, where appropriate.
the wall with the location of intermediate Knauf
Universal Brackets in line with the channel guidelines Insulation
and maximum 900mm vertical centres. Install insulation quilt where required, between and
Position service runs and outlets. behind the vertical Knauf ‘C’ Channels for continuity
and to prevent slumping.
Framing 1,2,3
Knauf ‘U’ Channel – Perimeter Support channels Boarding 4
should be used for the head and base of the lining. The plasterboard lining is fixed by screwing into the
Bed each section on two continuous beads of metal framework, using Knauf Screws at 300mm
Knauf Sealant along the guidelines using fixings centres. Reduce to 200mm at corners. Fixings should
appropriate for the background. Fix at nominal be to all horizontal and vertical members.
600mm centres.

Fix the intermediate Knauf Universal Brackets to the


background, at the marked positions, using fixings
appropriate for the background.

1. 2. 3. 4.

Fixing Knauf ‘U’ Channel – Marking position for the Knauf Fixing Knauf ‘C’ Channel to the Fixing Knauf Plasterboard to the
Perimeter Support to the soffit. Universal Bracket. Knauf Universal Bracket. Knauf ‘C’ Channel.