I.S.

3217:2013+A1:2017

Annex C2
(normative)

Emergency Lighting System Certificate of Design


No further reproduction or distribution permitted. Printed / viewed by:bookings@ipsdb.com @ 19/02/2021
Copyrighted material licensed to SAI Global for IPS Integrated Project Services (Ireland) Limited.

This certificate shall be printed on paper clearly showing the design company's details

Certificate Number:……………………………..
18276-CTD-DK0-L9-2878

New System:  Modification, Extension Or Alteration To Existing System:(tick appropriate box):


WuXi Biologics Ireland Ltd Biopharmaceutical Manufacturing Facility
Building Name Owner and/or Occupier…………………………………………………………………………………………….….
Emergency Lighting - Whole site, WuXi Biologics Ireland Ltd
Description of Works………………………………………………………………………………………………………………………..….
IDA Science & Technology Park, Mullagharlin, Dundalk, Co. Louth
Address of Building........................………………………………................................................……………………………...................
Designer’s Name......................................…………………………….…...............................................……………………………….......
Integrated Project Services (IPS) Ltd

1Design Drawing(s)…………………………………………………………………………………………………………………………….
Refer to Appendix 1

Justifiable Variations/Items/Areas Excluded: [tick appropriate box(s)]

Justifiable Variations to 2I.S. 3217:2013+A1:2017 and/or the Specification: No Yes  (listed as


attached)

Items/Areas Excluded From This Certificate: No  Yes  (listed as attached)

I/We hereby certify that, to the best of my/our ability, knowledge and belief, the Emergency Lighting
System at the above building as set out on the listed drawings has been designed by me/us in
accordance with the requirements and recommendations of 2I.S. 3217:2013+A1:2017 except as stated
on the attached justifiable variations (if any).

I/We confirm our competence to carry out this design.

I/We further confirm that, where the works are limited to modification, extension or alteration to an
existing system, that I/we have given due consideration to the impact on the original system and I/we
have taken adequate precautions to the best of my/our ability, knowledge and belief to ensure that
there is no adverse impact on either the original system or the modifications.
IPS Remit: Emergency Lighting Basic Design & Detail Design to 60% of IFC Scope
Comment…………………………………………………………………………………………………………………………………………..

…………………………………………………………………………………………………………………………………………………………

Details and signature of authorised person responsible for the design of the system:
Peter Higgins Director
Name..................………………………………..……..…. Position ....................………………………………………………………

Signed.……………………………………………………… 24 02 2021
Date:……./……./…….
Integrated Project Services (IPS) Ltd
For and on behalf of (company)………………………………………………..……………………………………………………….

1 !Design" Drawings
2 ! I.S. 3217:2013+A1:2017 "

63
Appendix 1

Document: Emergency Lighting System Certificate of Design


Certificate Reference: 18276-CTD-DK0-L9-2878
Reference: List of Applicable Drawings
Discipline

Document Number Drawing / Document Title REV. Date Issued

ELECTRICAL SERVICES - ADMINISTRATION BUILDING (DK1) L1 - LIGHTING


18276-EDR-DK1-L1-2201 E D 20/08/2019 Design
DRAWING

ELECTRICAL SERVICES - ADMINISTRATION BUILDING (DK1) L2 - LIGHTING


18276-EDR-DK1-L2-2202 E D 20/08/2019 Design
DRAWING

ELECTRICAL SERVICES - ADMINISTRATION BUILDING (DK1) L3 - LIGHTING


18276-EDR-DK1-L3-2203 E D 20/08/2019 Design
DRAWING
ELECTRICAL SERVICES - ADMINISTRATION BUILDING (DK1) L4 - LIGHTING
18276-EDR-DK1-L4-2204 E D 20/08/2019 Design
DRAWING
ELECTRICAL SERVICES - MANUFACTURING BUILDING (DK2) L1 -
18276-EDR-DK2-L1-2208 E C 06/09/2019 Design
LIGHTING DRAWING
ELECTRICAL SERVICES - MANUFACTURING BUILDING (DK2) L1.5 -
18276-EDR-DK2-L1.5-2209 E D 30/09/2019 Design
LIGHTING DRAWING
ELECTRICAL SERVICES - MANUFACTURING BUILDING (DK2) L2 -
18276-EDR-DK2-L2-2210 E C 06/09/2019 Design
LIGHTING DRAWING

ELECTRICAL SERVICES - MANUFACTURING BUILDING (DK2) L2.5 -


18276-EDR-DK2-L2.5-2211 E D 30/09/2019 Design
LIGHTING DRAWING

ELECTRICAL SERVICES - MANUFACTURING BUILDING (DK2) L3 -


18276-EDR-DK2-L3-2212 E C 06/09/2019 Design
LIGHTING DRAWING

18276-EDR-DK3-L1-2216 E Lighting Plan Warehouse Building (DK3) L1 C 12/08/2019 Design

18276-EDR-DK3-L2-2217 E Lighting Plan Warehouse Building (DK3) L2 C 12/08/2019 Tender

18276-EDR-DK3-L1.5-2218 E Lighting Plan Warehouse (DK3) L1.5 B 12/08/2019 Design

18276-EDR-DK4-L1-2221 E ELECTRICAL SERVICES - LIGHTING PLAN CUB DK4 LEVEL 1 C 13/08/2019 Design

18276-EDR-DK4-L2-2222 E ELECTRICAL SERVICES - LIGHTING PLAN CUB DK4 LEVEL 2 C 13/08/2019 Design

18276-EDR-DK4-L3-2223 E ELECTRICAL SERVICES - LIGHTING PLAN CUB DK4 LEVEL 3 B 13/08/2019 Design

18276-EDR-DK2-L3-2526 E DK2 MSAT LABS GENERAL & EMERGENCY LIGHTING C 24/04/2020 MSAT 90%

18276-EDR-DK7-L1-2591 E ELECTRICAL SERVICES (DK7) - LIGHTING & POWER LAYOUT A 06/09/2019 Review

18276-EDR-DK8-L1-2592 E ELECTRICAL SERVICES (DK8) - LIGHTING & POWER LAYOUT A 06/09/2019 Review

18276-EDR-DK9-L1-2593 E ELECTRICAL SERVICES (DK9) - LIGHTING & POWER LAYOUT A 06/09/2019 Review

18276-EDR-DK12-L1-2594 E ELECTRICAL SERVICES (DK12) - LIGHTING & POWER LAYOUT A 06/09/2019 Review