Professional Documents
Culture Documents
PRO 163 13-14 Dinesan
PRO 163 13-14 Dinesan
PRO 163 13-14 Dinesan
2)
The Assistant Engineer
Electrical Section
Thevakkal
=========================================================
No.CGRF-CR/Comp. 163 /2013-14 Date: 13/5/2014
ORDER
Subsequently, statement of facts was called for and the same was
submitted by the respondent on 16/01/2014. The Forum accorded an
opportunity to hear from the petitioner and respondent on 27/03/2014 and
both the parties were present for the same.
2
The petitioner stated that his house with consumer number 12454 has
been let out for rent for the last few years. On finding the energy meter to be
faulty petitioner had approached the respondents many times to get the same
replaced. But the meter was changed only in 05/2013 after 2years of fault.
But now the respondent has issued a bill amounting to Rs.1,715/- claiming
the same to be short assessment for the period from 12/10 to 03/13.
Petitioner submitted that during the mentioned period the house was
occupied by a family consisting of husband and wife only. From 01/04/2013
onwards, the building has been let out to another family consisting of four
members. Now the respondent has done a short assessment for a period
occupied by the previous tenants based on the comparatively higher
consumption of the new tenants. Petitioner termed the said action as
unjustifiable and malicious and prayed to cancel the same.
charges and water charges. Hence time limitation as per section 56(2) of the
Act 2003 is not applicable in the present case. The respondent submitted that
the assessment made is in order and prayed to sustain the same.
Having examined the petition in detail, and the statement of facts of the
respondent, considering all the facts and circumstances in detail, and perusing
all the documents of both sides, the Forum comes to the following observations,
conclusions and decisions thereof.
1) The Supply Code, 2005 allows the respondent to charge the consumer
with the average of previous six months for the faulty period with the
condition that the meter should be replaced within one month.
2) The Supply Code does not mention anything about extending of this
practice of charging average for the entire faulty period based on the
reason of non availability of meter.
3) But the respondent has extended this method of charging for average for
the entire faulty period of 07/11 to 03/13 (i.e. for 20 months).
4) Consumer has not disputed the bills issued during the above period.
5) The respondent re-decided to charge the consumer for 176 units for a
period 12/10 to 03/13 (i.e. for 29 months).
5
The respondent rectified this condition by replacing the faulty meter with a
good one and the petitioner has accepted the same.
The respondent had taken a clear action as per the Supply Code 2005
immediately after noticing the faulty condition of the meter. The respondent
decided to charge the petitioner for 124 units during the period. The respondent
noticed this action as wrong only after a long period of more than 2 years, that
too based on presumption. This time they decided to charge this consumer for
176 units for nearly 29 months. A presumption need not be correct without
supporting documents to prove it.
Even though the RAO made an assessment in favor of the respondent, it has
no legal standing as per the act. This assessment should have been made by the
respondent when the fault was detected so that the dispute could have been
solved then and there. Here the respondents not only resorted to a practice not
mentioned in any act or rule but also reassessed the consumer by mere
presumption. Had the respondents adopted the average assessment of 176 units
bimonthly, in the beginning itself, the petitioner could have self assessed about
the consumption and challenged, if the said average does not commensurate
with the consumption. Re-assessing an action already taken is not justifiable and
sustainable.
Further, section 56(2) of the Indian Electricity Act 2003, states that ‘no sum
due from any consumer shall be recovered after a period of 2 years unless such
sum has been shown continuously as recoverable as arrear of charges’. Even if
it is admitted that amounts furnished by the respondent in the revised
6
assessment reflect the actual consumption during the period from 12/10 to 03/13
such sums ‘became due’ during the corresponding billing cycles itself when the
consumption occurred. The respondent was supposed to issue such bills during
the corresponding billing cycles and in case of any missing in such billing, the
same should have been made up within two years from the points when the
amounts had become actually due. The Forum cannot accept respondent’s
argument that amounts become due only when the bill is issued since the same
goes against the principles of natural justice. Any consumer has the right to get
bill for his consumption within a reasonable timeframe and that right is upheld
by section 56(2) of the Electricity Act 2003. Section 18(8) of the Supply code
2005 also upholds this point. According to the same the licensee shall not
recover any arrears after a period of two years from the date when such sum
became first due unless such sum has been shown continuously in the bill as
recoverable as arrear of charges of electricity supplied. Even if the reassessment
done by the respondent for the period from 12/10 to 03/13 is treated to be
genuine arrears, the assessment, as such, cannot be recovered after a span of
two years and hence the issued short assessment bill is invalid.
Forum is of the opinion that the consumer cannot be burdened for the non
action of the respondent in time.
DECISION:
The petitioner is at liberty to file appeal before the Electricity Ombudsman, within 30
days of receipt of this order, if not satisfied with this decision.
Sd/-
1) Sri. Lorance. K.M
(CHAIRPERSON)
Sd/-
2) Sri. Silvester Peter P
2nd member
Sd/-
3) Sri. Jefrin Manuel
3rd member
Copy Submitted to: The Chief Engineer, Distribution Central, KSEB, Gandhi
Square, DH Road, Kochi -16.
Copy to: - (1) The Deputy Chief Engineer, Electrical Circle, KSEB
Perumbavoor
(2) The Executive Engineer, Electrical Division, KSEB,
Aluva
(3) The Asst. Exe. Engineer, ESD, K.S.E.B, Kalamaserry
(4) The Asst. Engineer, Ele. Section, Thevakkal
8