Professional Documents
Culture Documents
Hamidreza REZAEI
Hamidreza REZAEI
Hamidreza REZAEI
1
2
Context and ProblemStatement
PRODUCTION MANAGEMENT
Strategical
Tactical
3 Decision levels
Operationnal
Giard, V. (2003). Gestion de la production et des
flux, Economica, Coll.Gestion, 3eme édition.
3
Context and ProblemStatement
Strategical Strategical
Horizon:
• Long Term (+ 18 month)
Type of decision:
• Opening or closing site Tactical
• Localization of plants or warehouses
• Hiring / Dismissal
• Purchase machine…
4
Context and ProblemStatement
Tactical
Strategical
Horizon:
• Midterm(from 1 to 18 month)
Operationnal
Provide a framewok to the
operationnal level.
5
Context and ProblemStatement
Operationnal Strategical
Horizon:
• Short term (daily)
Type of decision:
Tactical
• Scheduling
• Inventory management…
Operationnal
6
Context and ProblemStatement
Strategical
Strategical
Planification
Tactical
Tactical
Operationnal Operationnal
7
Context and ProblemStatement
Strategical
Horizon:
• Long Term (+ 18 month)
Strategical
Objective:
• Validates the strategy that will deploy
the company in terms of growth and
investment.
Tactical
Methods used :
• Balance between workload / capacity on
a long-term in order to validate the
Operationnal
methods used (open / closed sites etc..)
8
Context and ProblemStatement
Tactical
Horizon:
• MidTerm (From 1 to 18 month)
Goal:
Strategical
• Determines the quantities to be
produced on a medium term horizon in
order to find a balance between the rate
of customer satisfaction and the various
Tactical
logistics costs:
• Production costs
• Holding costs Operationnal
• Setup costs
• Shortage costs …
9
Context and ProblemStatement
Opérationnelle
Horizon:
• Short term (Daily, Weekly…) Strategical
Goal:
• Schedule the production over a
short term horizon: Tactical
• determines the starting times
of tasks on different resources
to ensure the production of Operationnal
quantities of items defined the
tactical plans.
10
Context and ProblemStatement
Strategical
planification
Tactical
planification
Operationnal
planification RISKS
11
Context and ProblemStatement
MRP2
Approach
Vollmann, T., Berry, D. et Whybark (1997).
Manufacturing planning and control systems,
4th ed., New York et al.
12
Context and ProblemStatement
The MRP2 Approach
(Manufacturing resources Planning)
Kind of approach
Plan level n
• Hierarchical
• Structure in several plans.
• A goal,
• An horizon,
• A level of detail,
How it works :
Plan level n-1
• Each plan gives a framework to the next one (which is
immediately below it in the hierarchy)
13
Context and ProblemStatement
14
Context and ProblemStatement
S&OP Sales and Operation
• Tries to find a compromise Planning (S&OP)
between the objectives of sales
and production capacity thanks
to an analysis of the adequacy
load / capacity
Master Production
Horizon Schedule (MPS)
• From 12 to 18 month
Elaboration
Material Requierement
• Can be elaborated thanks
graphic tools or MILP Planning (MRP)
15
Context and ProblemStatement
Elaboration
• With a MILP Material Requierement
• With Algorithmes Planning (MRP)
16
Context and ProblemStatement
MRP Sales and Operation
• Determines the amounts, dates Planning (S&OP)
of manufacture or purchase of
components necessary to
produce in time the quantities
provided in the MPS.
Master Production
Horizon Schedule (MPS)
• From 1 to 6 month
Elaboration
• With a MILP Material Requierement
• With Algorithmes Planning (MRP)
17
Context and ProblemStatement
18
Context and ProblemStatement
Production sequencing
20
MRP Grouping Rules
•Lot for lot : batches match the manufacturing orders
• Lot for lot, with minimum size.
• EOQ : batch size is the economic order quantity
• Fixed lot, or multiple of fixed lots.
• Part period cover : the batch size covers the demand for a given number of periods
21
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 30 Gross requirements
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 40 Gross requirements
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 22
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10 10 10 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 30 Gross requirements
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 40 Gross requirements
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 23
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10 10 10 10
Net requirements 20
30-0-10
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 30 Gross requirements
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 40 Gross requirements
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 24
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10 10 10 10
Net requirements 20
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 30 Gross requirements
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 40 Gross requirements
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 25
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10 10 10 10
Net requirements 20
Manufacturing order (end) 20
Manufacturing order (begin)
Lot size: 30 Gross requirements
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin)
Lot size: 40 Gross requirements
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 26
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Product A
Inventory 10 10 10 10 0
0+10+20-30 0
Net requirements 20
Manufacturing order (end) 20
Manufacturing order (begin) 20
Lot size: 30 Gross requirements 40
Delay: 2 weeks Expected delivery 15
Product B
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 30
Lot size: 40 Gross requirements 20
Delay 1 week Expected delivery
Product C
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 27
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Product A
Inventory 10 10 10 10 0 0
Net requirements 20
Manufacturing order (end) 20
Manufacturing order (begin) 20
Lot size: 30 Gross requirements 40
Delay: 2 weeks Expected delivery 15
Product B
Product B
Link: 2 Inventory 10
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 30
Lot size: 40 Gross requirements 20
Delay 1 week Expected delivery
Product C
Product C
Link: 1 Inventory 5
Net requirements
Manufacturing order (end)
Manufacturing order (begin) 28
Example of MRP A B C
Periods 0 1 2 3 4 5
Lot for lot Gross requirements 30
Delay: 2 weeks Expected delivery
Product A
Inventory 10 10 10 10 0 0
Net requirements 20
Manufacturing order (end) 20
Manufacturing order (begin) 20
Lot size: 30 Gross requirements 40
Delay: 2 weeks Expected delivery 15
Product B
Link: 2 Inventory 10 10 15
Net requirements 15
Manufacturing order (end) 30
Manufacturing order (begin) 30
Lot size: 40 Gross requirements 20
Delay 1 week Expected delivery
Product C
Link: 1 Inventory 5 5 25
Net requirements 15
Manufacturing order (end) 40
Manufacturing order (begin) 40 29
Master Production Schedule
Item
20 20 20 50 20 50 20
Sécu : O
Lmul : 10 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20 20 50 20 50 20
Lot : BQ LT 20 20 50 20 50 20
Cycle : 2j 20 20 50 20 50 20
50 50 50 50 50 10 10 10 10 10 10 10 10 10 10 30 30 30 30 30
Sécu : O 120
Lmul : 50 200 270 220 170 120 70 60 50 40 30 20 10 0 40 30 20 40 10 30 0 20
10 10 20 30
Lot : BQ 50 50 50 50
Cycle : 6j 50 50 50 50
FORECAST
30
Cycle
Cycle 50
50
2,24
2,24
2,4 0,8
Décalage des besoins 2,24
dépendants !!! 2,4 0,8
2,24
3,2 3,2
3.2
3,2
3,2 3,2
3,2
2,24 8,64 15,04 2,24
2,56
2,56
6,4
2,56
6,4
2,56
1,6 4,8 1,6 4,8
1,6 4,8
1,6 4,8 1,6 4,8
1,6 4,8
2,56 15,36 23,36 7,36
2,4 7,2 7,2 7,2 2,4 7,2 7,2 7,2
2,4 7,2 7,2 7,2
2,4 7,2 7,2 7,2 2,4 7,2 7,2 7,2
2,4 7,2 7,2 7,2
0
9,6 9,6
31,2 48
31,2 2438,4
33