Professional Documents
Culture Documents
Civl3141draftreport 1st Part of Submission
Civl3141draftreport 1st Part of Submission
Civl3141draftreport 1st Part of Submission
Table of Figures
Figure 1 Catchment Map.......................................................................................................................3
Table of Tables
Table 1 Area range and number of squares...........................................................................................3
Task 1 – Critical review
The Probable Maximum Flood Estimates for the Lake Baroon Catchment (Gibbes, 2021) report
summarises the development of probable maximum precipitation (PMP) and probable maximum
flood (PMF) estimates for the Lake Baroon catchment, with the aim of comparing the estimated PMF
to the maximum discharge discussed in the emergency management procedures for Lake Baroon
(Seqwater 2020).
The purpose of this review to critically examine the content and methods of the report to identify its
strengths and weaknesses and provide recommendations for how it might be improved.
Rational values were chosen for the various terms of the GSDM and GTSMR and the methodology is
well explained. However, the process for calculating the EPW catchment, DAF, and TAF values could be
explained more clearly, perhaps with figures. Also, the report states that initial rainfall depths (D R)
corresponding to each duration were calculated from figure 4 of the GSDM. But the values for D R in
table 1 of the report do not seem to correspond with chart found in figure 4 of the GSDM, for the
catchment area of 67 km2. The DR values in table 1 should be checked for correctness. Or, if D R are
not obtained directly from figure 4, this should be explained more clearly.
The final GTSMR PMP depths were not derived correctly according to the conventions outlined in
section 2.5 of the GTSMR guidebook. The guidebook states that values of the enveloping curve
should always be greater than or equal to the corresponding PMP value – this is not the case for
several of the adjusted PMP values in table 1 of the report. Furthermore, preliminary GSDM PMP
values should not be altered for the purpose of fitting an enveloping curve. They should, however,
be rounded to the nearest 10mm according to section 4.5 of the GSDM.
In term of formatting, some minor issues need to be addressed. Sections of the report are separated
well with headings. However, the report’s formatting may be improved by breaking up the Results
and discussion section into multiple subsections and ensuring references are formatted consistently.
The list of symbols, acronyms and abbreviations section is a helpful tool for the reader to understand
the technical content of the report. However, the list appears to be incomplete – many symbols,
acronyms and abbreviations are not included in the list but are instead defined ad hoc in the body of
the report. For consistency, the list should either be removed or expanded to include these other
terms such as GSDM, EAF, MAF and D R, among others. Furthermore, the list’s inclusion of basic units
(such as litres and millimetres) is unnecessary as knowledge of these units is trivial and other units
found in the report are not included in the list. The term water year is included in the list despite not
being used in the body of the report. So, it is recommended that it be removed from the list.
In summary, the report is generally well constructed, with some capacity for improvement.
Task 2 – Catchment characterisation
a) To determine the catchment area, a catchment map was created using QTOPO. A scale of
1:50,000 was used over lake Baroon, with the latitude ranging from 26°40’S to 26°46’S and
the longitude ranging from 152°50’E to 152°56’E. Once the topological map was obtained,
the outlet was defined by Baroon Pocket Dam and the contours were followed to create the
catchment map, which can be seen in figure 1. The scale on the right side of the map
indicated the length of each square is 2km long, meaning each square has an area of 4km 2.
b) To determine the catchment area, the number of squares were estimated. Each square was
determined to be either fully enclosed by the boundary, mostly in the area, half in the area,
or mostly not in the area. Due to the squares being visually examined, a range was used for
each category. The range for each category and the number of squares in each category can
be seen in table 1.
Table 1 Area range and number of squares
c)
The area of the catchment is 67.6km 2, and the length of the flow path has been found to be 25km.
The equal area slope (S¿¿ e )¿ can be found by the formula Se =h /L , where h is distance between
highest and lowest point and L is the length of the mainstream flow path. By using h=265 m and
L=25 km , equal area slope is 10.6 m/km , and we can divide by 10 to get the percentage.
0.38
t c =0.76 A
0.38
t c =0.76 ×67.6
t c =3.77 hours
2. Bransby-Williams formula
58 L
t c= 0.1 0.2
A × Se
where t c = The time of concentration (min), L = Length of flow path from catchment divide to outlet
(km), A = Catchment area (ha) and Se = Equal-area slope of stream flow path (%)
58× 25
t c=
67 600.1 × 1.060.2
( )
0.8
L
t c =0.00025
√S
Where t c = The time of concentration (hr), L = Length of the catchment along the longest flow path
(m) and S = Overall slope of the catchment (mm-1)
( )
0.8
25000
t c =0.00025
√ 0.0106
t c =5.08 hours