Erection of Tower Structure-132KV-TL: Method Statement

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 14

  Method Statement

ERECTION OF TOWER
This Method Statement describes the specific safe working methods which will be used to carry out the
described work. It gives details of work procedure with control measures to counter health and safety issues
related to this work. The listed content of this Method Statement cannot be changed/ modified subjected to
job scope/customer specifications without the prior permission of LBU /LPG Manager, Erection Head, Safety co
ordinator and Project Manager. But task specific method statement once finalized & approved, that should not
be modified during work execution.

Project Name 400/132 KV SUB-STATION PROJECT AT NTPC SOLAPUR

132 KV Transmission Line from NTPC Solapur to Ujani.


Site /Location

Planned schedule of Activity 02/05/2014 to 31/12/2014


Method Statement No. ABB/TOWER STRUCTURE/ TL/02 Rev. No. 2( Proposed Dated 25.10.14 )

Risk Assessment Ref. No. NABB/PS//OHS/JSEA/003 Rev. No.


002 dated 22.10.2014
Title :- Erection of Tower Structure-132KV-TL
Scope of work: - Supply,Civil,Erection, Testing and Commissioning of 132 KV Transmission Line from NTPC
SOLAPUR to Ujjani .
Drawing References:- Refer Attached List(Drg. No)
Technical Specification Technical Spec. VI[Part-1&2] & Part-V
Document References:-

Certification of Plant etc. Hydra Regd. No.CG07NA3635 [M/s Unitech power Transmission Ltd]
Date Of Testing 01/04/2014 Valid Till date

Detail of Sub contractors M/S Unitech Power Transmission Ltd. Office Address- 136,Udyog Vihar, Phase-1,
Involved :- Gurgaon-122016, Haryana. Tel:0124-4571000/4571001
Mr. Rajesh Pillai-Project Manager
Mr.Anil Adappa/Mr. Kumar

Method Statement Prepared By : Signature Date


C P Singh (Site Manager)

Method Statement Reviewed By:-


Mr. ANUJ MAHAJAN (Project Manager)
Mr. ARJUN SINGH ( Chief Project Manager)
Method Statement Approved By:-

Page 1
  Method Statement

1.0 Introduction (Describe purpose of the work, Give details of type and scope of work being carried out, work
parties involved (include working hours). Client requirements/ specifications, Local legislation Enforcement
authorities requirements i.e. The Police, Civil Defence, Environment Agency* (EIA) to be considered with
reference to scope of work.

Purpose of the work: Construction of 132kV Transmission Line(From NTPC Solapur to Ujani)

Scope of Work:
- Segregation , Shifting of 132kV tower structure and hardware to the work place .
- Erection of 132 Tower Structure.

Working hours: 8 Hours a day


Client Specification: Ref customer specification- Tech. Spec. Section VI [Part 1 & 2] & Part IV

2.0 Location of Work (Give site address and precise location on site where work is to be carried out. Give details of
any other locations in the proximity of the works which may affect the safety of the work or be affected by the
work considering Surrounding Environment and what measures will be used to control these risks e.g.
segregation, warning notices, fencing, Structural stability precautions)

Work to be carried out in 123KV Transmission Line(D/C & S/C) at Different Locations From NTPCC To Ujani.

3.0 Safety Document /Specific Approval Required (Details of any safety documents or specific approval (i.e.
Client specific approval) required to undertake the work)

 Site Specific Risk Assessment


 PTW & Tool Box Talk in consultation with customer
 PSS OHSAS Manual
 OHS COP
 ABB Site manual, Part-1 & 2

4.0 Access & Egress to the work area: Give details of any special access or egress arrangements (i.e.
Ladders/MEWPS/Scaffold/Trestles/Step Ladder etc.) that will be used including any obstruction/restriction in
safe access to work area. Consider the site access from the public road onto and around the site before vehicles
arrive on site, taking into account the site traffic management plan, the designated work area for delivery
vehicles and the storage area for materials

Page 2
  Method Statement

 Compacted WBM / “Kaccha” Road available some locations.

5.0 Role & Responsibilities of Personnel/Parties Involved in activities:- Clearly define role and responsibilities
of all personnel involved in activity i.e. Site management staff including subcontractors parties- Main contractor
Project/Site Manager, Sub Contractor Site Manager, Project Engineer, OHS staff , Competent Supervisory Staff)

ABB Site management Staff:


Site manager: Mr. C P Singh
Site Safety Coordinator: Mr. Asit B Giri

M/S UNITECH POWER TRANSMISSION LTD. (Contractor) Site management Staff:


Project Manager: Mr. Rajesh Pillai
Site Manager: Mr. Anil Adappa
Civil Engineer: Mr.Kumar
Site Supervisor: Mr. Narendra singh / Mr.S K Mishra/Mr. Arun Roy
Safety Officer: Mr. Vargees

Site Manager :-  Check for the isolation of area for erection


 Check the Work permit from ABB (Client if required in
case of shut down job).
 Coordination with Client /Erection Agency/Safety
Departments for continuous monitoring of activity.
 Check the weather condition before start of work.
 Ensure tool box talk is done before start of the work
 Check fitness of worker visually.
 Check the materials availability and tested tools & tackles
with Proper lifting Machinery.
 Present of Contractor Erection Engineer/Erection
Supervisor/Certified Safety Supervisor for continuous
monitoring of activity in work location.
 Barricading of area during erection of work.
 Check the proper illumination in yard for night work.-
N/A Height work is not Permitted in night.

Erection  Cross check the location before start the activities


Engineer :- involved height work.

 Check the Work permit from ABB/Client.


 Check the weather condition before start of work.
 Check fitness of worker visually.
Page 3
  Method Statement

 Check the materials availability and tested tools & tackles


with Proper lifting Machinery.
 Present of Contractor Erection Engineer/Erection
Supervisor/Certified Safety Supervisor for continuous
monitoring of activity in work location.
 Barricading of area during erection of work.
 Access route to be decided and communicated to all
concerned.
 Check the proper illumination in yard for night work. –
N/A Height work is not Permitted in night.

Safety Officer /  Check the weather condition before start of work.


Warden:-  Arrange Tool Box meeting with staff and workers before
starting the activity.
 Check fitness of worker visually.
 Check for any underground / OH cables in the area and
isolation if required.
 Check the Work permit from ABB/Client.
 Work Permit to be issued after checking the safety
requirements of lifting Machinery, tools & tackles
arrangements.
 Close monitoring of activities involved height work and
emergency preparedness.
 Barricading requirements to be decided and
communicated to concerned.
 Check House Keeping.
 Check the proper illumination for night work.
N/A Height work is not Permitted in night.

6.0 Working/Activity Description:- It is important that all operatives should have clear idea of those operational
sequences and responsible supervisor must verify their competency prior to their engagement in operation.

6.1 Pre-Testing Checks


 OHS Induction
 Work specific Training
 Ground condition in & around work place

6.2 Resources (Equipment , tools including manpower) Details i.e. Equipment and Tools, specific operational
equipment, test kits, lifting resources, Details of materials to be used in operation, Details of the manpower
allocated to the task, e.g. titles, qualifications, competences, direct manpower, contractors. Details of plant,
tools and equipment to be used for the work, including the availability of relevant statutory documents, checks
or inspections etc. Details of fencing, barriers, cones, chains, dangers notices, warning signs etc.

Page 4
  Method Statement

 Machinery tools & tackles material as per list attached below.


 Skilled Manpower for manual/Hydra/Crane/ Tractor trolley/truck shifting of
material from storage yard to place of erection.
 Approval to do work in Extended hours by BU Manager – Height work not
allowed in Extended Hours
 Proper Illumination if working in extended hours with required permission

6.3 Details of Permits to Work required for activity: List out applicable Permits in sequence of work, for eg.
PTW(Permit to work), SFT, LAP(Limited access permit)

 Check for Work permit from Customer if the work to be performed under
shutdown.
 ABB work permit to be issued after checking the safety requirements.
 Tool Box Talk prior to start of work.

6.4 Operational Sequence of work (i.e. Test Procedure) :- Full description of the work, setting out the
methodology in a sequential manner, including any reference to any identified operational restraints. Also refer
here sec. 5.0 responsibilities part for every step of work sequence).
Unloading /Shifting and Erection of Structure

Sr.
No Activity Details of Job sequence Risk Involved Control Checks
.
1 Unloading 1. Unloading of material on an 1. Contact with rough 1. Ensure work permit is
and identified place of storage. edge. issued.
shifting of 2. Identification of structure 2. Fall of material. 2. Ensure work specific
lattice material. 3. Failure of lifting tool box/training
3. Segregation of all material equipment. 3. PPE (Hand Gloves,
structure
as per Bill of Material. 4. Slippage of material. Helmet, shoes) used.
Tower/Be 4. Shortage \ Damage report 5. Toppling of 4. Allow only authorize
am to be prepared. crane/hydra b’coz of person to work.
uneven access. 5. Check the condition
and load test report of
all lifting tools /crane.
6. Use proper size of
rope/slings/Belt as per
weight of Material to be
Lifted.
7. Ensure the
transportation route
must be firmed and
levelled.

Page 5
  Method Statement

2. Shifting 1. Shift the structure, nuts, 1. Tilting of Main leg 1. All lifting tools /
and bolts and washers as per member. equipment must have
Erection Bill of Material near to the 2. Fall of Material/Tools. valid test certificate.
of Main place of Erection. 3. Fall of worker. 2. Check the capacity of
2. Clear the area near the 4. Failure of lifting crane/hydra and weight
Leg
foundation and check the material. of Material.
Member. anchor bolts of foundation. 5. Toppling of 3. PPE (Hand Gloves, Full
3. Assemble the main leg Crane/Hydra. body harness ( energy
member up to 2-3 section. 6. Communication gap Absorber)with 2 lanyard
4. Fix and tighten the step between Supervisor having opening
bolts in criss cross manner and crane operator. minimum 80mm,
in all the leg member for Helmet, shoes) used.
the movement of a person. 4. Engineer/supervisor
5. Provide the vertical life line needs to be present till
in all the 4 leg member and completion of work.
keep 1 spare for change 5. Allow only authorize
over. /Trained person to
6. Erect the main leg member work.
by crane / Hydra and 6. Ensure work specific
provide guide rope 2 side. tool box/Training..
7. Remove the rope from 7. Check the condition
crane/hydra hook by and load test report of
climbing thro step bolts. all lifting tools /crane.
8. Level the main leg member 8. Use proper size of
by water tube. rope/slings/Belt as per
weight of Material to be
Lifted.
9. All persons should away
from the lowering
material.
10. The load should be
guide by the guide rope
to prevent toppling.

3. Erection 1. Assemble 2/3 members as 1. Tilting of Main leg 1. All lifting tools /
of cross per the drawing. member. equipment must have
members 2. Provide the packing washer 2. Fall of Material/Tools. valid test certificate.
up to where ever required. 3. Fall of worker. 2. Check the capacity of
3. Lift the above members and 4. Failure of lifting crane/hydra and weight
section 2-
fix it on the main leg material. of Material.
3 member. 5. Injury due to rough 3. PPE (Hand Gloves, Full
4. Complete the fixing of cross edge of members. body harness( Energy
members up to 2-3 section 6. Toppling of absorber) with 2
of main leg member. Crane/Hydra. lanyard having opening
7. Communication gap min 80mm, Helmet,
between Supervisor shoes) used.
and crane operator. 4. Engineer/supervisor
needs to be present till
completion of work.
5. Allow only authorize
/Trained person to
work.
6. Check the condition

Page 6
  Method Statement

and load test report of


all lifting tools /crane.
7. Use proper size of
rope/slings/Belt as per
weight of Material to be
lifted.

4. Erection To lift the next Section of 1. Tilting/Fall of Derrick. 1. All lifting tools /
of Derick Tower, the following 2. Fall of Material/Tools. equipment & winch /
and fixing steps to be followed : 3. Fall of worker. Hydra must have valid
of Balance 4. Failure of lifting test certificate.
material. 2. Provide the overlap of
leg/cross 1. The Derrick will have
5. Injury due to rough derrick and main
members. horizontal MS rod of edge of members. member by 1 to 1.5 Mtr.
12mm dia x 200 Long 3. PPE (Hand Gloves, Full
welded 100 mm from top body harness with 2
& bottom of Derrick. This lanyard having opening
rod will pass through the min 80mm, Helmet,
hole and welded at two shoes) used.
ends. One pulley ‘P1’ is 4. Engineer/supervisor
fitted to this rod using a needs to be present till
rope for lifting the load. completion of work.
5. Allow only authorize
2. Provide 2 -3 side guide
/Trained person to
rope on the derrick. work.
3. Fix one Pulley ‘P2’ on the 6. Check the condition
top of the Main member ‘ and load test report of
A’ already erected all lifting tools /crane.
(previous section). 7. Use proper size of
4. Provide 2/3 life line on rope/slings/Belt as per
the Main member ‘A’ weight of Material to be
through which derrick to lifted.
be lifted. 8. Use tool bag to carry
hand tools & small nuts
5. Fix one pulley ‘P3’ at the
and bolts.
bottom of the leg member 9. Ensure fall arrestor
at the foundation level along the leg with rope
for ease in hoisting the grab.
derrick.
6. Lift the derrick using
Pulley ‘P1’ up to the level
of main member ‘A’ with
the help of pulley ‘P2’
fixed on the top of main
member.
7. Positioning ropes should
be used to loosely tie the
derrick and the Main leg
member at two places so
Page 7
 Method Statement

as to avoid tilting during


hoisting of the derrick.
8. 2 trained workmen shall
ascend on the Main
member ‘A’ using
independent life line.
They shall anchor
themselves using double
lanyard. They shall guide
the derrick during
upward movement.
9. Now,remove the rope
from the top of the
derrick and Connect the
to the bottom of the
derrick.
10.During this transition
period, the derrick shall
be fastened by
positioning ropes to the
main member.
11.Now hoist the derrick
upwards using pulley
‘P2’ & ‘P3’ upto a level till
the overlap of Main
member ‘A’ & derrick
shall be 1-1.5 Mtr.
12.Now, the top of the
derrick shall be above
the main member ‘A’.

13.Tie/fasten the derrick


with the main member
‘A’ by rope at 2/3 places
keeping a over lap of 1 to
1.5 Mtr between main
member and derrick.
14.Remove the pulley ‘P2’
from Main member ‘A’.
.
Lifting of Main member (B)
of next section

15. Provide the vertical life line


with fall arrestor and step
bolt in all the main member
to be lifted.
16. Fix pulley ‘P2’ on the top of
the main member to be

Page 8
  Method Statement

lifted. (This is required for


lifting the derrick to the
next section.)
17. Lift the Main member (B)
with the pulley provided on
the top of derrick and fix it
on Main member (A) with
proper cleat plate/angle as
per drawing
18. Remove the rope on the
Main member (B) by
climbing on the step bolts.
19.While descending, the
step bolts on the Main
member ( B) used to
climb are removed. This
is to facilitate the fixing
of cross bracings.

20.Lift all the other main


members as per the
above sequence.
21. Provide the cross members
and gusset plate.
22. This completes the erection
of second section of the
Tower.
23. Continue the same till the
completion of tower up
peak.
24. Remove the derrick and
other lifting material etc.
25. Tighten all the bolts/nuts
of the tower.
26. Once again align the tower
and provide the check nut
on the anchor bolt.

6.5 Isolation Requirements:- Before starting the work, identify the work area demarcation and accordingly
isolate it from other part of operational interference. Responsible supervisor should cross verify adequate
isolation arrangements for safe operation prior to receive Permit to work and if PTW not applicable then before
start of operation during pre-check survey. Accordingly adequate caution tag/signs to be provided .

 Check for any underground / overhead Cables prior to start of activity.


 If so, Isolate same and get permit before start of work.
 Barricading to be done near the place of erection.
 Area to be levelled near the foundation.

Page 9
  Method Statement

6.6 Final Checks & restoration of work area after completion of work :- Those checks to be carried out by
responsible supervisor in witness of his line hierarchy by use of specific checklist of certain operational checks
and once those completed satisfactory, PTW(if applicable) to be closed and isolation arrangements to be
restored by removing barricades/cautionary tags.

 Remove all the site worker staff from site


 Remove any balance material.
 Remove all tools and Plants.
 Closing of Work Permit after completion of activity.

7.0 Task Specific Hazards: - Refer to Task Specific Risk Assessment and attach in appendix

Attachment: - List of tools and plants.

In addition, please provide below control measures in risk assessment (as applicable).

Fall Protection Use Full Body Harness with double lanyard to be used.
Measures: Provide vertical life line / fall arrestor.
(Where work at height
cannot be avoided)

Electrical Safety Measures (1) For electrical connections ensure with ELCB, MCB & three
core double insulated cable.
(2) Area Illumination is to be ensured for extended hours
works.

Lifting Safety Measures Use of specified Crane and Hydra according to Load Chart, Lifting
belts and D-shackles capacity.

Others (please provide Lunch break 1 Hr and Portable water container availability is need
details) to be ensured.

Hazardous
Substances:
(Attach MSDS if required)
N/A N/A N/A N/A N/A N/A N/A

8.0 Emergency Provisions: - Relevant operational possibility of a programme in the case of emergency
situation i.e. electrical supply restoration. In addition emergency response provisions i.e. first aiders, fire
fighting, first aid arrangements, nearest onsite/offsite emergency response also to be considered during
emergency planning.
1) Site Supervisor has to report any incident to Site Manager immediately.
Page 10
  Method Statement

2) Supervisor has to take off control over the danger and rescue over the incident
3) Site manager has to inform to the first aider
4) First aider to reach at spot with first aid box and stretcher and provide first aid
treatment and raise siren in case of emergency
5) Site manager to call ambulance (if required)
6) Site manager alerts to Doctor and asked for treatment (if required)
7) Site manager to inform Project Manager, client and concern government
authorities if required

Asit B Giri
Mobile No: 09766090757

ABB Site Office , ESSEL Office & NTPC First


Aid Centre

CITY HOSPITAL
Phone No- 0217-2315155 / 2315156

9.0 Waste Disposal/Housekeeping and Environmental issues :- Details waste disposal processes and or housekeeping
activities, Details of environmental impacts and control measures.

Our scope of work does not involve disposal of hazardous substances. Our works
will generate negligible wastage. Those too will not be harmful and will be
disposed of in the proper manner at designated place.

10.0 Personal Protective Equipment (PPE) :- PPE requirements for the task

YES/NO Yes Yes Yes No No No No

11.0 Amendments and additional information:- Should any part of this method statement require amendment
or alteration, this must be notified for agreement by all relevant parties prior to it being enforced.

13.0 Communication of method statement and signing off register: Communicate to all relevant parties (via a
toolbox talk) and ensure it is signed by all personnel.
Page 11
  Method Statement

Emergency response plan and contact number displayed at all work locations and also communicated during
Tool box meeting.

Persons involved with the work

I undersigned have read, discussed and fully understand the above method statement and risk assessment on
activity and will adhere to all method of work and condition set down.

Name Company Designation Date & Signature

H S SHARMA ABB India Ltd Site Manager


C P Singh
ASIT B GIRI ABB India Ltd Site safety supervisor
Rajesh Pillai M/s Unitech Power Project Manager
Transmission Ltd.
Anil Adapa M/s Unitech Power Site Manager
Transmission Ltd.
Jojy Varghese M/s Unitech Power Safety Officer
Transmission Ltd.
Pawar M/S Unitech Power Store In-Charge
Transmission Ltd

ANNEXURE for Point no- 6.2 (T & P Details)


TOOLS REQUIRED FOR TOWER/BEAM ERECTION

Sr No Man power / Tools Required Remark


1 Erection Gang – 15 person 1  
2 Derrick 2  
3 Wire Rope 12 mm 200 Mtrs 2  
4 Poly propelyne rope 8 Bundle (200 Mtrs)
5 Torque Wrench 4  
6 Double Pulley ( Set ) 4 Open able
7 Single Pulley 4  
8 Slings – 1 Mtrs 4 For fixing Pulley
9 Slings – 2 Mtrs 4  
10 Rope pieces ( 2M to 5M) LS  
11 D shackle 4 For fixing Pulley
12 Crow bar 1  
Spanner set 4  
13
14 Plier 2  

Page 12
  Method Statement

15 Hammer 2  
16 Jute Bag LS  
17 Cotton hand gloves 20 Pair  
18 Hydra/Crane/Winch Machine/Truck/Tractor 1 No For Shifting and lifting the material
19 Vertical life line / fall arrester 5 No.
ANNEXURE OF LIST OF REFERENCE DRAWINGS

ABB
Description of Document
Document No.

STRUCTURE DRAWINGS
 
3VIN100471T4564 765KV 7CA PORTAL DESIGN CALCULATION
ABB/ADN/STR-02 765KV 7CA PORTAL FABRICATION DRAWING
3VIN100471T4563 765KV 7CB PORTAL DESIGN CALCULATION
ABB/ADN/STR-01 765KV 7CB PORTAL FABRICATION DRAWING
3VIN100471T4565 765KV 7CC PORTAL DESIGN CALCULATION
ABB/ADN/STR-03 765KV 7CC PORTAL FABRICATION DRAWING
765KV 7GWCB BEAM DESIGN CALCULATION
765KV 7GWCB BEAM FABRICATION DRAWING
  765KV 7GWCC BEAM DESIGN CALCULATION
765KV 7GWCC BEAM FABRICATION DRG
   
  400KV GANTRY STRUCTURE
3VIN100471T4571 DESIGN CALCULATION FOR 400KV BEAM MKD. - G1
3VIN100471T1548 FABRICATION DETAILS FOR 400KV BEAM MKD. - G1
3VIN100471T4572 DESIGN CALCULATION FOR 400KV BEAM MKD. - G2
3VIN100471T1549 FABRICATION DETAILS FOR 400KV BEAM MKD. - G2
3VIN100471T4573 DESIGN CALCULATION FOR 400KV TOWER MKD. - TC
3VIN100471T1550 FABRICATION DETAILS FOR 400KV TOWER MKD. - TC
3VIN100471T4574 DESIGN CALCULATION FOR 400KV TOWER MKD. - TH
3VIN100471T1551 FABRICATION DETAILS FOR 400KV TOWER MKD. - TH
3VIN100471T4575 DESIGN CALCULATION FOR 400KV TOWER MKD. - TI
3VIN100471T1552 FABRICATION DETAILS FOR 400KV TOWER MKD. - TI
3VIN100471T4576 DESIGN CALCULATION FOR 400KV TOWER MKD. - TJ
3VIN100471T1553 FABRICATION DETAILS FOR 400KV TOWER MKD. - TJ
3VIN100471T4577 DESIGN CALCULATION FOR 400KV TOWER MKD. - TM
3VIN100471T1554 FABRICATION DETAILS FOR 400KV TOWER MKD. - TM
3VIN100471T4578 DESIGN CALCULATION FOR 400KV TOWER MKD. - TN
3VIN100471T1555 FABRICATION DETAILS FOR 400KV TOWER MKD. - TN
   
  765KV EQUIPMENT STRUCTURE
3VIN100471T4566 DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - LA
3VIN100471T1556 FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - LA
3VIN100471T4567 DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - BPI
3VIN100471T1557 FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - BPI

Page 13
  Method Statement

3VIN100471T4570 DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - ISOLATOR


3VIN100471T1560 FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - ISOLATOR
3VIN100471T4568 DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - CT
3VIN100471T1558 FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - CT
3VIN100471T4569 DESIGN CALCULATION FOR 765KV EQUIPMENT STRUCTURE MKD. - CVT
3VIN100471T1559 FABRICATION DETAILS FOR 765KV EQUIPMENT STRUCTURE MKD. - CVT
   
  400KV EQUIPMENT STRUCTURE
3VIN100471T1561 400KV EQUIPMENT STRUCTURE MKD - LA
3VIN100471T1562 400KV EQUIPMENT STRUCTURE MKD - BPI
3VIN100471T1564 400KV EQUIPMENT STRUCTURE MKD - CVT
3VIN100471T1563 400KV EQUIPMENT STRUCTURE MKD - ISOLATOR
3VIN100471T1565 400KV EQUIPMENT STRUCTURE MKD - CT
3VIN100471T1566 400KV EQUIPMENT STRUCTURE MKD - WT
3VIN100471T1568 400KV EQUIPMENT STRUCTURE MKD - LA - HIGH LEVEL
3VIN100471T1567 400KV EQUIPMENT STRUCTURE MKD - BPI - HIGH LEVEL
3VIN100471T1569 400KV EQUIPMENT STRUCTURE MKD - CT (High Level)
   

Page 14