Download as pdf or txt
Download as pdf or txt
You are on page 1of 39

‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

SWCC Contractor Safety Policy


To eliminate the concept of negligence among contractors, the Safety Department administers
safety orientations for contractors. These orientations are carried out by the safety inspector. In
these orientations the safety inspector explains the basic ideas of safety, how an individual can
protect himself against harm, and the Corporation’s Safety Rules that govern all kinds of activities
in plant including people’s behavior.
The handbook mandates safety obligations for the contractor which he has to fulfill. The handbook
is believed to organize and control all activities conducted by the contractor’s employees. In other
words, it clearly states SWCC’s guidelines which the contractor needs to comply with. Figure (2-1)
shows how the Policy should be carried out.

Contractor’s Orientation Process

Requesting Department Schedule Contractor’s visit


to Safety and Health and Environment Department

Information, Safety Manual provided to contractor’s


representative by the Safety Inspector

Acknowledgment Form to be signed by the


representative and to be stamped by his manager

Provide the Safety Department with the Stamped


Form and Contractor’s Safety Manual

No Contractor completes all


All the above Requirements

Yes

Clearance for ID Issuance


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

CONTRACTOR SAFETY HANDBOOK


This Contractor Safety handbook is prepared in conjunction with SWCC approved Systems and
Procedures as attachment to the STANDING INSTRUCTION No. P-037 with special reference to the
following documents and is issued as basic guidelines to be adhered by all contractor personnel
engaged at SWCC facilities.

This Handbook is divided into two sections. Chapter-1 “CONTRACTORS’ SAFETY ORIENTATION
PROGRAM” is intended for familiarization of all the Contractors engaged by SWCC to work on its
facilities with the Safety Principles and Policies of the Plant and to provide them with the basic
and minimum Safety requisites to ensure compliance with the Safety Rules & Regulation. The
Safety Orientation Program will be conducted by Safety, Health and Environment Department to
the Contractor Management and Supervisors prior to commence their activities.
Chapter-2 “CONTRACTOR SAFETY GUIDELINES” is for procedural description and detailed
instructions on execution of contractor’s activities in a safe and secure manner. This section deals
with the Safety Principles and Safe working practices. All Contractors shall therefore, ensure that
they meet all the Safety requirements and obligations prior to commence their work at SWCC
premises and that all employees are fully aware of the Safety Regulation and exercise the same
to ensure Safety of all men irrespective of their employers and of all SWCC proprietary.
In the event of conflict in applying the Standard Procedures and Practices, SWCC Safety, Health
and Environment Department with the approval of Plant Manager shall take the necessary action
to resolve the conflict and to ensure the greatest protection of the Safety and Health of all
personnel and Safety of the SWCC proprietary.
COPIES OF THIS HANDBOOK SHALL REMAIN AVAILABLE AT CONTRACTOR’S JOBSITE
THROUGHOUT THE TENURE OF HIS WORK DURATION AT SWCC PREMISES.
For more precise course of action and guidelines needed in determining safe procedures and
practices, the following standards will be used as the source of origin.
References:
- Occupational Safety & Health Administration (OSHA) 1910 & 1926.
- National Electrical Code (NEC).
- National Fire Protection Association (NFPA).
- American National Standard Institute (ANSI).
- Nuclear Regulatory Authority (IAEA).
- Middle East Environmental Protection Agency (MEEPA).
- Handbook of Civil Engineering.
- SWCC Systems and Procedures.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

TABLE OF CONTENTS

Chapter-1 contractors safety orientation

Section Description Page no.

1 CONTRACTOR PROFILE

2 CONTRACTORS SAFETY RESPONSIBILITIES

3 EMERGENCY PROCEDURE & CONTACT NUMBERS

4 TEN BASIC SAFETY RULES

5 CONTRACTORS SAFETY ORIENTATION CHECKLIST

5.1 MANDATORY ITEMS

5.2 REPORTING OF ACCIDENTS / INJURIES

5.3 HAZARDOUS CHEMICALS

5.4 SAFETY MEETINGS

5.5 CONFINED SPACE ENTRY

5.6 PERMIT TO WORK PROCEDURE

5.7 FIRE PREVENTION & PROTECTION

5.8 FALL PROTECTION

5.9 BARRICADE TAPE

5.10 EMERGENCY EVACUATION PROCEDURES

5.11 MOBILE EQUIPMENT

5.12 EXCAVATION

5.13 DEMOLITION

6 CONTRACTOR ACKNOWLEDGEMENT

7 SAFETY ORIENTATION ATTENDANCE SHEET


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

TABLE OF CONTENTS
CHAPTER-2 CONTRACTORS SAFETY GUIDELINES
Section Description Page no.
1 SWCC SAFETY REGULATIONS
2 SWCC REQUIREMENTS FOR PERMIT TO WORK
3 CONTRACTOR SAFETY ORGANIZATION
MANAGEMENT
3.1
Figure 1.1-Example of Project Manager’s Pledge
3.2 SAFETY REPRESENTATIVE
3.3 SUPERVISOR / FOREMAN
3.4 EMPLOYEE
4 CONTRACTOR SAFETY REQUIREMENTS
4.1 GENERAL SAFETY REQUIREMENTS
CONTRACTOR’S SAFETY PLAN
4.2
Figure 1.2-Example of Contactor’s Safety Plan
4.3 EMPLOYEES SAFETY HANDBOOK
4.4 CONTRACTOR SAFETY MEETINGS
4.5 DAILY TOOL BOX MEETING
4.6 WEEKLY SAFETY MEETING
4.7 MONTHLY SAFETY MEETING
5 EMPLOYEES SAFETY TRAINING
6 ACCIDENTS & MEDICAL CARE
6.1 FATALITIES
6.2 SERIOUS INJURIES
6.3 EMPLOYEE LOST WORKDAY CASE
6.4 SPECIAL INVESTIGATION OF ACCIDENTS
6.5 ACCIDENT REPORTING
6.6 ACCIDENT INVESTIGATION REPORT FORMS
6.7 MEDICAL FACILITIES
7 RULE OF CONDUCT AND SAFETY REGULATIONS
7.1 Entry into SWCC facilities
7.2 RULE OF CONDUCT
7.3 PERMISSION TO WORK
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

7.4 WORK DRESS STANDARD


7.5 PERSONAL PROTECTIVE EQUIPMENT
7.6 WORK SAFETY INSPECTION
7.7 EQUIPMENT INSPECTION, O & M AND REPAIR
7.8 REPORTING OF UNSAFE CONDITIONS
7.9 REPORTING OF INJURIES AND PROPERTY DAMAGE
7.10 PERSONAL CONDUCT
7.11 INSUBORDINATION
7.12 DRUG POSSESSION AND USE
8 SPECIFIC TASKS
8.1 SPECIAL SKILLS AND PROTECTIONS
8.1 WORK WITH IONIZING RADIATION
8.3 ENVIRONMENTAL PROTECTION
9 DEMOLITION & CONSTRUCTION
9.1 RESPONSIBLE PERSON
9.2 ORIGINAL DRAWINGS
9.3 DEMOLITION EXCAVATION PERMIT
9.4 UTILITIES AND INPUT / OUTPUT CONNECTIONS
9.5 SITE PROTECTION
9.6 METHOD OF DEMOLITION
9.7 STABILITY DURING DEMOLITION
9.8 WORKING PRACTICES
9.9 STRUCTURAL STEEL DEMOLITION
9.10 TANK VESSELS & PIPE WORKS
9.11 PROTECTIVE CLOTHING & EQUIPMENT
9.12 MECHANICAL EQUIPMENT
9.13 USE OF EXPLOSIVES
10 ENCROACHMENT TO SWCC FACILITIES
11 OTHER REGULATIONS
12 FORM
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

SAFETY & OCCUPATIONAL HEALTH POLICY


SWCC is the largest producer of desalinated water in the world by using the best available technologies
and relying on a solid goal and promising cadres and national capacities. Also, SWCC Supplies various
regions in the Kingdom with desalinated water.
out of its commitment to provide a safe work environment and ensuring the health and safety of
employees and operational processes and in line with the sixth strategic goal "Sustainability of Safety and
Security", SWCC is working to implement the Safety & Occupational Health Management System in
accordance with the requirements of local regulatory laws in Saudi Arabia and international standards
within the principles and commitment as following:
1. The Corporation is committed to providing a safe working environment for workers, contractors, and
visitors that will prevent accidents, injuries, or occupational diseases by taking all measures from
periodic evaluation of risks and risks related to employee safety and production operations safety.
2. The Corporation is committed to applying an integrated management system for occupational health
and safety in all its activities, in line with the requirements of local laws in the Kingdom of Saudi Arabia
and international standards ISO 4500I to reach the best levels in the system of the Safety &
Occupational Health.
3. The Corporation is committed to setting goals for the Safety & Occupational Health in all of its sector
and continuously maintaining updated systems and procedures for the proactive and interactive
monitoring process.
4. The Corporation is committed to Initialize conditions to ensure that employees are able to raise and
discuss the Safety & Occupational Health issues publicly and equally applying occupational health and
safety requirements at all levels.
5. The Corporation is committed to providing qualification, training, information and necessary
procedures to all employees and all concerned to increase awareness and to ensure that their
responsibilities are carried out in a safe manner.
6. The Corporation is committed to the effective application of the Safety & Occupational Health system
by providing all necessary resources for this.
7. The Corporation is committed to select contractors based on local and international standards in the
field of the Safety & Occupational Health.
8. All employees must comply with applicable laws and regulations such as (Personal Protective
Equipment) and others in the Safety & Occupational Health Management System.
9. Employees, contractors, and visitors are obligated to report the Safety & Occupational Health incidents
and near misses and unsafe condition and unsafe act Compulsorily.
10. All employees, contractors, and visitors are responsible for their own safety and that of others and
are expected to contribute to the achievement of the Safety & Occupational Health goals.
11. The commitment of all employees at all levels of responsibility to implement this policy.
12. Carry out periodic inspections to ensure compliance with this policy and breach of non-compliance
in accordance with the institution's regulations and regulations.
13. The Corporation is committed to make plans to face emergencies and crises in a manner that
preserves lives and properties and to provide the necessary training for them to all workers.
14. By reviewing the Safety & Occupational Health management system, which guarantees continuous
improvement of performance.
This policy shall be published on all sites under SWCC Control and shall be circulated and explained to all
employees and stakeholders, and everyone must implement it and report any failure in that. Also, periodic
inspections shall be held by specialists to ensure its proper implementation.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

SWCC Environmental Recommendations and Instructions


SWCC Gives utmost importance to the protection of the environment and the health of its
employees and all concerned parties. The Environmental Protection Department confirms the
identification and efficient treatment of environmental hazards to prevent all types of loss of life,
property and the environment. We are determined to achieve our vision by reducing the
likelihood of damage to the environment, injuries and occupational diseases of our employees,
contractors/subcontractors, visitors, our external environment and compliance with the
environmental laws of the regulatory authorities.
To achieve our objectives in the environment and occupational health, all employees and
contractors/subcontractors must ensure personal responsibility for the environment and
occupational health and preserve the environment. We encourage all SWCC employees,
contractors/subcontractors and operators to present a good example and to be leaders in the
environment, occupational safety and health at work and out of work and follow the below work
recommendations:
• Adherence to the use of clothing and personal protective equipment
• Obtaining the necessary permits and licenses to complete the work.
• The Contractor/subcontractor's personnel should receive environmental qualification and
training before performing their duties.
• Follow the steps of the procedures for operation and maintenance and environmental
management system during the performance of tasks.
• Ensure a clean work sites and waste removal resulting from contractor activities such as oils
and other waste.
• Work in accordance with applicable standards and regulations.
• Comply with the environmental requirements of the plant by reviewing the manual and
procedures of the Environmental Management System of SWCC.
• The materials, equipment and used devices by contractors/subcontractors shall be stored in
appropriate warehouses and specific areas that meet the storage conditions as per SWCC
requirement as per the following:
✓ Well determined area, protected from external influences and identified by signs that
determine the type and degree of gravity of the stored materials.
✓ Segregated by type of waste and accompanied by a signage in each zone.
✓ In Use, Used and Old oil and chemical drums should be placed in secondary containers to
avoid spillage and soil contamination.
✓ It should be equipped with a concrete floor and impermeable layer with a separate
discharge system from the rain drainage system at the plant.
✓ Allocate a covered area for hazardous industrial waste that cannot be left under the sun.
✓ Allocate paths for easy movement within the storage area.
✓ Commitment to storage in an orderly manner.
• The presence of the contractor/ subcontractor’s representative (to be determined with his
deputy before starting the contracting work) in the meetings of the environmental
committee in the plant and follow up the implementation of the recommendations issued by
the committee if requested, in addition to participating in the inspection visits to the work
sites.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

• Record all cases of damage to the environment that occurred and expected to occur, as well
as cases of damage to the property of the plant.
• The environmental department should be informed about environmental accidents and
investigated by contractors/subcontractors (accidents occurred, incidents, property damage
and work interruption).
• Ensure that all equipment are ready and in good status before starting to perform tasks by
following up the regular maintenance programs and ensure that they do not harm the
internal and external environment of the plant and the Corporation.
• Compliance with container codes when wastes disposal in the plant and do not mix wastes
of different types and gravity:
Municipal waste: green containers
Inert waste: Black containers
Non-hazardous industrial waste: Blue containers
Hazardous industrial waste: Red containers
Register and document any transport and disposal of all waste types and their
hazardousness by using the form SWCC MR-37 waste delivery note with all relevant
information (quantities, type and method of final disposal) and signature by the
responsible for the transport of such wastes and the final recipient.
Compliance with waste disposal and transporting according to the SWCC-MR-35 Waste
Removal Plan of the SWCC, which is prepared by the contractor representative and the
Environmental Management Department in the plant to avoid waste accumulation at the
plant, foul odors, rotting and environmental and health damage.
The contractor/subcontractor shall provide the Environment Department at the plant of
copies of all evidence of waste disposal in the case of final disposal in the landfill.
Ensure that environmental licenses are obtained from the Environmental authority before
carrying any transport disposal of any types of waste and provide SWCC with all qualification
certificates for this purpose.

‫تاري خ نهاية‬ ‫تاري خ بداية‬ ‫نطاق‬


‫التوقيع والختم‬ ‫التاري خ‬ ‫اسم الممثل ونائبه‬ ‫رقم العقد‬ ‫المقاول‬
‫العقد‬ ‫العقد‬ ‫العمل‬
Date of Date of
Signature & Representative & Contract Scope
date contract contract Contractor
stamp his deputy number of work
ending starting

SA05C1 napoli
eng suhail Nanaah
-32AZ- contracting est
388-00

By signing, the contractor agrees that he has read all the ‫بالتوقيع يقر المقاول عىل االطالع عىل كل التعليمات الموضحة أعاله‬
‫ز‬ ‫ز‬
above instructions and to abide by them and follow them in ‫وااللتام بالتقيد بها واتباعها يف كل األماكن والمرافق التابعة للمؤسسة‬
all places and facilities of the saline water conversion ‫العامة لتحلية المياه المالحة خالل كامل مدة عمله‬
corporation and during the entire period of his work

This form shall be signed by the contractor before starting ‫يتم التوقيع عىل هذا النموذج من قبل المقاول قبل انطالق أي عمل‬
‫ز‬
any work activity in the plant ‫يف منظومة أو وحدة اإلنتاج‬
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

CHAPTER-1
Contractors Safety Orientation Program
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

1. CONTRACTOR’S PROFILE

CONTRACTOR’S NAME Napoli contracting est.

TYPE OF WORK ASSIGNED

JOBSITE LOCATION AT SWCC

TYPE OF MACHINERY TO BE USED

Dammam , almazroyah
ADDRESS

TELEPHONE NO. 0543932699

eng . farhan shaikh


PROJECT MANAGER’S NAME

EMERGENCY CONTACT NUMBER 0504910838

SUPERVISOR / FOREMAN NAME

EMERGENCY CONTACT NUMBER

ESTIMATED NUMBER OF WORKERS


REQUIRED TO WORK AT SWCC SITE

Email Info@napoli.sa

Project duration

SWCC contact person/ Engineer/


Project responsible>

Site / Project Managers Signature: _____________________________ Date: ______________


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

OUTLINE

Copies of driver's license, certifications or trainings, records of employees operating


vehicles, forklifts or heavy equipment
Review “contractor safety policy”
Review “emergency procedures & emergency numbers”
Review “ten basic safety rules”
Review “contractor safety orientation checklist”
Show “safety orientation” video

2. CONTRACTOR’S SAFETY RESPONSIBILITIES

All contractors shall be responsible for developing, maintaining and supervising an on-site Safety
Program equal to or exceeding the requirements of SWCC Plant’s Safety Program. The safety
requirements listed below should be followed by all contract employees.
1. All contract personnel are required to wear hard hats and safety shoes while in SWCC plant
property.
2. Safety glasses are considered basic eye protection. Certain areas and jobs will require
additional protection such as face shields or chemical goggles. Chemical goggles or face
shields must be worn when handling chemicals or operations where eye injury may result.
3. Hearing protection in the form of ear muff or ear plugs must be worn in all high-noise level
areas and during any high-noise activities. Cotton or tissues is not considered as protection.
4. Housekeeping is a top safety priority and every contractor should clean up after themselves.
5. Wear clothes suited for the job, these includes a shirt with sleeves and long pants.
6. Absolutely no loose clothing or jewelry is to be worn around moving machinery.
7. All shoes and footwear have steel or composite material for foot protection. Absolutely no
slippers are to be worn inside the plant.
8. Welding blankets shall be used to protect surrounding equipment and materials. Welding
curtains shall be set up when situations exist where exposure to the welding flash is a risk.
Welding gloves shall be worn during any type of welding operations.
9. Hot work permits shall be obtained and return on daily basis when working in areas that
requires such permit. These permits can be obtained by contacting the area Shift Charge
Engineer at the Main Control Room.
10. The Confined Space Entry and Permit to Work System of SWCC will be followed. These
permits can be obtained by contacting the area Shift Charge Engineer.
11. All contract personnel are required to wear the full body harness when working roofs or
elevated structures above 1.8 M (6 ft).
12. All scaffoldings shall be properly erected as per standard. Planking is to be fixed with hook
clamps, pipe lock at both ends or equipped with cleats. Ladder should protrude at least 36"
from top the rail.
13. Horse play is dangerous and will not be tolerated.
14. Contract employees operating moving equipment shall be trained and authorized to
operate such equipment.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

15. All power tool cords, equipment, cables and extension cords must be protected with
Ground Fault Circuit Interrupters (GFCI). It should not be hung up off the ground to prevent
tripping hazards. Do not hang cords or attached to hot pipes.
16. Any hazardous waste or regulated waste must be properly disposed by the contractor.
17. SWCC reserves the right to inspect all vehicles, equipment and packages entering or leaving
the plant.
18. Work on any chemical system by a contractor will require the appropriate permits, personal
protective equipment, and procedures.

3. EMERGENCY PROCEDURES & NUMBERS

UPON DISCOVERY OF ANY UNSAFE CONDITION OR IN CASE OF FIRE, ACCIDENT OR ANY OTHER
EMERGENCIES, IMMEDIATELY CALL ONE OF THE FOLLOWING NUMBERS, IDENTIFY YOURSELF AND TELL THE
PHONE NUMBER YOU ARE CALLING FROM:

999 SECURITY DEPARTMENT

998 FIRE STATION

997 AMBULANCE (CLINIC)


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

4. TEN BASIC SAFETY RULES

4.1. Comply with all company safety rules and procedures.


4.2. Immediately report all incidents and near misses to your supervisor. Notify emergency
services and administer first aid promptly when needed. Immediately correct or report
unsafe conditions.
4.3. Use the right tools and equipment for the task at hand. Use tools and equipment
appropriately and safely.
4.4. Ensure that tools and equipment are properly adjusted, repaired and serviced.
4.5. Always wear the correct personal protective equipment (PPE). Maintain PPE in good
condition.
4.6. Keep everything neat, tidy and organized; make a place for everything and keep
everything in its place.
4.7. Don’t take chances; if you don’t know, ask.
4.8. Don’t get distracted or engage in horseplay. Focus your attention on the task at hand.
Avoid distracting others.
4.9. Lift loads properly and safely; always lift with your legs, bending your knees. Get help for
heavy loads.
4.10. Get the necessary training to perform your job safely.

5. CONTRACTOR SAFETY ORIENTATION CHECKLIST

All contractor employees are required to be oriented in the safety requirement of the Plant.
Review all applicable items and check them off. Upon completion of the safety orientation, sign
the orientation checklist. The original copy will be filed at the SWCC Safety Department.
5.1. MANDATORY ITEMS

SAFETY HARD HATS


✓ Must meet ANSI Standard Z89.0.
✓ Must be worn at all times inside the plant.
SAFETY GLASSES
✓ Must meet ANSI Standard Z87.0.
✓ Must be worn when work activities cause hazard to the eyes.
✓ Safety glasses must have proper side shields.
SAFETY SHOES
✓ Must meet ANSI Z41.0.
✓ Must have steel or composite protection.
RESPIRATORS
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

✓ Must be worn when respiratory hazards are present.


✓ Employees must be trained in proper used and application of respirators.
✓ The only exception is the single filter disposable dust mask.

5.2. REPORTING OF ACCIDENTS / INJURIES

✓ Contractor will provide First Aid Kits for his employees.


✓ All accidents or injuries must be reported to SWCC Safety Department.
✓ All accidents or injuries must be investigated.
✓ A written report of all accidents or injuries will be provided to SWCC Safety Department.

5.3. HAZARDOUS CHEMICALS COMMUNICATION

✓ All contract employees are trained in the hazards associated with the chemicals being used.
✓ All contract employees are trained in the personal protective equipment requirements of
each chemical being used.
✓ MSDS will be provided to SWCC Safety Department for all chemicals that are brought into
the plant by contractor.

5.4. SAFETY MEETINGS

✓ Contractor will hold Safety Meetings in accordance to the CONTRACTOR SAFETY


GUIDELINES and provide SWCC Safety Department with a copy of minutes and attendance
every month.

5.5. CONFINED SPACE ENTRY

✓ A Confined Space Entry permit must be obtained before entering any confined space.
✓ All equipment in confined space will be placed in ZERO POTENTIAL ENERGY STATE.
✓ Evaluation of confined space will be performed first before entry.
✓ Monitoring of Oxygen level will be performed before entry into confined space.
✓ Periodic monitoring of Oxygen level will be performed by contractor.
✓ Contract employee will attend stand by as a whole watch.
✓ Contract employees are aware of emergency procedures should a rescue be required.
✓ Rescue procedures have been reviewed will all contract employees.
✓ Full Body Harness and Lifeline must be provided should employees to enter any tanks.
✓ Self-Contained Breathing Apparatus (SCBA) available should confined space conditions
require.

5.6. PERMIT TO WORK PROCEDURE


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

✓ Contract employees should aware that NO WORK SHALL BE STARTED without obtaining a
valid written Permission known as PERMIT TO WORK (PTW).
✓ Contractor employees should be briefed about the Safety requirements and rules of SWCC
Permit to Work System.
✓ Contractor employees must understand that SWCC Operations Department through Senior
Authorized Person (SAP) will issue the Permit to Work to the Authorized Person of SWCC
relevant section or Contractor depending on the merit of the case (Ref to clause 2 of
Chapter-2)
✓ Contractor employees are not allowed to alter the position of any ISOLATION boundaries
of the Plant, Process or Equipment, neither they Start / Stop or hinder in any Operation &
Maintenance activities.

5.7. FIRE PREVENTION & PROTECTION

✓ Contractor will use approved containers for any flammable liquids brought into the plant.
✓ Contractor will supply fire extinguishers during hot work operations.
✓ Contract employees have been trained in the class of fire and types of fire extinguishers.
✓ A contract employee will be stand-by as fire watch during hot work operations.
✓ All contract employees have been trained in the use of fire extinguishers.
✓ Contract employees are aware of what to do in case of fire or emergency evacuation.
✓ Oxygen, Acetylene and Liquefied Petroleum Gas (LPG) Cylinder Hoses should be fixed with
flashback arresters in the regulator side and check valves in torch side.

5.8. FALL PROTECTION

✓ Contract employees must wear fall protection (full body harness) when performing work
1.8 M (6 ft.) or higher.
✓ Contract employees have been trained in the proper use and inspection of fall protection
equipment.
✓ All employees are familiar with proper tie off techniques.

5.9. BARRICADE TAPE

✓ Contract employees have been trained in the meaning of different colors of barricade tape
used at SWCC plant.
✓ Contract employees should be familiar with procedures to enter a barricaded area.
✓ Contractor will provide barricade tape to isolate work areas when fall hazards or other
types of hazards present.

5.10. EMERGENCY EVACUATION PROCEDURES


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

✓ All contract employees have been trained in the emergency signals used for notifying
employees in case of emergency.
✓ Contract employees have been trained in procedures for evacuation of the plant.
✓ Contract employees should be familiar with the locations of assembly points should any
emergency that require the plant to be evacuated.

5.11. MOBILE EQUIPMENT

✓ Contractor will ensure that all mobile equipment (forklift, cranes, vehicles, etc.) will be in
good condition and working properly. Fire extinguisher should be provided in each unit.
✓ A proof of certification training copy for employees operating forklifts, cranes or other
heavy equipment will be given to Safety Department.
✓ Contractor will provide valid driver’s license for contract employees who will be driving
vehicles within SWCC.
✓ Traffic Rules and Regulations should be observed inside the premises.

5.12. EXCAVATION

✓ Contractor will evaluate excavation conditions (soil type / work area) and familiarize
employees with working conditions and any potential hazards that may occur.
✓ In applying an excavation permit the area should be detailed.
✓ Contractor will provide qualified person to conduct daily inspections of excavation area,
soil condition, and any shoring equipment if used.
✓ Contractor will contact SWCC project coordinator immediately should any underground
facilities or other unexpected conditions to be encountered.
✓ If evidence of possible cave-ins or slides should occur, the contractor will stop the work
immediately and construct the proper shoring supports to protect employees.
✓ Contractor will barricade and provide adequate lightings in the excavation area and identify
the hazards present with safety sign.
✓ Contractor will provide a ladder or steps for employees to enter and exit excavation area
when excavation area is deeper than 1.2 M (4 ft.).

5.13. DEMOLITION

✓ Contractor will meet with SWCC project coordinator prior to working to review operating
procedures and demolition requirements.
✓ In applying demolition permit the area should be detailed.
✓ Contractor will ensure that all utilities (gas, water and electricity) have been shut off and
placed in a ZERO POTENTIAL ENERGY STATE before starting to work.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

✓ Contractor will place barricade tape around the demolition work area and hang safety signs
identifying “DANGER – DO NOT ENTER”.
✓ Contractor will ensure that surrounding areas, adjacent structures and equipment are
protected from demolition operations or debris.
✓ Contractor will install bracing to stabilize walls, vessels or other structures should be
demolition work require.
✓ Contractor will ensure that his employees are wearing proper personal protective
equipment for demolition operations (hard hat, safety shoes, goggles, ear plugs, respirators
heavy gloves and full body harness).
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

6. CONTRACTOR ACKNOWLEDGEMENT

I, the undersigned, employee of _________________________________________ passed the


Safety Orientation conducted by Fire and Safety Department concerning the items contained within
the SWCC “Contractor Safety Orientation Program” and fully understands of all the contents and
instructions given to me.

Standing Instruction No. P-037”, was also given to me along with its attachment namely
“CONTRACTORS SAFETY GUIDELINES”.
I agree to review the above information with my subordinates of all Safety Policies and Procedures
requirements covered in these Guidelines and understand that any violators of Safety Rules will
not be admitted within the SWCC plant.

CONTRACTOR REPRESENTATIVE:

Name: Suhail nanaah Position: BCC'S Civil Engineering

Date: 27/8/2022 Signature:

SWCC SAFETY INSTRUCTOR:

Name: Position:

Date: Signature:
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

7. SAFETY ORIENTATION ATTENDANCE SHEET

As an employee of ___________________________________________________ I have passed the Safety


Orientation conducted by Fire and Safety Department concerning the items contained within the SWCC
“Contractor Safety Orientation Program” and fully understands of all the contents and instructions given to
me.

As a contract employee, I promised to abide all SWCC Safety Policies and Procedures and agree to receive
any disciplinary action(s) including expulsion of SWCC plant, if the Safety Policies and Procedures will be
violated.

# Name SIGNATURE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

CONTRACTOR REPRESENTATIVE: SWCC SAFETY INSTRUCTOR:


Name: Name:

Date: Date:

Signature: Signature:
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

CHAPTER-2
CONTRACTORS SAFETY GUIDELINES
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

1. SWCC SAFETY REGULATIONS

1.1. Each contractor who is engaged by SWCC to perform any type of work at any of SWCC facilities shall
be given a copy of STANDING INSTRUCTION No. P-037 along with its attachments “SAFETY
ORIENTATION PROGRAM” (Appendix-A) and “CONTRACTOR SAFETY GUIDELINES” (APPENDIX-B).
1.2. Each contractor shall receive instructions on his Safety obligations prior to the start of any activities
undertaken at SWCC premises.
1.3. The Fire & Safety Department shall give Safety Instructions as part of the “SAFETY ORIENTATION
PROGRAM” to the Principal Manager and/or Site Supervisor of the contractor and to such other
personnel that the Manager and Supervisor shall select.
1.4. The Safety Instructions shall be given in English or Arabic Languages. Knowledge of one of these
languages by the contractor personnel attending these instructions is mandatory. A copy of Safety
Orientation Program in English and Arabic Languages shall also be provided by SWCC Fire & Safety
Department.
1.5. Each contractor shall be made responsive to the SWCC SAFETY PRINCIPLES AND GUIDELINES which
shall be followed in letter and spirit during the tenure of their work activities at SWCC premises.
1.6. Duties and function of SWCC Safety Organization in relations to the contractor’s activities and means
of contacts with Fire & Safety, Ambulance and other Emergency Services shall be discussed and
reviewed in particular.

2. SWCC REQUIREMENTS FOR PERMIT TO WORK

2.1. Each contractor shall be aware of the Permit To Work (PTW) System being followed at SWCC Plants
and appraised of the condition that if contract duration is one month or less, the PTW will be issued
to the relevant SWCC Authorized Person (AP) in charge of the work and the contractor will be
considered as working under the AP’s supervision.
2.2. If the Scope of work and contract duration exceeds one month period, the contractor Supervisor or
Foreman will be required to undergo test process for the appointment of Authorized Person prior
to commence the work, in accordance with clause III.7.10 of Permit to Work System (SO-7).
2.3. The Department responsible for the contractor’s activities shall nominate the contractor employee
for appointment as AP after satisfying themselves that the person concerned has the necessary
detailed knowledge of the Plant and equipment on which he is to work, as well as all relevant SWCC
and PTW Safety Rules. It will be the responsibility of the parent department to provide copy of
Permit to Work System (SO-7) to the contractor.
2.4. After passing the AP test, the person concerned will be issued with the AP License Card and will be
authorized to Receive, Clear and Suspend all Permit to Work (PTW) and Sanction for Test (SFT) in
the concerned area.

3. CONTRACTOR SAFETY ORGANIZATION

3.1. MANAGEMENT:
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

3.1.1. The contractor’s Project Manager is directly responsible for compliance with
provisions of this Safety Manual and for execution of all items contained in the
contractor’s Safety Plan.
3.1.2. The contractor Project Manager shall monitor the work plan and issue directives and
delegate authority required for its safe and efficient execution.
3.1.3. The Project Manager shall sign a pledge that he will inform and instruct his
subordinates under his supervision of all existing SWCC Safety Rules, Guidelines and
Regulations. An example of the pledge is illustrated in Figure 1.1.
3.1.4. Coordination and cooperation shall be established and maintained with other
contractors sharing the same work location(s) or adjacent area(s) to assure a project-
wide safe environment.

3.2. SAFETY REPRESENTATIVE

3.2.1. The Contractor Foreman / Supervisor shall also act as “Safety Representative” who
shall be responsible for routine implementation of the SWCC Safety requirements. He
shall carryout daily safety inspection at the worksite.
3.2.2. All routine Safety matters shall be coordinated through the contractor Safety
representative.
3.3. SUPERVISORS / FOREMEN

3.3.1. The contractor’s Supervisor / Foreman shall be responsible for Safety Conduct and
work practices of the workers.
3.3.2. The contractor Supervisor / Foreman will be required to undergo test process for the
appointment of “AUTHORIZED PERSON” prior to commence the work, if the work
duration is more than a month. This is required to qualify him to Receive, Clear and
Suspend Permit to Work in the concerned area.
3.3.3. The Supervisor / Foreman shall execute provisions of the Safety Plan as detailed in
section III.a.1 above.
3.3.4. The Plan shall provide such Safety Training as required to perform the work in a safe
and efficient manner. Safety training may also be given by the Safety Representative or
Training Officer. This shall not relieve contractor’s Site Officials responsibility for
assuring that workers conduct themselves in a safe manner and employ safe work
practices.

3.4. EMPLOYEE

3.4.1. Each contractor employee shall be given safety instructions by his employer on, or
prior to, his first day at work site.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

3.4.2. The employee shall abide by all the safety training, instructions rules and all follow-
up supervision from his Supervisor / Foreman.
3.4.3. He shall not engage in any activities which may endanger a fellow worker or SWCC
proprietary or is contrary to SWCC Safety and General Rules & Regulations.
3.4.4. Orientation & Training requirements are mandatory for all tasks, including those in
Confined Spaces, Handling Toxic Materials, Ionizing Radiation, Explosives, Flammable
Liquids & Gases and other similar hazardous materials handling.

4. CONTRACTOR SAFETY REQUIREMENTS

4.1. GENERAL SAFETY REQUIREMENTS

It is the responsibility of contractors to comply with the requirements of Safety Standard or


Procedures in practice at SWCC Plants. Procedures referred herein are recommended for
inclusion in contractor plan. Copies of procedures are available at SWCC offices.

4.2. CONTRACTOR SAFETY PLAN


4.2.1. Within thirty (30) days of Notice of Contract Award, contractors are required by
contract to submit a uniform Safety Plan to SWCC Management for approval. Written
approval will be given by SWCC or additional details requested to complete the Plan.
4.2.2. The Plan shall conform to Contractors Safety Plan Outline as indicated in Figure 1.2.
The Plan will form the basis for the Contractor’s Safety Program including employees
Safety training.

CONTRACTOR’S SAFETY PLAN


SAFETY POLICY, ORGANIZATION AND PROGRAM SAFETY INSTRUCTIONS, EDUCATION & TRAINING
- Policy - Safety Instructions for Employees
- Organization - Safety Meetings
- Safety Program - General Training Program
- Specific Safety Training Program
MEDICAL & EMERGENCY SERVICES INSPECTION
- General Requirements for Medical Care - Job Site Safety Inspection
- Medical Station, Equipment and Supplies - Safety Inspection of Manual Hand Tools
- Doctor, Hospital & Ambulance Services - Safety Inspection of Powered Portable Hand
Emergency Transportation Tools
- First Aid - Equipment Machinery Safety Inspection
- Medical Support - Facility Safety Inspection

Figure 1.2 – Contractors Safety Plan Outline


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

4.3. EMPLOYEES SAFETY HANDBOOK

4.3.1. In addition to the Safety Plan, the contractor shall prepare and submit for approval
an Employee Handbook which shall be issued to each employee before he begins to
work. The Safety Handbook shall contain the contractor’s Safety policy, rules for safe
conduct of employees and regulations on safe work practices.
4.3.2. The Arabic Translation of the Safety Handbook (if required), is the responsibility of
the contractor and must be approved by SWCC.
4.3.3. After reviewing the Handbook, each employee must sign a duplication sheet which
states that he received, reviewed and understood and agrees to abide by the rules. One
copy of the signed sheet shall be retained by the contractor’s Safety representative and
the other shall be retained by the employee until the completion of the work.

4.4. CONTRACTOR SAFETY MEETINGS


Each contractor shall hold Safety Meetings as outlined in Section (4.5) to (4.7) below and
maintain a record of agenda and attendance.

4.5. DAILY TOOL BOX MEETINGS


Daily Tool Box Safety Meeting shall be conducted by the contractor Foreman / Supervisor
at job site prior to start of work.

4.6. WEEKLY EMPLOYEE SAFETY MEETINGS


Weekly employee’s Safety Meetings are required to be held by the contractor Foreman /
Supervisor with compulsory attendance of all workers. It is recommended that the
meetings be organized as follows:
i. Review safety topics covering any accident and near misses during preceding week with
corrective actions to prevent the same.
ii. Discussion of any anticipated Safety hazard in work schedule during the coming week.
iii. Specific crew Safety matters and the required protective action by the employee or his
Supervisor / Foreman.

4.7. MONTHLY SAFETY MEETINGS


Monthly Safety Meetings attended by the contractor Foreman / Supervisor and periodic
staff is required. Minutes of Monthly Safety Meeting along with the attendance sheet shall
be provided to SWCC Fire & Safety Department. The agenda of each meeting shall include
the following items:
Review the contractor’s accident record since the last meeting and the corrective actions
taken to prevent recurrence.
i. Review of Safety Inspection conducted by the contractor and SWCC Safety personnel since last
meeting.
ii. Review of the potential hazards and required accident prevention actions.
iii. Discussion on the Foreman / Supervisor’s Safety problems & suggestions.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

5. EMPLOYEES SAFETY TRAINING

5.1. It shall be one of the contractor’s principal responsibilities to develop and provide formal
and comprehensive safety training programs for the employees who perform, including
follow-up supervision to assure that workers comply with safety training they have
received. Statistics indicate that approximately 10 % of all job related accidents are caused
by unsafe conditions such as faulty or defective equipment, while 90 % result from unsafe
act of workers. Consequently, the majority of job-site injuries, accidents and near misses
are caused by the inattention of the concerned persons.

5.2. Before adequate safety training program can be developed, contractors shall determine by
task analysis the following information:

5.2.1. Specific work the employee will perform.


5.2.2. Hazard(s) associated with the work.
5.2.3. Engineering control which can eliminate or minimize the hazard(s).
5.2.4. Safety equipment required if engineering control cannot be accomplished, Personal
Protective Equipment (PPE) i.e., eye protection, face shield, hard hats, safety shoes,
respirator etc.
5.2.5. Safety work practices required by employees themselves and other personnel in the
area irrespective of their employer and protection of SWCC proprietary.

5.3. The contractor shall take the opportunity to consider alternative solutions without any
shortcut or bypassing of Safe working practices to resolve job safety hazards revealed by
the work task analysis such as:
5.3.1. Finding an entirely new way to do the task
5.3.2. Changing the physical conditions that create the hazard(s)
5.3.3. Changing the procedure for performing the task
5.3.4. Trying to reduce the necessity of doing the hazardous task, or at least, the frequency
that it must be performed.

5.4. When all factors of task as outlined in (2) and (3) above have been considered, general and
specific safety training programs shall be formulated and presented.
5.5. Follow-up training shall be accomplished through continuous monitoring by the Supervisor
of employee work practices to enforce and emphasize the safety training they received.
5.6. Supervisor / Foreman shall correct immediately any unsafe work practices or job conditions
note during follow-up training which could cause accidents.
5.7. Orientation & Training requirements are mandatory for all tasks, including those in Confined
Spaces, Handling Toxic Materials, Ionizing Radiation, Explosives, Flammable Liquids & Gases
and other similar hazardous materials in handling and operations.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

5.8. The Saudi Arabian Government requirements for vehicle and other machinery operation to
have valid Driver's License / Operator’s Permit will be mandatory respectively.

6. ACCIDENTS AND MEDICAL CARE

A. It is a requirement of the Safety Manual that each accidental occurrence involving any of
the accidents to be discussed in clause (6.i) to (6.iv) below be investigated to determine the
cause.
B. It is also a requirement of the Safety Manual that preventive actions shall be taken to
prevent recurrence of the accidents.
C. Record and report of all such accidents shall also be available to SWCC authorities for
review.

6.1. FATALITIES

A. For on duty fatalities, the contractor shall investigate injuries received as a consequence of
occupational related hazards and exposures regardless of the length of time between the
occurrence and death.
B. The contractor shall investigate all fatalities of persons other than his employees whose
deaths are apparently related to contractor activities.

6.2. SERIOUS INJURIES

A. A serious injury is defined as an injury that results in hospitalization of the victim for more
than 24 hours for other than observation of diagnostic purposes. Hospitalization may occur
at any time, regardless of the length of time between the occurrence and hospitalization.
Hospitalization may occur at any place whether in the Kingdom of Saudi Arabia or other
country.
B. The types of serious injuries that shall be investigated are outlined below:
C. Contractor employee occupational and off-duty injuries
D. Injuries of persons other than the contractor employees in which the serious injuries are
apparently related to contractor’s activities.

6.3. EMPLOYEES LOST WORKDAY CASE

A. The contractor shall investigate all employees lost workday cases due to occupational
injuries. This is generally defined as any occupational injury that results in more lost
workdays away from work or work day(s) of restricted activities.
B. The contractor shall investigate all employees lost workday cases which are the result of
other accidents or fire involving contractor’s worksite, equipment, machinery or vehicle
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

failure or breakdown, material shortage or employees disputes or strikes etc which results
in more lost workdays away from work or work day(s) of restricted activities.
6.4. SPECIAL INVESTIGATION OF ACCIDENTS

A. Whenever unusual, catastrophic, multiple fatalities or multiple serious injuries occur at


contractor’s worksite or involving contractor’s activities, an independent investigation of
the accident shall take place.
B. The investigation shall be conducted by a committee consisting of at least three groups (of
one or more members); one group shall be supplied by SWCC Fire & Safety Department
and one group by the contractor. SWCC reserve the right to appoint the third group.
C. These investigations shall be independent of the investigation carried out by outside
agencies such as High Command Committee, Governmental Agencies, Civil Defense
Authorities or Underwriters Agencies.

6.5. ACCIDENT REPORTING

A. Any accident related to contractor’s activities, resulting in personnel Injury, Damage to


SWCC Property or Production Loss (irrespective of its magnitude) must be reported
promptly to SWCC Fire & Safety Department.
B. Accidents / Injuries resulting in fatal or serious injuries shall immediately reported by the
contractor to SWCC Fire & Safety Department by telephone. Immediate notification of the
incident by telephone shall also be made by the contractor to SWCC Security.
C. The verbal information of the incident shall be followed by written notification of the
accident / injury on the prescribed form.
D. Within 5 days of the closing of each Gregorian month, the contractor will provide the SWCC
Fire & Safety Department a summary of job related accidents and injuries of the preceding
month. Injuries shall be reported on the form provided and all sections of the form shall be
completed

6.6. ACCIDENT INVESTIGATION REPORT FORMS

A. The contractor shall investigate, record and report investigations of all accidents and
injuries.
B. When an accident occurs, a preliminary accident report (Form PS- 01) is to be, immediately,
submitted to SWCC Fire and Safety Department and a detailed report is to be submitted
within three days of the accident.
Note:

The Report Form does not replace but is in addition to “NOTICE OF EVENT, OCCURRENCE OR LOSS” or other
similar forms required by the Insurance Brochure & Claim Procedure Manual which is issued by the Insurance
Agency.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

6.7. MEDICAL FACILITIES

A. The contractor is responsible for providing medical care as required by the laws of the
Kingdom of Saudi Arabia and SWCC.
B. Each contractor is responsible in providing, or have arranged to provide, all necessary First
Aid and Medical care to any of their injured or ill employee.
C. If applicable, the contractor shall also provide similar facilities for each of their sub-
contractors and low-tier sub-contractor.
D. Available services (for example, Ambulance and Emergency Medical Services etc.) shall be
arranged with any emergency hospital administration office in the locality.

7. RULE OF CONDUCT & SAFETY REGULATIONS

7.1. ENTRY INTO SWCC FACILITIES

A. Contractor personnel shall comply with SWCC Safety Rules when they are, in the course of
work, required to enter SWCC premises or facility.
B. Additional Safety controls as required by SWCC shall be observed for the protection of
personnel and property.
C. No contractor employee shall leave his place of assignment and found in areas where his
presence is not required.

7.2. RULE OF CONDUCT

A. All personnel are required to adhere to all Rules of Conduct relating to Job Safety and Safe
Working Practices while on SWCC project job site.
B. Personnel are required to observe the Rule of Conduct while absent from the jobsite in
performance of work.

7.3. PERMISSION TO WORK

A. No work of any type or nature is allowed to be commenced or continued without issuance


of a valid written permission referred to as “PERMIT TO WORK” at any SWCC facilities.
B. Each contractor shall follow PERMIT TO WORK SYSTEM with special reference to the
following clauses:
i. If contract duration is one month or less, the PTW will be issued to the relevant SWCC
Authorized Person (AP) in charge of the work and the contractor will be considered as working
under the AP’s supervision.
ii. If the Scope of work and contract duration exceeds one month period, the contractor
Supervisor or Foreman will be required to undergo test process for the appointment of
Authorized Person prior to commencement of the work, in accordance with clause III.7.10 of
Permit to Work System (SO-7).
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

7.4. WORK DRESS STANDARD

A. All contractor personnel shall wear clothing appropriate to the individual work assignment
and be in accordance with a work dress standard established by the employer.
B. The contractor work dress standard shall contain the following rule:
i. Excessively loose or severely torn clothing shall not be worn especially by those whose work
exposes them to machines such as rotating or reciprocating equipment, band and table saws
or other moving parts.
ii. Shirts with short sleeves are preferred but long sleeves shirts may be worn during working
hours.
iii. Wearing of “THOBE” at job-site is not allowed.
iv. Wearing of shorts or pants with cut off legs is prohibited.
v. Sandals shall not be worn during working hours at any work location.
vi. Contractor persons are required wearing of Safety or other suitable clothes consistent with
type of work being performed.

7.5. PERSONAL PROTECTIVE EQUIPMENT

A. The contractor shall provide to the workers of the required personal protective equipment
i.e. Coverall, Safety Shoes, Safety Hat, Safety Glasses, Face Shield, Ear protection,
Respirators, Masks and Full Body Harness etc., depending on the nature and location of
their job.
B. Where conditions apply, wearing of Personal Protective Equipment by the contractor
workers is mandatory.
C. Personal Protective Equipment shall conform to the Industrial Safety Standards set by
SWCC.
D. Employees shall be instructed by the contractor on how to use the Personal Protective and
Safety Equipment.

7.6. WORKSITE SAFETY INSPECTION

A. Daily Safety Inspection of the contractor worksite by the contractor Safety representative
is required.
B. Monitoring of Site Safety operations by SWCC Fire & Safety Department and other SWCC
Authorities will be performed.
C. Weekly report of contractor safety inspection shall be maintained in the contractor’s Safety
File for review.

7.7. EQUIPMENT INSPECTION, O & M AND REPAIR


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

Safety requirements regarding equipment inspection, operation, maintenance and repair shall
be discussed with SWCC concerned Department and agreed upon in writing, prior to their
execution.

7.8. REPORTING UNSAFE CONDITIONS

A. In order to maintain a safe working environment, contractor shall inform his employees
that everyone is responsible for informing his Foreman / Supervisor of all acts and
conditions that may cause injuries or damage to equipment / property.
B. The contractor Foreman / Supervisor, who also functions as Contractor’s Safety
Representative, shall report any unsafe condition(s) and potential hazards to SWCC Fire &
Safety Department.

7.9. REPORTING INJURIES AND PROPERTY DAMAGE

A. The contractor shall inform his employees that everyone is responsible to report each
occupational injury promptly to his Foreman / Supervisor to ensure that proper and
adequate medical attention is obtained.
B. All accidents that result in injury to one or more persons irrespective of their employer such
as private vehicle drivers, passengers, pedestrians or jobsite visitors shall be reported
promptly to the contractor Foreman / Supervisor.
C. All accidents that result in damage to any Constructed or Partial Constructed Facility,
Process Equipment, Private or Public Property shall be reported promptly to the contractor
Foreman / Supervisor.
D. All occurrences in which serious injury or serious property damage was prevented by
fortuitous circumstances or deliberated preventive action shall be reported promptly to
the contractor Foreman / Supervisor.
E. The contractor Foreman / Supervisor, who also functions as Contractor’s Safety
Representative, shall immediately notify SWCC Fire & Safety Department on all the above
occurrence.
F. The contractor Foreman/ Supervisor must prepare a monthly Safety Report signed by
SWCC Project Engineer and submit it to SWCC Fire & Safety Department within the first
working week of the new month (Form PS-02).

7.10. PERSONAL CONDUCT

A. Indulgence in practical jokes, horseplay, scuffling, wrestling or fighting is forbidden within


SWCC premises.
B. Destroying or tempering with Safety Devices, Signs and Signals or willfully and
unnecessarily discharging Fire Extinguishing Units are prohibited.
C. Sleeping on the site is strictly prohibited.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

D. Wandering around in areas other than jobsite is not allowed.


E. Smoking or use of open flame in areas of ‘NO SMOKING’ is prohibited.
F. Carrying of matches, cigarette lighters and other source of ignition in all fuel or gas areas
where such items are a hazard shall cause for disciplinary action.
G. Observance of Road Traffic Rule and Regulations within SWCC premises is mandatory.
H. Contractor employee shall promptly report all observed unsafe and potentially hazardous
condition to their Foreman / Supervisor so that timely corrective action can be taken to
prevent injuries or damage.
7.11. INSUBORDINATION

A. Noncompliance toward any Supervisor in respect to carrying out properly issued


instruction or orders for Safety purposes shall be sufficient cause for initiating disciplinary
action against offender(s) in accordance with established disciplinary procedures.
B. A copy of any disciplinary action initiated by contractor against violation of safety rules and
regulations of his employee(s) shall be sent to SWCC Fire & Safety Department for record
and follow-up.

7.12. DRUG POSSESSION AND USE

A. The possession or use of illegal narcotics or intoxicants is a serious crime in the Kingdom of
Saudi Arabia.
B. An employee whose action or demeanor indicate symptoms of possible use of narcotics or
drunkenness shall be subjected to an examination by contractor’s medical unit or shall be
offered evacuation to the nearest employer’s designated medical facility for such
examination.
C. Refusal to cooperate shall render in removal of the employee from the jobsite.
D. Proof of possession or use of illegal narcotics or intoxicants shall result in immediate
expulsion of the concerned person from the project.
E. Drug violations or suspected drug violations shall be immediately reported to SWCC
Security.

8. SPECIFIC TASKS

8.1. SPECIAL SKILLS AND PROTECTIONS

8.1.1. Orientation, Training and requirements of special skills are mandatory for contractor
workers for all specific tasks e.g.

A. Work inside the Confined Spaces.


B. Diving and Underwater Repairs.
C. Stack Climbing and Work at Large Heights.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

D. Handling of Toxic Materials.


E. Use of Explosive.
F. Handling of Flammable Liquids and Gases
G. Working on Fiber Glass Material
H. Other similar Hazardous Material Handling and Operations
8.1.2. Special precautions and protective measures shall be adopted in executing these
tasks in accordance with the set rules of the safety and safe practices.

8.1.3. SWCC Fire & Safety Department shall be informed in advance by the contractor about
such activities with the location and estimated duration of tasks.

8.2. WORK WITH IONIZING RADIATION

8.2.1. All contractor work involving use of radioactive nuclear sources and X-ray machines
shall conform to Radiation Safety Standards.
8.2.2. Copies of Radiation Safety Standard shall be provided by the Health Services
Department to Health Care and other contractors who employ X-ray machines and
any radioactive nuclear sources on or about premises of facilities under contractor
control.
8.2.3. Use of X-ray or nuclear source machines or equipment shall conform to Radiation
Safety Standards.
8.2.4. Contractors who have occasion to use X-ray or nuclear source equipment shall notify
the Health Services Department at least 10 working days prior to schedule delivery
of each X-ray or nuclear source. The notice shall include a copy of the Saudi Arabian
Government permit to use such material, details of planned storage, and use, and the
name of the person responsible for its care, custody and control. Upon receipt of
notice of delivery, the Health Services Department shall provide a copy of Safety
Standards to the contractor.
8.2.5. The Project Manager under whose jurisdiction X-ray or radioactive nuclear source will
be used shall convene a meeting with responsible contractor, Medical Services
Department personnel and Fire & Safety representatives and others who will be
involved with the operation. At this meeting, the contractor shall present for
approval, plans for X-ray or radioactive nuclear source use accompanied by Safety
Measures to be employed based on the Radiation Safety Standard.
8.2.6. During the use of X-ray or radioactive nuclear source equipment the affected
surrounded area as determined by the intensity of the radiation source and
mentioned in Safety Measures of the source, shall be barricaded / cordoned-off with
WARNING Signs and monitored by Medical Services and Fire & Safety Department to
assure contractor compliance with Radiation Protection Standards.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

8.3. ENVIRONMENTAL PROTECTION

8.3.1. Releasing or discharging in any form, type or amount of Toxic substances which are
hazardous to the environment is absolutely prohibited in the Sea, Land or Air without
prior approval of Environmental Protection Agency (EPA) and agreement of SWCC
Management.
8.3.2. All approved discharge of such substances shall be carried out as “CONTROLLED
RELEASE” under the direct supervision of SWCC in accordance with the limits and
standards set by the Environmental Protection Agency
8.3.3. Any accidental release of such substances or discharge of any type of Oil in the sea
by the contractor personnel MUST IMMEDIATELY reported to SWCC Fire & Safety
Department to prevent any further damage to the Process Cycle of SWCC Plant.

9. DEMOLITION AND CONSTRUCTION

In order to provide Supervision and review of any demolition that is carried out by SWCC
employees or by the contractor engaged by SWCC, following working practices and guidelines
shall be followed:

9.1. DEMOLITION COORDINATOR

9.1.1. Before demolition work starts, an experienced and skilled person having demolition
knowledge shall be appointed as “DEMOLITION COORDINATOR” by SWCC in writing
as the person in charge of that particular job.
9.1.2. The Coordinator shall directly supervise the work force, ensuring that PERMIT TO
WORK requirements are met, and liaise with other contractor(s) and SWCC
employees in the general area to the site to minimize disturbances.

9.2. ORIGINAL DRAWINGS

9.2.1. The original Drawings of the structure to be demolished shall be obtained.


9.2.2. An examination shall be made to determine if any changes to the original
construction have been made to the structure or if any part of the structure has been
adversely affected by rot, corrosion, subsidence or other demolition work.

9.3. DEMOLITION / EXCAVATION PERMIT

A PERMIT TO WORK along with Excavation / Demolition Permit (Form O-3) shall be required in
accordance with clause III.3.13.5 of PERMIT TO WORK SYSTEM (SO-7) prior to execution of any
Excavation / Demolition activity.

9.4. UTILITIES AND INPUT / OUTPUT CONNECTIONS


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

All utility services such as Electricity, Gas, Water and other Process related supplies shall be
shutoff and then disconnected outside the line of demolition work.

9.5. SITE PROTECTION

9.5.1. Adjacent structures shall be protected from debris and where necessary, bracing shall
be installed to ensure their stability.
9.5.2. Barricades shall be erected around the work area.
9.5.3. Signs bearing words in bold 6 inches red or black on yellow background shall be
erected at frequent intervals at the approach points to the barricade. The wording on
the signs is detailed below:
Sign-2 shall read Sign-1 shall read

DANGER! DANGER!
DEMOLITION
IN DO NOT
PROGRESS ENTER

9.6. METHOD OF DEMOLITION

9.6.1. The method of demolition to be used shall be determined by consultation with the
SWCC representative and the representatives engaged in the demolition work. The
re-use of salvage material shall be considered prior to this decision.
9.6.2. During consultation, it shall be recommended that the safest and most efficient
method to demolish a structure is to start at the top working towards ground level.
There are, however, cases where such a method is impractical or uneconomical and
where other methods have to be considered.

9.7. STABILITY DURING DEMOLITION

9.7.1. As work progress, continuing inspections shall be made to detect hazards arising
through weakened or overloaded floors, unsupported walls or loose material.
9.7.2. Should the inspection in (a) above detect a weakness or overload, immediate steps
shall be taken by bracing or by other means to prevent the premature collapse of the
whole or any part of the structure.

9.8. WORKING PRACTICES

9.8.1. A safe mean of access to and passage from all workplaces shall be provided.
9.8.2. Workplaces and areas around ladders and stairways shall be kept clear of material
and debris.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

9.8.3. Nails in timber shall be removed or bent over or the timber stacked where it will not
be a source of danger.
9.8.4. All glass windows, doors, partitions etc., shall be completely removed prior to
structural demolition.

9.9. STRUCTURAL STEEL DEMOLITION

9.9.1. All steel constructions shall be demolished column length by column length and tier
by tier.
9.9.2. A structural member being removed shall not be under any stress other than that its
own weight.
9.9.3. Members being cut or dismantled shall be chained or lashed in place to prevent
uncontrolled swing or dropping.

9.10. TANKS VESSELS AND PIPE WORKS

9.10.1. ADVICE ON VOLATIZING TANKS AND VESSELS


A. All vessels, tanks and pipe-work which contain or had to be contained any type of oil, fuel
or any other volatile materials must be emptied and evacuated of all the residues and
vapors prior to its demolition. For vessels and tanks of about 6,000 gallons capacity, both
vapors and residues can usually be removed by steaming out but due to high heat capacity
of large tanks, steaming out can not be relied on to volatize all residues.
B. It is relatively easy to eliminate explosive concentration of vapors within the large tanks,
vessel or pipe-work by forced ventilation using large blowers or ejector system. This
method will rapidly reduce the vapor concentration. With material less volatile, the main
dander lies in the hot cutting causing fire to any residues in the tank. It is therefore
essential that the residues are removed before work starts.
C. The risk of explosion or fire during hot cutting work can be practically eliminated by using
cold cutting techniques. Although, often more costly and laborious, it may prove to be
the only safe method.

9.10.2. DEMOLISHING TANKS AND VESSELS


A. No tank, vessel or pipe-work which contained any explosive of flammable material shall
be subjected to any welding or hot cutting techniques until all steps have been taken to
remove or make safe of the substances and any fumes.
B. No tank vessel or pipe-work shall be subjected to any demolition activity unless it is at
ZERO pressure and certified not having any toxic or explosive contents.
C. When hot cutting is planned, the advice of SWCC Fire & Safety Department shall be
sought.

9.11. PROTECTIVE CLOTHING AND EQUIPMENT


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

9.11.1. All demolition workers shall be provided with and make use of the following
protective equipment:
A. Safety Helmet
B. Eye Protection (Safety Goggles)
C. Ear Protection (Ear Plugs)
D. Heavy Duty Gloves
E. Face Masks or Respirators, whenever necessary to prevent inhalation of dust and fumes
F. Safety Shoes and Protective clothing
G. Full Body Harness, with lifelines where required, shall be used by men working in
isolated or dangerous locations where there is a possibility of them falling and where
other preventive measures are impractical.

9.12. MECHANICAL EQUIPMENT

9.12.1. Mechanical equipment such as cranes and dozers shall be equipped with wire mesh
guards over windows and with a solid protection over the driving position so that
there is no danger of operator being struck by flying debris
9.12.2. The Basic Safety Rules for all ladders or scaffolding use for the purpose of demolishing
etc., shall apply.
9.13. USE OF EXPLOSIVES

Use of explosives for any demolition purpose shall be in accordance with Laws of the Kingdom of
Saudi Arabia and adherence to all Rules and Regulations in this regard are mandatory. Use of
explosives will only be allowed after proper planning for execution and with the approval of the
competent authorities.

10. ENCROACHMENT TO SWCC FACILITIES

Refer to SWCC approved “ENCROACHMENT APPLICATION /PERMIT SYSTEM” (SO-100) to


provide general guidelines to any outsider / SWCC contractor who wants to encroach into SWCC
facilities and to ensure proper documentation and updating of changes in as built drawings
caused by the encroachment.

11. OTHER REGULATION

All other regulations not mentioned in this handbook shall be referred to the existing Safety
Rules & Regulations of SWCC.
‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

FORM CS -01
DETAILED REPORT REQUIRED WITHIN 3 DAYS Reference Number:
Accident Location Date of Accident Time of Accident

Company Personnel Injured ID Number

Type of Injuries: Property Damage and Estimated Cost Damage:

Description of Accident:

Witness Statement(s)

What Caused The Accident:

What Corrective Action Has Been Taken

Name:______________________________ Signature: _________________________________

Job Title: ___________________________ Date: _____________________________________


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

FORM CS – 02
CONTRACTOR CONTRACT No.
PROJECT LOCATION
1. Work Injuries:
2. Fires:
3. Motor Vehicle Accidents:
4. Incidents Involving Damage To SWCC Equipment:
5. Crane, Heavy Equipment & Man-lift Accidents:
SAFETY MEETING:
(A) Topics Discussed:

1.
2.
3.
4.
5.
(B) Attendance:

(C) Instructor(s):

Contractor Representative Signature Date

SWCC Project Engineer Signature Date


‫كتيب السالمة للمقاولين‬ ‫المؤسسة العامة‬

Contractors Safety Handbook ‫لتحلية المياه المالحة‬

Industrial Security and Environment ‫اإلدارة التنفيذية لألمن الصناعي والبيئة‬

CONTRACTOR’S PLEDGE

I,_____________________________ with I.D. Card No._________________

of ____________________________ as a ___________________________

(Name of Company) (Position)

Do hereby pledge to inform and instruct my employees on all existing Safety Rules and Regulations in
Saline Water Conversion Corporation (SWCC).

I understand that violators of Safety Rules shall not be admitted within the SWCC Premises.

____________________________ ___________________________

Signature Date

c.c. Safety File Attachment: Copy of I.D. Card

You might also like