Professional Documents
Culture Documents
Week 4 Project Management Discussion Student Name Name of University Author Note Date
Week 4 Project Management Discussion Student Name Name of University Author Note Date
Student Name
Name of University
Author Note
Date
Week 4 project management discussion
Week - 4 Discussion
by Yijia Zhang - Tuesday, January 31, 2023, 4:24 PM
Number of replies: 1
1. Describe a potential timing issue that can occur early in a project and a potential
timing issue that can occur at the end of a project. How would you address each of these
issues in your project?
2. Describe a few normal causes and special causes of variation on a project you have
worked on. How did you address these variations?
A project is a one-time activity that is part of every company to successfully achieve profits
and improve productivity through product or service development. Generally in companies,
the project manager is essential for successfully managing the project plan, executing the
project, and controlling the loss or delay (Kloppenborg, Stamford). Normal and special
causes are two important variations in a project that are helped to complete the project on
time. In companies, common cause variation is involved in different factors which are
unnecessarily affecting the process variation (Gerardi, 2018). Special cause variation is the
process that is involved in more than a factor that is affecting the process variation in a non-
random manner.
References
Gerardi, J. (2018, February 13). Common Cause Variation vs Special Cause Variation.
Retrieved from Project Cubicle: https://www.projectcubicle.com/common-cause-variation-
special-cause-variation/
Ibironke, & Elamah. (1-9). Factors Affecting Time, Cost And Quality Management In
Building. School of Environmental Sciences, Federal University of Technology, 2011.
Describe a potential timing issue that can occur early in a project and a potential timing
issue that can occur at the end of a project. How would you address each of these issues
in your project?
Clarity on resource availability and timescales is required for project scheduling. It's a
detailed document that outlines the project timeframe as well as the organizational
resources needed to fulfill each task. One of the potential timing issues is the project
would not start on time. For example, the weather could have an impact on a
construction project. During the project, builders must consider rain, storms, natural
calamities, and extreme temperature variations. Because the factors are
uncontrollable, it is vital to include nature while planning and bidding on
construction projects. A potential timing issue that can occur at the end of a project
is project delay. Poor planning in terms of scope development and project execution
methodologies frequently causes project timeframe delays. Weather, environment
and unforeseen site conditions can cause a project to be delayed by days or weeks.
However, most delays come as a result of inadequate front-end planning at the start
of the project.
Describe a few normal causes and special causes of variation on a project you have
worked on. How did you address these variations?
References
Bowen, ME. & Neuhauser, D. (Apr 19, 2013). Understanding and managing variation: three
different perspectives. Implement Sci. 8(1).
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3633027/#:~:text=Common%2Dcause
%20variation%20is%20random,that%20are%20not%20random%20variation.
Kashi, S., Rozenes, S. & Ben-Gal, I.(Aug 18, 2020). Project Management Monitoring Based
on Expected Duration Entropy. Entropy (Basel). 22(8), 905.
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7517532/