Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 76.10 Sqm 240.00 18,264.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
11 12mmTHK Regular gypsum board bulkhead 200mm height 15.00 Lm 60.00 900.00
12 Gypsum Cornice 150x50mm 30.00 Lm 110.00 3,300.00
13 Access Panel -300x300mm - Qty As per actual MEP requirement 1.00 Pcs 120.00 120.00
Decorative Solid Wood fixed ceiling including all necessary accessories and
14 fixings to complete the work all in accordance with the issued specification, 1.00 Ls 5,250.00 5,250.00
drawings and to the satisfactory of Engineer
Supply and fixing of Sliding Wooden door , including all necessary
15 accessories and fixings to complete the work all in accordance with the 1.00 Ls 4,500.00 4,500.00
issued specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wooden door, including ironmongery all necessary
16 accessories and fixings to complete the work all in accordance with the 2.00 Ls 2,800.00 5,600.00
issued specification, drawings and to the satisfactory of Engineer
C Sun House Area
Flooring
Supply and laying of screeding /Self leveling concrete to level the floor for
1 15.00 Sqm 65.00 975.00
tile fixture
Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 15.00 Sqm 240.00 3,600.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
6 12mmTHK Regular gypsum board bulkhead 300mm height 5.00 Lm 65.00 325.00
Decorative Solid Wood fixed ceiling including all necessary accessories and
7 fixings to complete the work all in accordance with the issued specification, 1.00 Ls 5,250.00 5,250.00
drawings and to the satisfactory of Engineer
Supply and installation of solid wooden Pergola including all necessary
8 accessories and fixings to complete the work all in accordance with the 1.00 Ls 6,500.00 6,500.00
issued specification, drawings and to the satisfactory of Engineer
Supply and installation of Water Falling Stone Cladding, Dry fixing method
including all necessary accessories and fixings to complete the work all in
9 10.00 Sqm 285.00 2,850.00
accordance with the issued specification, drawings and to the satisfactory of
Engineer
9 12mmTHK Regular gypsum board bulkhead 200mm height 15.00 Lm 60.00 900.00
Supply and fixing of Wooden door, including ironmongery all necessary
10 accessories and fixings to complete the work all in accordance with the 2.00 Ls 2,800.00 5,600.00
issued specification, drawings and to the satisfactory of Engineer
E Driver room & Maid Room
Flooring
Supply and laying of screeding /Self leveling concrete to level the floor for
1 23.50 Sqm 65.00 1,527.50
tile fixture
Supply and Installation 600x600mm Floor porceline tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider 80Dhs/
2 and accessories to complete the work all in accordance with issued 23.50 Sqm 160.00 3,760.00 sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 80Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
Supply and apply of Jotun Fenomastic paint finish, including all necessary
3 accessories and fixings to complete the work all in accordance with the 75.00 Sqm 20.00 1,500.00
issued specification, drawings and to the satisfactory of Engineer
Supply and fixing storage unit with required shelf and necessary supports
4 fittings and accessories to complete the work all in accordance with issued 1.00 Nos 3,850.00 3,850.00
specification, drawings and to the satisfy to Engineer
Supply and Installation 300x300mm Wall porcelain tiles for Bath rooms Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider 80Dhs/
5 and accessories to complete the work all in accordance with issued 42.00 Sqm 160.00 6,720.00 sqm+
specifications, drawings and to the satisfy to Engineer Installation
Tile Price Consider 80Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 38.09 Sqm 240.00 9,141.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
8 12mmTHK Regular gypsum board bulkhead 200mm height 20.00 Lm 60.00 1,200.00
11 Access Panel -300x300mm - Qty As per actual MEP requirement 1.00 Pcs 120.00 120.00
Supply and fixing of Decorative mirror, including all necessary accessories
12 and fixings to complete the work all in accordance with the issued 2.00 Ls 3,250.00 6,500.00
specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wall hang mirror, wooden cover including all necessary
13 accessories and fixings to complete the work all in accordance with the 1.00 Ls 2,250.00 2,250.00
issued specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wooden Door, including all necessary accessories and
14 fixings to complete the work all in accordance with the issued specification, 1.00 Ls 3,850.00 3,850.00
drawings and to the satisfactory of Engineer
Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 22.55 Sqm 240.00 5,412.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 18.00 Sqm 240.00 4,320.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
8 12mmTHK Regular gypsum board bulkhead 200mm height 5.00 Lm 60.00 300.00
10 Access Panel -300x300mm - Qty As per actual MEP requirement 1.00 Pcs 120.00 120.00
Supply and fixing of Decorative mirror, including all necessary accessories
11 and fixings to complete the work all in accordance with the issued 2.00 Ls 3,250.00 6,500.00
specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wall hang mirror, wooden cover including all necessary
12 accessories and fixings to complete the work all in accordance with the 1.00 Ls 2,250.00 2,250.00
issued specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wooden Door, including all necessary accessories and
13 fixings to complete the work all in accordance with the issued specification, 1.00 Ls 3,850.00 3,850.00
drawings and to the satisfactory of Engineer
I Living & Corridor in First Floor
Flooring
Supply and laying of screeding /Self leveling concrete to level the floor for
1 35.00 Sqm 65.00 2,275.00
tile fixture
Supply and Installation 600x600mm Floor World Parquet tiles for flooring, Tile Cost
including all necessary fixing, cement mortar, grouting, tile adhesive, fittings consider
2 and accessories to complete the work all in accordance with issued 35.00 Sqm 240.00 8,400.00 160Dhs/ sqm+
specification, drawings and to the satisfy to Engineer Installation
Tile Price Consider 160Dhs/Sqm ( PC rate) 80Dhs/ Sqm
Wall Finishes
Wall Finishes
8 12mmTHK Regular gypsum board bulkhead 200mm height 10.00 Lm 60.00 600.00
10 Access Panel -300x300mm - Qty As per actual MEP requirement 1.00 Pcs 120.00 120.00
Supply and fixing of Decorative mirror, including all necessary accessories
11 and fixings to complete the work all in accordance with the issued 2.00 Ls 3,250.00 6,500.00
specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wall hang mirror, wooden cover including all necessary
12 accessories and fixings to complete the work all in accordance with the 1.00 Ls 2,250.00 2,250.00
issued specification, drawings and to the satisfactory of Engineer
Supply and fixing of Wooden Door, including all necessary accessories and
13 fixings to complete the work all in accordance with the issued specification, 1.00 Ls 3,850.00 3,850.00
drawings and to the satisfactory of Engineer
Exclusion :
01) MEP & Swimming Pool Work, Supply of lights are excluded
02) Supply of FF& E Furniture
03) The above mention work cost consider any changes as a variation