LEVEL - 3

DELIVERY & INSTALLATION STATUS


SL NO ACTIVITY DESCRIPTION REMARKS
DELIVERED INSTALLED
TOTAL QTY
QTY QTY

HINGES READY WITH HAFELE NOT RELEASING


1 ROOM ENTRANCE DOOR 37 37 22
DUE TO PAYMENT ISSUE

2 VENEER CLADDING 37 29 28 ROOM 33 1ST FIX ONGOING

3 WALL PAPER CLADDING 37 30 28 ROOM - 7, 16, 33, 31,32, 13,03 ONGOING

4 DB CARCASS WITH SHUTTER 37 30 27 2 OR 3 PANEL MISSING

5 LEDGE WITHOUT CURTAIN POCKET 14 14 14 ROOM 33 1ST FIX ONGOING

6 CURTAIN POCKET SHUTTER 14 9 5

7 TV UNIT 37 29 28 ROOM 33 1ST FIX ONGOING

WARDROBE & LUGGAGE RACK ROOM 13 & 15 MATERIAL NOT RECEIVED AND
8 37 28 24
CARCASS 31,32,33 & 34 INSTALLATION ONGOING

HEAD BOARD CLADDING (TOP &


9 37 28 27 ROOM 33 1ST FIX ONGOING
SIDE PANEL)

10 WALL PAPER DRY AREA 37 30 19 LPO ISUUED FOR FJ & DS ROOM FROM ASGC

11 WALL PAPER WET AREA 37 30 21 LPO ISUUED FOR FJ & DS ROOM FROM ASGC

12 FIRST FIX DRY AREA 37 37 32 5 ROOM INSTATTION ONGOING

13 FIRST FIX WET AREA 37 25 23 ROOM 18 & 37 UNDER REVIEW

FIRST FIX INSPECTION STATUS - DRY


14 37 NA 28 1 NOS UNDER REVIEW
AREA

7 ROOM FJ & DS NOT READY FRON ASGC


FIRST FIX INSPECTION STATUS - WET
15 37 NA 23 MARBLE WORK ONGOING AND 3, 33, 32 26
AREA AREA
ALSO NOT READY
9 NOS STANDARD ROOM AND 1 NOS DA . WE
16 VANITY MIROOR BACK PANEL 37 0 10 ARE USING THE MATERIAL DELIVERED FOR
6TH FLOOR

HINGES READY WITH HAFELE NOT RELEASING


17 CORRIDOR WOODEN DOOR FRAME 26 6 0
DUE TO PAYMENT ISSUE

HINGES READY WITH HAFELE NOT RELEASING


18 CORRIDOR WOODEN DOOR SHUTTER 26 14 0
DUE TO PAYMENT ISSUE