FPM 222 Checklist Plumbing

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 4

CHECKLIST

PLUMBING WORKS
Checklist No. Date:
Name of Work: Drgs Ref:
Employer:
Contract No.:
Contractor:
Item Dscrptn: Inspection Requested by: BOQ No.

1ST INSPECTION 2ND INSPECTION Mix Grade:


Req. on: Req. on:
Location Section Level By.: By.: Quantity
Date: Date:
Time: Time:
Points to Check O Action Req. O Action Req. REMARKS
P P
1. Dimensions, level & SIZE
2. No of inlets
3. Inlet & outlet level
MANHOLE

4. Inlet & out let pipe size


5. Manhole No
5. Man hole Cover Hevey /Med/Light
6 . Man hole for soil wast/ Rani water
7 Cleanliness
1. PIPE SIZE (300-250-200-160-110 )
2. Type of Pipe swr A/B Agri
2. Slop
PIPE

3 .Inlet Manhole PIPE Level


4. Out let Man hole Pipe Level
5. Intervel Bettven Two Mahole

1. Box Outs
2. Pipe Sleeves
3. Embedded Items
4. Quality of Bulk Materials / RMC
GENERAL

5. Plastisizers / Additives
6. Expansion Joint Provisions if any
7. Existing Concrete Hacking & Cleaning
8. Special treatments in existing surface
CLEARANCE

Engineer Contractor
Clearance for Concreting Clearance Date
Details of Additional Steel Provided if any: [Other than specified in Drg.] Pour Start Date & Time:
POST CONCRETING

Pour End Date & Time:


No. of Cubes Taken:
Average Slump:
Method of Pouring & Vibration Acceptable To Improve Arrangement for Curing / Ponding Acceptable To Improve

Stability of Formwork after Pour Acceptable To Improve Others [Specify] Acceptable To Improve

Line, Level & finishing Acceptable To Improve Acceptable To Improve

Sch. date for formwork removal with supports Actual Date of Removal
Sch. date for form work removal entirely Actual Date of Removal
Line, Level & finishing of Concrete surface Acceptable To Rectify Acceptable To Rectify
DESHUTTER

Removal of Battens, Maskin tape etc. Acceptable To Rectify Acceptable To Rectify

Action Required if any:- Remarks: Rectifications done as specified:

Dry finish
Wet finish
Grouting Task End Date:
Epoxy Treatment
Contractor: Resident Architect Client

TVH Studio Cria AWHO


PLUMBING WORKS

Checklist No. Date:

Name of Work: Drgs Ref:


Employer:
Contract No.:
Contractor:
Item Dscrptn: Inspection Requested by: BOQ No.

1ST INSPECTION 2ND INSPECTION Mix Grade:


Req. on: Req. on:
Location Section Level By.: By.: Quantity
Date: Date:
Time: Time:
Points to Check O Action Req. O Action Req. REMARKS
P P

1. Dimensions, level & SIZE


2. No of inlets
3. Inlet & outlet level
MANHOLE

4. Inlet & out let pipe size


5. Manhole No
5. Man hole Cover Hevey /Med/Light
6 . Man hole for soil wast/ Rani water
7 Cleanliness
1. PIPE SIZE (300-250-200-160-110 )
2. Type of Pipe swr A/B Agri
2. Slop
PIPE

3 .Inlet Manhole PIPE Level


4. Out let Man hole Pipe Level
5. Intervel Bettven Two Mahole

1. Box Outs
2. Pipe Sleeves
3. Embedded Items
GENERAL

4. Quality of Bulk Materials / RMC


5. Plastisizers / Additives
6. Expansion Joint Provisions if any
7. Existing Concrete Hacking & Cleaning
8. Special treatments in existing surface
CLEARA
NCE

Clearance for Concreting Engineer Contractor


Details of Additional Steel Provided if any: [Other than specified in Drg.]
POST CONCRETING

To
Method of Pouring & Vibration Acceptable To Improve Arrangement for Curing / Pon Acceptable
Improve
To
Stability of Formwork after Pour Acceptable To Improve Others [Specify] Acceptable
Improve
To
Line, Level & finishing Acceptable To Improve Acceptable
Improve
Sch. date for formwork removal with supports Actual Date o
Sch. date for form work removal entirely Actual Date o
To
Line, Level & finishing of Concrete surface Acceptable To Rectify Acceptable
Rectify
DESHUTTER

To
Removal of Battens, Maskin tape etc. Acceptable To Rectify Acceptable
Rectify
Action Required if any:- Remarks: Rectifications done as specified:
Dry finish
Wet finish
Grouting Task End Date:

Epoxy Treatment
Contractor: Resident Architect

TVH Studio Cria AWHO


CHECKLIST

PLUMBING WORKS
Checklist No. Date:
Name of Work: Drgs Ref:
Employer:
Contract No.:
Contractor:
Item Dscrptn: Inspection Requested by:

1ST INSPECTION 2ND INSPECTION


Req. on: Req. on:
Location Section Level By.: By.: Quantity
Date: Date:
Time: Time:
Points to Check O Action Req. O Action Req. REMARKS
P P

1. Dimensions, level & SIZE


2. No of inlets
3. Inlet & outlet level
MANHOLE

4. Inlet & out let pipe size


5. Manhole No
5. Man hole Cover Hevey /Med/Light
6 . Man hole for soil waste/ Rain water
7 Cleanliness
1. PIPE SIZE (300-250-200-160-110 )
2. Type of Pipe swr A/B Agri
2. Slop
PIPE

3 .Inlet Manhole PIPE Level


4. Out let Man hole Pipe Level
5. Intervel Between Two Man hole

1. Gully drap no
2. Drap level
Gully drap

3. No of inlet pipe
4. Out let collection to Man hole No
5. Shaft No
CLEARANC
E

Clearance for Concreting Engineer Contractor Clearance Date


Contractor: Client

TVH Studio Cria

You might also like