GOVERNMENT OF SARAWAK

JABATAN KERJA RAYA


_______________________________________

PERFORMANCE BASED CONTRACT FOR THE LONG TERM


MANAGEMENT AND MAINTENANCE OF STATE ROADS [JALANRAYA
NEGERI (JRN)] IN SARAWAK - PACKAGE 4 (MIRI DIVISION)

(CONTRACT NO: PWD/HO/B130/2019)

PAVEMENT REHABILITATION WORK AT Q21-3 & Q21-4 , BELURU LONG


TERU TRUNK ROAD.

ENDAYA CONSTRUCTION SDN BHD, REGIONAL OFFICE


Lot 1934, 1st – 3rd Floor, Marina Square, Phase 2,
98000 Miri Sarawak.
ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

TABLE OF CONTENTS
1.0 LOCALITY PLAN
2.0 PROBLEM STATEMENT
3.0 ACTION TAKEN
4.0 PROPOSED SOLUTION
5.0 ATTACHMENT
ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

1.0 LOCALITY PLAN

Approximately
KM36+200 (from
SK Bakong, Beluru
toward Long Lama
Town)

KM0+500 – KM12+200,
location to propose remedial
work.

Bakong Bridge,
KM 18+191
ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

2.0 PROBLEM STATEMENT

a) Pavement undulation with several distress (delamination, corrugations, shoving,


crescent shape cracks, potholes, lane to shoulder drop-off, etc).
b) The affected pavement carriageway received a massive of vehicle loading such as
materials transportation activity from Long Lama Quarry, and construction of
resettlement new township.

3.0 ACTION TAKEN

a) Signages of “awas kurangkan laju” installed


b) Cold patch activity under activity 1012 had been carried out continuously.
c) Activity 1011, potholes repair also have been carried out repeatedly.
d) Activity 3018 and 3019 Shallow Patching and Deep patching scheduled accordingly
for temporary repair.

4.0 PROPOSED SOLUTION


a) To proposed remedial work.
ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

KM 0+500 (RHS) KM 0+600 (BOTH SIDE)

KM 1+000 (LHS) KM 1+600 (RHS)

KM 1+650 (LHS) KM 1+700 (BOTH SIDE)

5.0 ATTACHMENTS Q21-3,(KM 0+500 – KM2+700)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

Q21-3 (KM8+200 – KM9+800)

KM8+200 (LHS) KM8+300 (RHS)

KM9+000 (LHS) KM9+200 (RHS)

KM9+500 (BOTH SIDE) KM9+800 (BOTH SIDE)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

Q21-3 (KM11+600 – KM12+200)

KM11+600 (BOTH SIDE) KM11+700(RHS)

KM11+750 (BOTH SIDE) KM11+800 (RHS)

KM11+900 (RHS) KM12+150 (RHS)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

Q21-4 (KM2+800 – KM8+700)

KM2+800 (RHS) KM3+500 (RHS)

KM3+900 (RHS) KM4+100 (CENTER)

KM4+200 (CENTER) KM4+500 (BOTH SIDE)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

Q21-4 (KM5+500 – KM6+700)

KM5+500 (BOTH SIDE) KM6+000 (RHS)

KM6+100 (BOTH SIDE) KM6+200 (RHS)

KM6+300 (RHS) KM6+400 (RHS)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

Q21-4 (KM7+200 – KM8+700)

KM7+200 (RHS) KM7+400 (BOTH SIDE)

KM7+500 (RHS) KM7+800 (RHS)

KM8+000 (BOTH SIDE) KM8+300 (BOTH SIDE)


ENDAYA CONSTRUCTION SDN BHD (049693-V)
Defect Report

KM8+500 (BOTH SIDE) KM8+700 (RHS)