METHOD OF STATEMENT : INSTALLATION OF PERIMETER HOARDING

1. OBJECTIVE

To outline the sequence of activities, method and resources needed for the
operation of erecting temporary hoarding.

2. SCOPE

The work shall include all labour, material, equipment, safety requirement and
services necessary for the execution erecting temporary hoarding.

3. WORK SEQUENCE FLOW

                _to attach drawing_

4. MATERIAL

           Material to be used is as follows:-


                4.1          50 x 50 x 2.0mm thick SHS M.S Posts
                4.2          50 x 25 x 1.2mm thick RHS M.S Nogging
                4.2          50 x 25 x 1.6mm thick SHS M.S Braces
                4.3          0.3mm thick metal decking
                4.4          Nail / Rivet
                4.5          Cement
                4.6          Sand
                4.7          Water

5. EQUIPMENTS & MACHINERIES REQUIRED

           Equipment and machineries to be used as follows :-


5.1          Minimum: One (1) number of JCB Backhoe (if required)
                5.2          Minimum: One (1) set of hand excavating equipment
                5.3          Minimum: One (1) set of steel work equipment
                5.4          Minimum: One (1) set of water levelling
                5.5          Minimum: One (1) number of spirit level

6. SITE PREPARATION WORK

                6.1          Setting out boundaries of ground in the proposed perimeter.

1
7. METHOD OF WORK

7.1          Determine the location of the temporary hoarding will be


established with confirmation from the surveyor.
7.2          After getting confirmation, using the given point and mark the
main pole as per alignment shown in the drawings
(Appendix A). Center to center of the main column is3000mm.
7.3          Preparation of the main pillars started by using hand digging to
the depth 400mm.
7.4          Pole-sized 50 x 50 x 1.6mm thk SHS M.S constructed using
equipment such as spirit level, water level, and tape
measure. Two workers used to establish the main pillars.
7.5          Pillars need to ensure accurate position along the fenceline at 
3.0m (panel width) intervals and make sure the base are sitting 
on an even level surface.
7.6          Erect the remaining pillars along the line as note previously until
the hoarding line is complete.
7.7          50x25x1.2mm thk nogging need to install three (3) lines to
support metal deck panels.
7.8          Metal deck panels will be installed with the frame hoarding as per
Appendix A (spacing 4” for every panels).
7.9          This work will be repeated until completion.
7.10        Entrance gate will be erected at remaining area (refer item no.3)
with support at both side (left and right) using welded angles.

 8. QUALITY ISSUES

Boundaries demarcation required to ensure no double handling or trespassing


to others people land.
·         View inspection required during the process of erection hoarding.
·         Regular inspection to be carried out by weekly basis to ensure the
hoarding in good condition.

9. SAFETY ISSUES

·         Safety helmets and safety footwear should always be worn.


·         All soft spots or holes shall be identified and barricade if necessary.
·         The site shall be kept clear of unnecessary obstruction.
·         First aid kit boxes will be provided at site office.
·         During raining, no erection hoarding activities are allowed to work.

10. ENVIRONMENTAL ISSUES

·         All workers shall ensure that tools and machinery are in a good
condition to avoid any oil leakage that could harm to environment.